National Steel and Shipbuilding Company v. The United States

419 F.2d 863, 190 Ct. Cl. 247, 1969 U.S. Ct. Cl. LEXIS 167
CourtUnited States Court of Claims
DecidedDecember 12, 1969
Docket1-67
StatusPublished
Cited by19 cases

This text of 419 F.2d 863 (National Steel and Shipbuilding Company v. The United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
National Steel and Shipbuilding Company v. The United States, 419 F.2d 863, 190 Ct. Cl. 247, 1969 U.S. Ct. Cl. LEXIS 167 (cc 1969).

Opinion

ON PLAINTIFF’S MOTION AND DEFENDANT’S CROSS-MOTION FOR SUMMARY JUDGMENT

PER CURIAM:

This case was referred to Trial Commissioner David Schwartz with directions to prepare and file his opinion on the issues of plaintiff’s motion and defendant’s cross-motion for summary judgment under the order of reference and Rule 99(c) [since September 1,1969, *866 Rule 166(c)]. The commissioner has done so in an opinion and report filed on January 10, 1969, wherein such facts as are necessary to the opinion are set forth. Defendant filed a request for review by the court and plaintiff urged that the court not adopt Section II of the commissioner’s report in which he concludes that the Maritime Subsidy Board acted properly in dismissing its administrative claim grounded on Article 7.(d) of the contract. The case has been submitted to the court on oral argument of counsel and the briefs of the parties.

The court agrees that there was no administrative remedy for plaintiff’s claim and that the hearing board had no jurisdiction of this breach-of-contract claim. On that basis there is no question that the court can decide all the issues, legal or factual, for itself. The parties having agreed that the case shall be decided on the administrative record, the court can deal with that record without deference to the administrative decision. See Clack v. United States, 395 F.2d 773, 779, 184 Ct.Cl. 40, 49-50 (1968). In any event, the court also agrees that the Federal Maritime Board committed legal errors in failing to apply the proper criteria in determining whether the defendant had employed all reasonable effort and reasonable diligence to supply plaintiff with working plans on the specified dates, and that under the proper legal standards the only possible conclusion is that reached by the trial commissioner.

Since the court agrees with the commissioner's opinion and recommended conclusion, as hereinafter set forth, it hereby adopts the same as the basis for its judgment in this case together with the foregoing paragraph. Therefore, plaintiff’s motion for summary judgment is granted, on liability alone, defendant’s cross-motion is denied and proceedings on damages and on any remaining issues will continue after an interval to afford the parties the opportunity to reach agreement, pursuant to the provisions of Rule 131(c).

OPINION OF COMMISSIONER

SCHWARTZ, Commissioner:

The cross-motions for summary judgment in this suit for breach of contract raise issues of the reasonableness of the efforts and diligence of the Federal Maritime Board in furnishing plaintiff National Steel and Shipbuilding Corporation (“Nassco”) with the working plans for two cargo ships built by plaintiff under a contract.

I

By contract No. FMB-66, dated February 13,1958, the Federal Maritime Board (“FMB”) 1 let to plaintiff the construction of two single screw cargo vessels for a fixed price of $23,509,000. Another contract of the same date, No. FMB-65, let the building of two identical vessels to another shipyard, New York Shipbuilding Corporation (“New York” or “New York Ship”). Each shipbuilder was a party only to its contract with the FMB. New York Ship is not a party to this case.

The four ships were built for owner" ship by American Export Lines, Inc. pursuant to a program for the replacement of cargo ships under Title Y of the Merchant Marine Act of 1936, as amended, 49 Stat. 1995, as amended, 46 U.S.C. § 1151 et seq. American Export, a party to both contracts, received a construc *867 tion-differential subsidy under Sections 501 and 504 of the Act, 49 Stat. 1995, 1998, as amended, 46 U.S.C. §§ 1151, 1154. It is not a party to this case.

The contract had been advertised as one for four vessels, with notice that the FMB might split the work between two or more bidders and elect to furnish one of them with the necessary working plans. Plaintiff in its bid accordingly provided for a reduction of $720,000 in its bid price in the event the FMB furnished it with the plans. New York Ship’s bid provided for - a decrease of $10,000 in the same event. The FMB chose to split the contract between the yards, accept plaintiff’s reduction in price and furnish it with the working plans. The award of two ships to plaintiff, a new and small shipyard, was made with the approval of The President, in the interest of developing shipyard capacity useful in national defense, pursuant to authority contained in Section 502(f) of the Act, 49 Stat. 1996, as amended, 46 U.S.C. § 1152(f).

