Dittmore-Freimuth Corp. v. The United States

390 F.2d 664, 182 Ct. Cl. 507, 1968 U.S. Ct. Cl. LEXIS 54
CourtUnited States Court of Claims
DecidedFebruary 16, 1968
Docket182-64
StatusPublished
Cited by45 cases

This text of 390 F.2d 664 (Dittmore-Freimuth Corp. v. The United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Dittmore-Freimuth Corp. v. The United States, 390 F.2d 664, 182 Ct. Cl. 507, 1968 U.S. Ct. Cl. LEXIS 54 (cc 1968).

Opinion

OPINION

SKELTON, Judge.

Plaintiff, by this action, seeks an equitable adjustment for additional costs it incurred in the performance of four contracts 1 entered into with the defendant for the manufacture of rocket launcher adapters 2 and spare parts. The adapter was designed for attachment to a rocket launcher (hereinafter referred to as the combo) in order to adapt the combo for the launching of sub-caliber rockets from naval aircraft.

More particularly, plaintiff alleges that the Government did in fact and in law authorize or compel changes in the applicable drawings and performance requirements, but has failed to compensate plaintiff for the resultant increased costs as required by the contract. In this connection, plaintiff also seeks reimbursement for extensive delays in the delivery of the adapters during which time its plant and personnel were idle.

Although this assertion is the foundation for plaintiff’s grievance, it also advances claims for the costs expended (1) in obtaining the most current Government drawings, (2) in conducting tests at a Government-designated facility rather than at the contractor’s plant, and (3) in rebutting the contracting officer’s initial decision including, those costs for preparing and conducting the present litigation. For convenience, these claims will be considered in separately numbered portions of the opinion after the recitation of the facts.

Plaintiff alleged unsuccessfully before both the contracting officer and the Armed Services Board of Contract Appeals (hereinafter referred to as ASBCA or Board) that it was entitled to an equitable adjustment under the Changes Article of the contracts for extra costs, the bulk of which involved retooling expenses allegedly incurred as a result of performance tests which plaintiff asserts were in excess of the requirements of the specifications. In its opinion, the *668 ASBCA found that the tests were authorized by and in accordance with the contracts, that the adapters could have been successfully manufactured under the existing plans and specifications and that the Government did not directly or indirectly change the contracts. 3

On June 15, 1964, plaintiff filed its petition in this court. Trial Commissioner Richard Arens, to whom this case was referred pursuant to order of the court under Rule 57(a), also concluded that the plaintiff’s claims must be denied. He, however, did not consider the merits of the case because he found that the plaintiff did not give notice to the Government as required by the contract and because the extra work was not authorized by the defendant. While lack of notice or protest is generally a good defense to such an action as this, there is an old line of cases holding that this defense is not well taken where the contracting officer and the Appeals Board considered the claim on its merits without any point being made as to lack of notice or protest. E. g., Pox Valley Engineering, Inc. v. United States, 151 Ct. Cl. 228, 237-238 (1960). In all fairness to the commissioner, however, and although this issue was technically raised before him, none of the cases supporting this rule were brought to his attention by either party. While we have derived much benefit from his factual presentation, the merits of the case must be considered by us.

The only evidence before the court is the administrative record which was received in evidence, following which plaintiff filed its brief and a detailed statement in the nature of an assignment of errors allegedly committed by the Board. 4

The plaintiff attacks the Board’s decision as arbitrary, capricious, unsupported by substantial evidence, and as an incorrect interpretation of the contracts between the parties.

As will be more fully shown, resolution of the controlling issues turns both on questions of fact and questions of law. It becomes our task, therefore, to ascertain whether or not the Board’s factual determinations meet the standards contained in the Wunderlich Act, 68 Stat. 81, 41 U.S.C. § 321 (1964), and whether or not its interpretation of the contract language is correct.

