P.L.S. Coat & Suit Corp. v. United States

180 F. Supp. 400, 148 Ct. Cl. 296, 1960 U.S. Ct. Cl. LEXIS 52
CourtUnited States Court of Claims
DecidedJanuary 20, 1960
Docket213-56, 513-56
StatusPublished
Cited by19 cases

This text of 180 F. Supp. 400 (P.L.S. Coat & Suit Corp. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
P.L.S. Coat & Suit Corp. v. United States, 180 F. Supp. 400, 148 Ct. Cl. 296, 1960 U.S. Ct. Cl. LEXIS 52 (cc 1960).

Opinion

PER CURIAM.

In these cases plaintiffs seek to recover extra costs alleged to have been incurred in manufacturing raincoats under contracts with the Department of the Navy. Each plaintiff had two contracts under which claims have been made. Plaintiffs allege that their costs were increased because the raincoat material which was furnished by the Government was not in conformity with contract specifications and was otherwise defective.

Defendant has moved for summary judgments dismissing plaintiffs’ petitions on the grounds (1) that plaintiffs’ claims are barred because of their failure to comply with contract provisions relative to replacement of defective material, failure to obey the contracting officer’s written instructions regarding such replacement, and failure to follow the disputes and appeals provision of the contracts; (2) that the decisions of the Armed Services Board of Contract Appeals (ASBCA) on questions of fact relating to the quality of the Government-furnished cloth which decisions were adverse to plaintiffs, should be accorded finality here; and (3) that irrespective of the aforementioned decisions, summary judgments should be granted defendant on the basis of independent documentary evidence now before the court in the form of affidavits and exhibits in support of its motions.

*402 Plaintiffs urge recovery on two grounds: First, that defendant breached the contracts in its failure to furnish non-defective cloth, or second that under applicable contract provisions plaintiff is •entitled to an equitable adjustment of the contract prices because of the defective cloth supplied.

With respect to one of the contracts in the PLS case, No. DA30-352-TAP-135, xecovery must be denied on the grounds that plaintiff itself has failed to conform to the contract provisions. The applicable provisions are as follows: 1

“Substitution of Government Furnished Property
“The Government reserves the right to substitute material in lieu of the material listed herein as ‘Government Furnished Property’, and in the event such substitution affects the cost of performance of this contract, it shall be treated as coming ■within the terms of Section 2 ■(changes) of the General Provisions hereof, and an equitable adjustment in price shall be effected in accordance with the provisions of that Section.
******

«Clause “A”-—Government-furnished Property

“(a) The Government shall deliver to the Contractor, for use in ■connection with and under the terms ■of this contract, the property which the schedule or the specifications ¡state the Government will furnish (hereinafter referred to as “Government-furnished Property”). The delivery or performance dates for the ■supplies or services to be furnished by the Contractor under this contract are based upon the expectation that Government-furnished property •of a type suitable for use will be delivered to the Contractor at the times stated in the schedule or if not so stated in sufficient time to enable the Contractor to meet such delivery or performance dates. In the event that Government-furnished property is not delivered to the Contractor by such time or times, the Contracting Officer shall, if requested by the Contractor, make a determination of the delay occasioned the Contractor thereby, and shall grant to the Contractor a reasonable extension of time in respect of such delivery or performance dates. The Government shall not be liable to the Contractor for damages or loss of profit by reason of any delay in delivery of or failure to deliver any or all of the Government-furnished property, except that in case of such delay or failure, upon the written request of the Contractor, an equitable adjustment shall be made in the delivery or performance dates, or price, or both, and in any other contractual provision affected thereby, in accordance with the procedures provided for in the clause of this contract entitled ‘Changes’.
******
“2. Changes
“The Contracting Officer may at any time, by a written order, and without notice to the sureties, make changes, within the general scope of this contract, in any one or more of the following: (i) drawings, designs, or specifications, where the supplies to be furnished are to be specially manufactured for the Government in accordance therewith; (ii) method of shipment or packing; and (iii) place of delivery. If any such change causes an increase or decrease in the cost of, or the time required for, performance of this contract, an equitable adjustment shall be made in the contract price or delivery schedule, or both, and the contract shall be modified in writing accordingly. Any claim by the Contractor for adjustment un *403 der this clause must be asserted within 30 days from the date of receipt by the Contractor of the notification of change: Provided, however, That the Contracting Officer, if he decides that the facts justify such action, may receive and act upon any such claim asserted at any time prior to final payment under this contract. Failure to agree to any adjustment shall be a dispute concerning a question of fact within the meaning of the clause of this contract entitled ‘Disputes.’ However, nothing in this clause shall excuse the Contractor from proceeding with the contract as changed.
* * * * * *
“12. Disputes
“Except as otherwise provided in this contract, any dispute concerning a question of fact arising under this contract which is not disposed of by agreement shall be decided by the Contracting Officer, who shall reduce his decision to writing and mail or otherwise furnish a copy thereof to the Contractor. Within 30 days from the date of receipt of such copy, the Contractor may appeal by mailing or otherwise furnishing to the Contracting Officer a written appeal addressed to the Secretary, and the decision of the Secretary or his duly authorized representative for the hearing of such appeals shall be final and conclusive: Provided, That if no such appeal is taken, the decision of the Contracting Officer shall be final and conclusive. * * *»

Under these provisions the Government upon proper notice was to have the opportunity to replace defective material, and/or provide for an equitable adjustment of the contract price. The need for a prompt request to the contracting officer is quite obvious. Both provisions make reference to the Changes provision in the contract which provides that any claim by the contractor for adjustment under this clause is to be made within 30 days from the date of receipt of the notification of change by the contractor. However, the Changes provision further states that the contracting officer if he decides the facts warrant it may receive and act upon any such claim at any time prior to final payment. It also provides that failure to agree shall constitute a dispute concerning a question of fact within the Disputes clause of the contract.

Deliveries under this contract were completed May 15, 1953, and final payment was made June 18,1953. Plaintiff’s claim directed to the contracting officer was made on January 12, 1954, some seven months after final payment.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Roberts Logging Co. v. Yurich
482 F. Supp. 1231 (E.D. Wisconsin, 1980)
Timber Access Industries Co. v. United States
553 F.2d 1250 (Court of Claims, 1977)
N. Fiorito Co. v. United States
180 Ct. Cl. 1285 (Court of Claims, 1967)
Moran Bros., Inc. v. The United States
346 F.2d 590 (Court of Claims, 1965)
Anthony Grace & Sons, Inc. v. The United States
345 F.2d 808 (Court of Claims, 1965)
Anthony P. Miller, Inc. v. United States
161 Ct. Cl. 455 (Court of Claims, 1963)
Robert L. Guyler v. The United States
314 F.2d 506 (Court of Claims, 1963)
River Construction Corp. v. United States
159 Ct. Cl. 254 (Court of Claims, 1962)
Keco Industries, Inc. v. United States
157 Ct. Cl. 691 (Court of Claims, 1962)
Union Painting Co. v. United States
194 F. Supp. 803 (D. Alaska, 1961)
Lester Bros. v. United States
151 Ct. Cl. 536 (Court of Claims, 1960)
United States v. Hamden Co-Operative Creamery Co.
185 F. Supp. 541 (E.D. New York, 1960)

Cite This Page — Counsel Stack

Bluebook (online)
180 F. Supp. 400, 148 Ct. Cl. 296, 1960 U.S. Ct. Cl. LEXIS 52, Counsel Stack Legal Research, https://law.counselstack.com/opinion/pls-coat-suit-corp-v-united-states-cc-1960.