Plaintiff performed its contract and delivered its two vessels on contract delivery dates. The controversy concerns increased costs incurred by it, allegedly from the breach by the FMB of its obligation under the contract to employ all reasonable effort and diligence to supply plaintiff with some 650 working plans, for use in the construction of the ships, on dates specified in the contract. These plans were prepared by New York Ship and furnished to the FMB pursuant to New York Ship’s contract with the FMB, and then pursuant to the FMB-Nassco contract supplied by the FMB to plaintiff.

Article I of the Special Provisions of the FMB-Nassco contract (appendix hereto) provides that the contractor shall build, complete and deliver the vessels, and adds in parenthesis: “(with the contractor receiving from the Board re-produeibles of all working plans, purchase specifications and purchase orders * * *).” Addendum 3 to the specifications, a part of the contract, in its first paragraph states in plainer language the obligation to furnish Nassco with working plans (appendix hereto):

The Owner and the Board shall furnish approved reproducibles of (1) complete working plans, (2) complete purchase specifications, and (3) complete purchase orders.

Working plans are detailed drawings for use in construction, and the “purchase specifications” and “purchase orders” were the procurement documents and data for equipment which was to be identical in the four ships. The term “working plans” is used in the record and herein to include both the working drawings and the procurement papers.

“Reproducibles,” as the word implies, are plans processed so as to be capable of reproduction. “Approved reproducibles” were working plans approved, as was required, by the J. J. Henry Co., design agents for the American Export Lines, and by the FMB, and, in the case of various plans, by agencies with an interest in the particular feature of the vessel, such as the Coast Guard, the Public Health Service, the American Bureau of Shipping and insurers.

Although the agreement by the FMB (and the Owner, whose liability is not raised) to supply working plans to the plaintiff was unqualified, the agreement did not extend to a guarantee that plans would be supplied by specific dates.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

State v. Robinson
Supreme Court of North Carolina, 2026
In re: Hayes
Court of Appeals of North Carolina, 2024
Locklear v. Cummings
822 S.E.2d 587 (Court of Appeals of North Carolina, 2018)
Yankee Atomic Electric Co. v. United States
42 Cont. Cas. Fed. 77,396 (Federal Claims, 1998)
Seville Construction, Inc. v. United States
40 Cont. Cas. Fed. 76,909 (Federal Claims, 1996)
Youngdale & Sons Construction Co. v. United States
38 Cont. Cas. Fed. 76,467 (Federal Claims, 1993)
Goldberger Foods, Inc. v. United States
37 Cont. Cas. Fed. 76,111 (Court of Claims, 1991)
American Satellite Co. v. United States
36 Cont. Cas. Fed. 75,884 (Court of Claims, 1990)
Blinderman Construction Co. v. United States
35 Cont. Cas. Fed. 75,716 (Court of Claims, 1989)
S. Leo Harmonay, Inc. v. Binks Manufacturing Co.
597 F. Supp. 1014 (S.D. New York, 1984)
Blackmon v. Hill
427 So. 2d 228 (District Court of Appeal of Florida, 1983)
Westinghouse Electric Corp. v. Garrett Corp.
437 F. Supp. 1301 (D. Maryland, 1977)
American Ship Building Co.
21 Cont. Cas. Fed. 84,081 (Court of Claims, 1975)
Colonial Metals Co. v. United States
494 F.2d 1355 (Court of Claims, 1974)
Teitelbaum v. United States
458 F.2d 72 (Court of Claims, 1972)
United States v. Russell Eugene Briddle
436 F.2d 4 (Eighth Circuit, 1971)
Ingalls East Division, Litton Industries
193 Ct. Cl. 1094 (Court of Claims, 1970)

Cite This Page — Counsel Stack

Bluebook (online)
419 F.2d 863, 190 Ct. Cl. 247, 1969 U.S. Ct. Cl. LEXIS 167, Counsel Stack Legal Research, https://law.counselstack.com/opinion/national-steel-and-shipbuilding-company-v-the-united-states-cc-1969.