Only a thorough investigation of the facts concerning this complex subject matter will permit the complicated relationship between the parties, upon which this controversy turns, to be properly understood. The summary of the material facts set out in this opinion is based upon the administrative record and the Board’s decision. In those instances where we relate facts and the Board has made no corresponding factual determination, our analysis is supported either by uncontradicted evidence found in the administrative record, or by evidence of such a nature that as a matter of law the Board could have made only one finding of fact. Preliminarily we state that from the standpoint of the constructive change order contention which reflects the main thrust of the plaintiff’s petition, the ASBCA determinations were not factually or legally in error. The facts underlying the present dispute are as follows:

In March 1953, the invitations for bids (IFB) on contract No. N383s-89240 for the manufacture of 15,110 Rocket Launcher Adapters were issued by the defendant through the Aviation Supply Office, Department of the Navy. The bid package only provided that the item should conform to Bureau of Aeronautics Drawing BUA-49A219H1, dated October *669 26, 1949. Although the defendant inadvertently neglected to incorporate by reference specification MIL-A-6760A, dated July 20, 1951, which by its terms referenced restricted specification SR-142, these test specifications were enclosed in the package transmitted to the contractors.

The plaintiff, Dittmore-Freimuth Corporation, with its principal office in Milwaukee, Wisconsin, filed its bid under date of March 31, 1953, after considering the applicability of both omitted test specifications and was the low bidder.

On or about April 1,1953, Mr. Maurice Rudin, Supervisory Procurement Agent of the Navy Aviation Supply Office, (ASO) in Philadelphia, Pennsylvania, telephoned plaintiff and the bid was confirmed. Then, sometime during the middle of April 1953, Mr. Rudin indicated to the plaintiff that he intended to cancel the IFB since he considered that the inclusion of specification MIL-A-6760A was a necessary and integral part of the contract, and its omission rendered the invitation for bid incomplete. The record indicates that Mr. Rudin’s action was precipitated by a letter to him dated April 13, 1953, from the Firecraft Corporation, 5 which had manufactured the adapter on a prior contract and *670 which had been a high bidder on the contract herein involved. The letter, which is set out in footnote 5, supra, in pertinent part, related to the fact that Firecraft computed its bid on the basis of all specifications and modifications since it had recently completed the manufacture of such an item.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Rose v. Air Force
Federal Circuit, 2025
Sweeney v. Department of Homeland Security
248 F. App'x 179 (Federal Circuit, 2007)
Curtis v. Department of Treasury
97 F. App'x 296 (Federal Circuit, 2004)
Alexander v. Office of Personnel Management
21 F. App'x 919 (Federal Circuit, 2001)
Drellie Gibson, III v. Department of Veterans Affairs
160 F.3d 722 (Federal Circuit, 1998)
Joseph Sousa v. Department of the Army
108 F.3d 1391 (Federal Circuit, 1997)
Russell N. Kell v. Department of Veterans Affairs
101 F.3d 716 (Federal Circuit, 1996)
Samuel L. Lovett, Sr. v. United States Postal Service
48 F.3d 1237 (Federal Circuit, 1995)
June P. Thomas v. Office of Personnel Management
996 F.2d 317 (Federal Circuit, 1993)
Toney F. Edwards v. Department of the Army
983 F.2d 1087 (Federal Circuit, 1992)
Elmer O. Walcott v. United States Postal Service
980 F.2d 744 (Federal Circuit, 1992)
Pamela F. Smythe-Coats v. Bureau of Prisons
945 F.2d 416 (Federal Circuit, 1991)
Underground Construction Co. v. United States
35 Cont. Cas. Fed. 75,604 (Court of Claims, 1988)
Anthony E. Mazza v. U.S. Postal Inspection Service
829 F.2d 42 (Federal Circuit, 1987)
Martin J. Simko Construction, Inc. v. United States
33 Cont. Cas. Fed. 74,888 (Court of Claims, 1986)
Riley E. Jackson v. Veterans Administration
768 F.2d 1325 (Federal Circuit, 1985)
John G. Hagmeyer v. Department of the Treasury
757 F.2d 1281 (Federal Circuit, 1985)
Peterson-Sharpe Engineering Corp. v. United States
32 Cont. Cas. Fed. 72,873 (Court of Claims, 1984)

Cite This Page — Counsel Stack

Bluebook (online)
390 F.2d 664, 182 Ct. Cl. 507, 1968 U.S. Ct. Cl. LEXIS 54, Counsel Stack Legal Research, https://law.counselstack.com/opinion/dittmore-freimuth-corp-v-the-united-states-cc-1968.