River Construction Corp. v. United States

159 Ct. Cl. 254, 1962 U.S. Ct. Cl. LEXIS 153, 1962 WL 9302
CourtUnited States Court of Claims
DecidedNovember 7, 1962
DocketNo. 13-56
StatusPublished
Cited by71 cases

This text of 159 Ct. Cl. 254 (River Construction Corp. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
River Construction Corp. v. United States, 159 Ct. Cl. 254, 1962 U.S. Ct. Cl. LEXIS 153, 1962 WL 9302 (cc 1962).

Opinion

Per Curiam :

Plaintiff, on behalf of itself and its subcon-

tractor, Preload Central Corporation, seeks an equitable adjustment for alleged changes in plaintiff’s contract to construct a concrete water pipeline and damages for alleged unreasonable delays by the Government, amounting to a suspension of work in performance of the contract. The posture of the case before the court is that at the conclusion of plaintiff’s case-in-chief defendant moved to dismiss under Pule 49(c) on the ground that upon the facts and the law plaintiff had not shown a right to recover. The Trial Commissioner, Marion T. Bennett, allowed defendant’s motion, subject to approval by the court. For reasons which appear later, the court affirms that ruling. We, therefore, adopt the Commissioner’s findings of fact and his opinion with minor modification, and the same will be set forth below as a basis for the judgment of the court.

There are several questions in this case but the threshold one is whether defendant’s motion to dismiss was timely made. The motion was made after defendant had introduced three exhibits used by it in cross-examination. We [258]*258are satisfied that defendant’s motion was timely within the meaning of Buie 49 (c), which is based on Buie 41 (b) of the Federal Buies of Civil Procedure, for the motion was “promptly” made before defendant opened its case-in-chief and after plaintiff’s case-in-chief was closed. It would be unreasonable to compel a defendant to forego proper cross-examination, as plaintiff urges, or risk forfeiture of its right to move to dismiss at the close of plaintiff’s case. The Commissioner’s views to the same effect have been stricken from his opinion to avoid a repetition of what we have restated in principle.

The basic question here is whether the administrative decision of the Corps of Engineers Claims and Appeals Board, adverse to- plaintiff, is final or whether it is illegal because “fraudulent, capricious or arbitrary or so grossly erroneous as necessarily to imply bad faith, or is not supported by substantial evidence,” as provided by the so-called “Wunderlich Act,” chapter 199, 68 Stat. 81,41 U.S.C. §§ 321-322 (1958).

The questions decided by the Board were essentially questions of fact and thus within its jurisdiction. Detailed findings of fact have been made as to what the Board considered. The Board’s decision was based on substantial evidence and was not in violation of any of the admonitions of the Wun-derlich Act. It is not necessary to reiterate the details set forth in the findings and in the opinion of the Commissioner. Suffice to say that it was plaintiff’s claim before the Board that certain tests which its subcontractor was required by the defendant to perform on the concrete water pipe required the subcontractor to overdesign the pipe to meet the tests and thus there was a change meriting an equitable adjustment and, further, that alleged delay of defendant in making certain alleged changes amounted to a suspension of work entitling it to increased costs incurred during the delay period. Upon the record plaintiff made before the Board, it was administratively determined that plaintiff and its subcontractor had agreed to perform the tests, that they did not amount to changes, and that the Government had acted expeditiously in resolving the disputes about the earth loads to be borne by the pipe and in making a change for which [259]*259plaintiff did receive an increase in contract price and a time extension. Plaintiff did not meet its burden of proof in supporting its allegations now repeated before the court. For this reason, if for none other, plaintiff’s case must fall and the Board’s decision must stand. This is so even considering plaintiff’s case before the Board in its most favorable light and giving the benefit of any doubt to plaintiff.

If more were needed to invalidate plaintiff’s claim, however, it could be found in two collateral issues wherein plaintiff has failed in the trial in the court. First, plaintiff has not proved its damages by merely seeking the difference between actual verified costs and payments made to it under the contract by defendant. The costs have not been shown to be defendant’s fault. No evidence has been offered to show it other than the record before the Board. Plaintiff offered only two witnesses, one an expert on prestressed concrete pipe who gave cumulative testimony about the tests and the other who testified as to how much it had cost plaintiff and its subcontractor to perform. Second, plaintiff offered no evidence to the court to undercut the findings and conclusions of the Board. Plaintiff offered only the evidence of the two witnesses mentioned and the administrative record considered by the Board, and rested. Having concluded upon examination of that administrative record that it fully supports the Board’s decision and nothing having been offered of a new nature to show otherwise, as plaintiff had opportunity to do, we can only uphold the Board and dismiss the complaint under Article 15 of the contract and the Wunderlich Act. The authorities are gathered in the Commissioner’s opinion which follows.

