Wunderlich v. United States

117 Ct. Cl. 92, 1950 U.S. Ct. Cl. LEXIS 19, 1950 WL 5033
CourtUnited States Court of Claims
DecidedJune 5, 1950
DocketNo. 46307
StatusPublished
Cited by19 cases

This text of 117 Ct. Cl. 92 (Wunderlich v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Wunderlich v. United States, 117 Ct. Cl. 92, 1950 U.S. Ct. Cl. LEXIS 19, 1950 WL 5033 (cc 1950).

Opinion

[207]*207Opinion

Madden, Judge,

delivered the opinion of the Court:

The plaintiff is a partnership engaged in the construction business. On March 14, 1938, it made a contract with the United States, which acted through the Bureau of Reclamation of the Department of the Interior, by which it agreed to construct the Vallecito Dam on the Pine River in southern Colorado. It was to be paid,unit prices for most items of the work, and the estimated total price of the project was $2,115,870.

The site of the dam was about 7,550 feet above sea level. It was to be an earth-filled dam about 4,000 feet long at the crest, 600 feet wide at the base, and with a maximum height of about 125 feet. The embankment was to consist of three zones. Zone 1, the upstream zone, and Zone 3, the downstream zone, were to be constructed of pervious and semi-pervious materials, i. e. rock, gravel and cobble stones; Zone 2, in the center, was to contain only impervious material, i. e. earth and only such stones as could be effectively sealed in the earth, leaving no voids. The face of the upstream slope was to be covered with three feet of large stones, riprap. The downstream slope of the dam was to be covered with cobble stones, with a cobble-sluiced gravel fill at the downstream toe.

In constructing the dam a deep trench, called a cut-off trench, was to be dug under the place where Zone 2 of the dam was to be located, which trench was to be tamped full of impervious material to prevent the seepage of water under [208]*208Zone 2. At the ends of this trench, at each abutment of the dam, was to be built a concrete cut-off wall, placed on bedrock. The earth, gravel, and rock for the embankment were to be obtained from the required excavation and from borrow pits, except that the riprap stones were to be obtained from a designated rock quarry.

The normal flow of water out of the reservoir created by the dam was to be through a twin-barrelled concrete conduit through the embankment at the lower part of the right abutment. A control house for the control of the gates of this conduit was to be built on the crest of the dam. The flow through the conduit was to be emptied into an open channel, called the outlet channel, which was to be lined with concrete at the bottom. The outlet channel was to empty, in turn, into the spillway channel, at a point about 200 feet downstream from the dam. The spillway channel was to start from a point at the top of the dam, near the right abutment, and to carry the overflow of the reservoir in flood times. It was also to be lined with concrete on the bottom and was to extend about 2,800 feet downstream where it was to empty into the stilling basin, which in turn would overflow into the river. Gates to control the flow into the spillway channel were to be placed at its upper end.

The contract completion date was December 18,1941. The work was in fact completed in October 1941. Although relations between the representatives of the plaintiff and of the Government were cordial and cooperative during the performance of the contract, differences of opinion as to what was required of the parties by the contract resulted in the filing by the plaintiff with the contracting officer of a large number of claims. Some 43 claims were excepted from the otherwise final settlement made for the work. The contracting officer thereafter, on December 29, 1942, made his decision on the claims. The plaintiff appealed to the head of the department, the Secretary of the Interior, from the parts of the contracting officer’s decision which were adverse. The Secretary of the Interior affirmed the contracting officer’s decision in all respects.

■ The plaintiff, in its petition in this suit, used the same numbers for its claims which it had used in the proceedings [209]*209in the department. It did not, however, include some of the claims in this suit which it had urged upon the department. Some other claims which it included in its petition it has now abandoned, since receiving our Commissioner’s report. The numbering of the claims in our findings and opinion is, therefore, not consecutive, there being some numbers missing in the sequence.

As to certain of the claims, the findings of the contracting officer were favorable to the plaintiff and the plaintiff is satisfied with the amounts awarded. Those amounts have not been paid, and the plaintiff is entitled to a judgment for those amounts. Those claims are as follows: No. 5, $2,450; No. 13, $4,125; No. 18, $466.40; and No. 41, $500.

