Blinderman Construction Co. v. United States

35 Cont. Cas. Fed. 75,716, 17 Cl. Ct. 860, 1989 U.S. Claims LEXIS 178, 1989 WL 102477
CourtUnited States Court of Claims
DecidedSeptember 8, 1989
DocketNo. 305-88C
StatusPublished
Cited by6 cases

This text of 35 Cont. Cas. Fed. 75,716 (Blinderman Construction Co. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Blinderman Construction Co. v. United States, 35 Cont. Cas. Fed. 75,716, 17 Cl. Ct. 860, 1989 U.S. Claims LEXIS 178, 1989 WL 102477 (cc 1989).

Opinion

OPINION

NETTESHEIM, Judge.

This case is before the court after argument on cross-motions for summary judgment.

FACTS

The following facts are the only ones material to the resolution of the cross-motions and are undisputed. On September 23, 1983, contract DACA 27-83-C-0100 was executed between the Army Corps of Engineers (the “Corps”) and Blinderman Construction Company, Inc. (“plaintiff”), in the amount of $8,143,655.00 for the construction of unaccompanied enlisted personnel housing at Chanute Air Force Base in Rantoul, Illinois.

In the specifications for the contract, Technical Provision 15K “Ventilating System,” paragraph 1 “Applicable Publications” states that “[t]he publications listed below form a part of this specification to the extent referenced____” Listed in paragraph 1.6 of the solicitation under “Applicable Publications” is National Fire Protection Association (“NFPA”) Code No. 90A (1981 ed.) “Standard for the Installation of Air Conditioning and Ventilation Systems.” Paragraph 3-3.2.1 of this code provision reads: “Approved fire dampers shall be provided where ducts or air grills penetrate partitions required to have a fire resistance rating of 2 hours or more. {See Figure 3-3.)” Paragraph 3-3.7.2.1 of the code provision states:

The designer of an air duct system shall show on the drawings the location and mounting arrangement of all automatic fire door assemblies, fire dampers, smoke dampers, ceiling dampers, and fire protection means of similar nature required by this standard. .

(Emphasis added.)

Technical Provision 15-K, paragraph 8.4, provided in full:

Fire Doors and Fire Dampers: Fire dampers or doors shall conform to UL 10 and UL 555, respectively. Fire dampers or doors shall be provided where indicated in ducts passing through fire rated partitions or walls. Fire doors and fire dampers shall be automatic operating type approved for the protection of openings in fire rated walls and partitions and shall be installed in accordance with the conditions of their approval and the manufacturer’s instructions. Hinged or unhinged access doors shall be provided in the ducts to make all fire doors and fire dampers accessible for inspection and maintenance, and shall be as specified for duct access doors. Ductwork in fire-rated floor-ceiling or roof-ceiling assembly system with air ducts that pierce the ceiling of the assembly shall be constructed in conformance with designs in UL Fire Resistance Directory. Other designs that have been tested by an independent, nationally recognized testing organization and comply with the requirements set forth in NFPA No. 90A are acceptable. Unless otherwise indicated, the installation details given in NFPA No. 91 for fire doors and in SMACNA Fire Damper Guide for Air Handling Systems for fire dampers shall be followed, except minimum metal thickness [862]*862for all sleeves provided for fire dampers shall be not lighter than 14-gage (0.0781 inch). Necessary items associated with the fire doors and fire dampers such as retaining angles, sleeves, and breakaway connections shall be provided.

(Emphasis added.) This specification was amended on July 15, 1983, after the invitation for bids had been released to bidders, but before bid opening. Amendment No. 0001 deleted the words “where indicated.” The specification as revised read: “Fire dampers or doors shall be provided in ducts passing through fire partitions or walls____” Amendment No. 0001 also added a note on the Contract Drawing Sheet Nos. 128, 129, 131, 132, 133, and 134, stating that “[f]ire dampers or doors shall be provided in all ducts passing through fire rated partitions or walls. See sheet 53 & 54 for wall fire ratings.” The Contract Drawing Sheet Nos. 53 and 54 depict the locations of both one-hour and two-hour fire-rated partitions.