OPINION OP THE COMMISSIONER

Late in 1948 the plaintiff, River Construction Corporation, hereinafter referred to as the plaintiff, entered into a contract with the defendant, acting through the Army Corps of Engineers, for the construction of a 54-inch concrete water pipeline about 5,100 feet long at Chain of Rocks in Illinois, near St. Louis, Missouri. Preload Central Corporation, hereinafter referred to as Preload, submitted a proposal to [260]*260plaintiff for the manufacture and supplying of prestressed concrete pipe for the project. Preload’s proposal, including detailed plans and specifications, was submitted to the defendant, and plaintiff’s bid, as accepted by the defendant, contemplated the use of Preload’s pipe.

The work under the contract was performed by plaintiff and Preload. Preload’s costs incurred in performing the contract were in excess of its estimates and bid price. Pre-load claims that its costs were increased by actions of the defendant in requiring certain tests to be made, thereby increasing the design requirements for the pipe. Preload asserts that the defendant, in effect, ordered changes in the contract, but has failed to compensate Preload for the resultant increased costs, as required by the contract. The plaintiff also claims that its costs were increased by delays caused by defendant. The claims for increased costs were presented to and denied by the contracting officer, and appeal was made to the Corps of Engineers Claims and Appeals Board, which denied all of the claims that are here asserted.

At the outset, the issue before the court should be clearly defined. The plaintiff has presented its case as though the issue were whether in fact the defendant required Preload to do work which was in excess of the contract requirements.

Under the Wunderlich Act, ch. 199, 68 Stat. 81, 41 U.S.C. §§321-322 (1958), where a contract entered into with the United States as a party provides that the decision of a representative of the head of a Government agency, upon questions of fact, shall be final and conclusive, such decision shall be final and conclusive “unless the same is fradulent [sic] or capricious or arbitrary or so grossly erroneous as necessarily to imply bad faith, or is not supported by substantial evidence.”

Free access — add to your briefcase to read the full text and ask questions with AI

Related

BAE Systems San Francisco Ship Repair
Armed Services Board of Contract Appeals, 2016
Spodek v. United States
73 Fed. Cl. 1 (Federal Claims, 2006)
Orlosky Inc. v. United States
68 Fed. Cl. 296 (Federal Claims, 2005)
CEMS, Inc. v. United States
59 Fed. Cl. 168 (Federal Claims, 2003)
Cavalier Clothes, Inc. v. United States
51 Fed. Cl. 399 (Federal Claims, 2001)
Northrop Grumman Corp. v. United States
47 Fed. Cl. 20 (Federal Claims, 2000)
Datalect Computer Services, Ltd. v. United States
42 Cont. Cas. Fed. 77,379 (Federal Claims, 1998)
Louis Leustek & Sons, Inc. v. United States
41 Fed. Cl. 657 (Federal Claims, 1998)
L & A Jackson Enterprises v. United States
41 Cont. Cas. Fed. 77,117 (Federal Claims, 1997)
Celeron Gathering Corp. v. United States
40 Cont. Cas. Fed. 76,888 (Federal Claims, 1996)
Ralph L. Jones Co. v. United States
33 Fed. Cl. 327 (Federal Claims, 1995)
Miller Elevator Co. v. United States
39 Cont. Cas. Fed. 76,635 (Federal Claims, 1994)
Commercial Contractors, Inc. v. United States
39 Cont. Cas. Fed. 76,582 (Federal Claims, 1993)
Mega Construction Co. v. United States
39 Cont. Cas. Fed. 76,564 (Federal Claims, 1993)
American Line Builders, Inc. v. United States
38 Cont. Cas. Fed. 76,406 (Court of Claims, 1992)
Romala Corp. v. United States
36 Cont. Cas. Fed. 75,831 (Court of Claims, 1990)
G & H Machinery Co. v. United States
35 Cont. Cas. Fed. 75,638 (Court of Claims, 1989)
Avedon Corp. v. United States
35 Cont. Cas. Fed. 75,577 (Court of Claims, 1988)

Cite This Page — Counsel Stack

Bluebook (online)
159 Ct. Cl. 254, 1962 U.S. Ct. Cl. LEXIS 153, 1962 WL 9302, Counsel Stack Legal Research, https://law.counselstack.com/opinion/river-construction-corp-v-united-states-cc-1962.