As to the contested claims, the Government urges that the departmental action was final and binding upon the plaintiff, under the terms of its contract. The pertinent provisions of the contract are Article 15 of the contract, relating to Disputes, and Paragraph 14 of the specifications, relating to Protests. We quote these provisions in a footnote.1 As. to most of the claims, we have found that the plaintiff’s, protests were oral. The Government seems to urge that, since they were not written, they were ineffective. But Paragraph 14 does not say that a contractor’s protests and requests for written instructions must be in writing, and we do not [210]*210construe it to so require. The contracting officer did not, as Paragraph 14 provides, respond to the plaintiff’s protests •and requests for written instructions by furnishing such instructions. He refused to furnish them, saying that.the contract required what he was demanding of the plaintiff. The plaintiff performed the work demanded, and did not, within 10 days, file written protests with the contracting officer. We think that it was not required to do so and lost no rights by not doing so. The Government was in default, so far as the specified procedural steps were concerned, and has no right to complain of the plaintiff’s default.

Paragraph 14 of the specifications provides no finality of departmental decision in circumstances such as we have here. Indeed, finality is almost expressly excluded by the provision that the contracting officer’s decision shall be final except where protests are made and followed up in the specified manner. Since the plaintiff did protest, and the Government failed to respond with written instructions, the plaintiff is entitled to whatever rights it would have had if its protests had been followed by the rest of the specified procedure. Its rights, then, were not determined by any departmental decision agreed to by its accepting paragraph 14 of the specifications.

As we have said, the plaintiff did file its claims with the contracting officer and appealed that officer’s adverse decisions to the head of the department, who affirmed the decisions. Those steps were the steps described in Article 15 of the contract, which we have quoted. Were they taken because Article 15 of the contract was applicable, or were they taken only as a hopeful avenue to possible relief ? In the case of United States v. Moorman, 338 U. S. 457, the Supreme Court held that paragraph 2-16 of the specifications there involved stood on its own feet, and that this court’s decision making it subject to Article 15 of the contract, 113 C. Cls. 115 at 179, was erroneous. Paragraph 2-16 in the Moorman case covered the same factual situations as paragraph 14 in the instant case. It said:

If the contractor considers any work demanded of him to be outside the requirements of the contract, or if

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Hoel-Steffen Construction Co. v. United States
684 F.2d 843 (Court of Claims, 1982)
Construction Management Corp. v. Brown & Root, Inc.
41 Misc. 2d 864 (New York Supreme Court, 1964)
Silverman Brothers, Inc. v. United States
324 F.2d 287 (First Circuit, 1963)
Stein Bros. Mfg. Co. v. The United States
337 F.2d 861 (Court of Claims, 1963)
Stein Bros. Mfg. Co. v. United States
337 F.2d 861 (Court of Claims, 1963)
River Construction Corp. v. United States
159 Ct. Cl. 254 (Court of Claims, 1962)
Wm. A. Smith Contracting Co., Inc. v. United States
292 F.2d 854 (Court of Claims, 1961)
Wm. A. Smith Contracting Co. v. United States
155 Ct. Cl. 44 (Court of Claims, 1961)
Idaho Falls Bonded Produce & Supply Co. v. United States
107 F. Supp. 952 (Court of Claims, 1952)
Cramp Shipbuilding Co. v. United States
122 Ct. Cl. 72 (Court of Claims, 1952)
Slonk v. United States
121 Ct. Cl. 246 (Court of Claims, 1952)
Pottsville Casting & Machine Shops, Inc. v. United States
101 F. Supp. 370 (Court of Claims, 1951)
United States v. Wunderlich
342 U.S. 98 (Supreme Court, 1951)
United States v. Wunderlich
120 Ct. Cl. 822 (Court of Claims, 1951)
Bell Aircraft Corp. v. United States
100 F. Supp. 661 (Court of Claims, 1951)

Cite This Page — Counsel Stack

Bluebook (online)
117 Ct. Cl. 92, 1950 U.S. Ct. Cl. LEXIS 19, 1950 WL 5033, Counsel Stack Legal Research, https://law.counselstack.com/opinion/wunderlich-v-united-states-cc-1950.