In the General Provisions of the contract, clause 2 “Specifications and Drawings” provides, in pertinent part:

Anything mentioned in the specifications and not shown on the drawings, or shown on the drawings and not mentioned in the specifications, shall be of like effect as if shown or mentioned in both. In case of difference between drawings and specifications, the specifications shall govern. In case of discrepancy either in the figures, in the drawings, or in the specifications, the matter shall be promptly submitted to the Contracting Officer, who shall promptly make a determination in writing____

On July 18, 1984, the Corps inspector informed plaintiff that “fire dampers are required in all ducts at fire walls____”

On October 11, 1984, plaintiffs mechanical subcontractor, R.H. Bishop Company, wrote plaintiff stating that NFPA-90A, at paragraph 3-3.2.1, provides that fire dampers are required in only two-hour fire rated partitions. The letter concluded with the contention that, “if the Owner wishes Fire Dampers in locations other than those required by NFPA-90A, ... [Bishop] should receive payment for the additional Fire Dampers.”

By Transmittal 152, dated October 19, 1984, plaintiff submitted the manufacturer’s shop drawings for ductwork. This transmittal was disapproved on November 6, 1984, in part because “fire dampers are not shown where the ducts pass [through] corridor walls.”

By letter dated January 15, 1985, to plaintiff, Bishop requested compensation in the amount of $9,235.77 for 145 fire dampers for the one-hour fire rated partitions that Bishop did not consider itself required to furnish. On May 7, 1985, plaintiff, based on its view that those dampers were not required because of a conflict between the note added to the 120- and 130-series contract drawings and the drawings depicting the fire-rated partitions, submitted a proposal to the Corps in the amount of $12,925.00 for the 145 dampers. The Corps responded to plaintiff’s proposal by letter dated July 17, 1985, stating:

The note on Contract Drawing No. 128 requires fire dampers in ducts passing through the fire rated partitions shown on Contract Drawings No. 53 and 54. These drawings indicate locations of the one hour and two hour fire rated partitions. Therefore, it is considered a contract requirement to provide fire dampers where ducts pass through the one hour rated corridor partitions.

By letter dated February 6, 1987, plaintiff filed a request for a contracting officer’s decision on its proposal. The contracting officer denied plaintiff’s claim on May 19, 1987.

DISCUSSION

The recital of undisputed material facts follows the Supreme Court’s instruction in Anderson v. Liberty Lobby, Inc., 477 U.S. 242, 106 S.Ct. 2505, 91 L.Ed.2d 202 (1986), that “the mere existence of some alleged factual dispute between the parties will not defeat an otherwise properly supported motion for summary judgment; the requirement is that there be no genuine issue of material fact.” Id. at 247-48, 106 S.Ct. at 2510 (emphasis in original). Plaintiff con[863]*863troverts the averments of one of defendant’s affiants, for example, but this affidavit does not serve as a basis for granting defendant’s cross-motion.

Plaintiff and defendant agree that the NFPA standards apply to this contract, but disagree as to the effect of incorporating the standards into the contract specifications.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Barlovento, LLC v. AUI, Inc.
D. New Mexico, 2020
PCL Construction Services, Inc. v. United States
47 Fed. Cl. 745 (Federal Claims, 2000)
Seville Construction, Inc. v. United States
40 Cont. Cas. Fed. 76,909 (Federal Claims, 1996)
Kiewit/Tulsa-Houston v. United States
37 Cont. Cas. Fed. 76,255 (Court of Claims, 1992)
Craft Machine Works, Inc. v. United States
36 Cont. Cas. Fed. 75,861 (Court of Claims, 1990)
Neal & Co. v. United States
36 Cont. Cas. Fed. 75,802 (Court of Claims, 1990)

Cite This Page — Counsel Stack

Bluebook (online)
35 Cont. Cas. Fed. 75,716, 17 Cl. Ct. 860, 1989 U.S. Claims LEXIS 178, 1989 WL 102477, Counsel Stack Legal Research, https://law.counselstack.com/opinion/blinderman-construction-co-v-united-states-cc-1989.