B-W Construction Co. v. United States

97 Ct. Cl. 92, 1942 U.S. Ct. Cl. LEXIS 35, 1942 WL 4350
CourtUnited States Court of Claims
DecidedOctober 5, 1942
DocketNo. 43925
StatusPublished
Cited by9 cases

This text of 97 Ct. Cl. 92 (B-W Construction Co. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
B-W Construction Co. v. United States, 97 Ct. Cl. 92, 1942 U.S. Ct. Cl. LEXIS 35, 1942 WL 4350 (cc 1942).

Opinion

Whitaker, Judge,

delivered the opinion of the court:

On September 7, 1932, plaintiff entered into a contract with the defendant for the erection of what was denominated the Male Receiving Building at St. Elizabeths Hospital, Washington, D. C.

In this suit plaintiff seeks to recover: (1) the sum of $21,482.00, the cost of structural concrete and reinforcing steel which it alleges it was required to use in addition to that required by the contract, as amended by change order No. 1; (2) the sum of $11,227.69 which it alleges was the amount of damages suffered by it on account of delays caused by the defendant; and (3) for the sum of $1,225.00, liquidated damages deducted at the time of final settlement.

Cost of additional structural concrete and reinforcing steel

On the day following the signing of the contract plaintiff suggested a change in the plans for the building which would eliminate many of the columns in the corridors and in the dining room of the-building. This was to be done by the use of a two-way joist system, instead of the one-way system prescribed by the contract.

The defendant was unfamiliar with the two-way joist system but was interested in eliminating the columns and agreed to discuss the proposed change with plaintiff. These discussions resulted in the issuance of a change order on October 11,. 1932, which was accepted by plaintiff, providing for the elimination of “certain columns to be designated when and if the contractor submits acceptable plans.and methods to accomplish' the desired result.” It was stipulated in this change order that “the additional cost, if any, [was] not to exceed $8,600.00.”

Plaintiff proceeded to prepare proposed plans. A number of conferences were had between the parties which finally-resulted in the approval on November 29, 1932 of the plans, submitted by the plaintiff. In plaintiff’s letter transmitting-these plans it said: [111]*111It was a provision of Change Order No. 1 that the additional cost was not to exceed $8,600.00. This amount has been paid the plaintiff.

[110]*110We will greatly appreciate anything you can do to* expedite formal approval of these drawings in accordance with the provisions of Change Order No. 1.

[111]*111That plaintiff well understood that the amount to be paid it for this work was not to exceed $8,600 is shown by its letter of December 15, 1932, in which it requested, “that the cost incident to Change No. 1 be fixed at Eighty-six Hundred Dollars ($8,600.00).”

Again on January 3, 1933 it wrote the contracting officer itemizing the cost going to make up the $8,600; and finally on January 11, 1933, the contracting officer wrote plaintiff, “you are advised the additional cost that you estimate of $8,600.00 for this additional work and materials to be placed is approved.”

It is true that the plaintiff estimated that 5,692 cubic yards of reinforced concrete and 499.3 tons of reinforcing steel would be necessary to do the work, and that actually 5,752 cubic yards of reinforced concrete were actually used, but there is no showing that anything more was required of the plaintiff than was called for by Change Order No. 1, as supplemented by the plans drawn by the plaintiff and approved by the defendant.

Evidently plaintiff did not think that anything more was being required of it, because while the work was going on it made no such claim, it made no request for additional compensation, nor for any order in writing to do the additional work, which it was required by the contract to make if it was to claim additional compensation for doing any extra work. Plumley v. United States, 226 U. S. 545; Griffiths v. United States. 74 C. Cls. 245. It made no claim for extra compensation on this account until July 10, 1934, about two weeks before the entire building was completed.

We are clearly of the opinion that the plaintiff is not entitled to recover on this item.

Damages due to delays alleged to ha/oe been ccmsed by the defendant

The contracting officer allowed plaintiff an extension of time of 123 days on account of delays which he held were [112]*112caused by the defendant. Plaintiff claims damages for these delays.

The first item is a delay of 52 days alleged to have been caused by the defendant in failing to approve promptly the plans for a redesign of the building to eliminate certain columns, discussed above.

As stated,' plaintiff had suggested this change in the plans. This suggestion was approved by the defendant, subject to working out satisfactory plans. These plans were to be prepared by the plaintiff. It originally prepared the plans in its Chicago office and mailed them to^ Saint Elizabeths Hospital. Saint Elizabeths Hospital had secured the services of the Veterans’ Administration to prepare the plans and otherwise assist it in the construction of this building. It referred plaintiff’s plans to them for checking and approval. Correspondence back and forth ensued; but plaintiff and defendant soon found that the matter could not be handled at long distance, and plaintiff’s representatives came from Chicago to Washington to go over the plans in person wdth defendant’s engineers. A room in the Veterans’ Administration building was put at their disposal and lengthy conferences between plaintiff and defendant were held daily. The proof shows that the matter was handled expeditiously by both parties. The commissioner has so found, and plaintiff has taken no exception to this finding. The testimony leaves no room for doubt that this is so.

Defendant’s representative who was immediately in charge of checking these plans was a man by the name of Kafter, who had been borrowed by the Veterans’ Administration from the Bureau of Yards and Docks for this purpose. He testified time and again that he and his associates did everything they could to expedite the work. He says they worked overtime practically every day, that they worked nights, that they worked on Thanksgiving day, Sundays, and Saturday afternoons.

Sholtes, who was the architectural engineer for Saint Elizabeths Hospital in charge of the architectural work, says there, was no delay whatever, but that everyone did all they could to expedite getting out the plans.

[113]*113Kelly, who was the superintendent of construction at Saint Elizabeths Hospital, testified:

The matter was handled with unusual expediency [sic] because the Hospital was just as anxious to go ahead with the revision on a full-speed basis as the contractor could have been.

Sanger, the contracting officer, says that he gave the matter his personal attention so that it could be expedited. He said that it was he who suggested to plaintiff’s representatives that they would make available to them a room at the Veterans’ Administration where their representatives could work in close conjunction with representatives of the Government, in order that the matter might be expedited.

The plaintiff offers no testimony to refute this but relies alone upon the finding of the head of the department that the delay of 52 days “resulted from acts of the Government.” Its position is that this finding of the head of the department is final and conclusive, and entitles it to damages.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

S&E Contractors, Inc. v. United States
406 U.S. 1 (Supreme Court, 1972)
WRB Corp. v. United States
183 Ct. Cl. 409 (Court of Claims, 1968)
Vogt Bros. Mfg. Co. v. United States
160 Ct. Cl. 687 (Court of Claims, 1963)
River Construction Corp. v. United States
159 Ct. Cl. 254 (Court of Claims, 1962)
Wunderlich v. United States
117 Ct. Cl. 92 (Court of Claims, 1950)
Pfotzer v. United States
77 F. Supp. 390 (Court of Claims, 1948)
James Stewart & Co. v. United States
63 F. Supp. 653 (Court of Claims, 1946)
American Transformer Co. v. United States
63 F. Supp. 194 (Court of Claims, 1945)

Cite This Page — Counsel Stack

Bluebook (online)
97 Ct. Cl. 92, 1942 U.S. Ct. Cl. LEXIS 35, 1942 WL 4350, Counsel Stack Legal Research, https://law.counselstack.com/opinion/b-w-construction-co-v-united-states-cc-1942.