Unicon Management Corporation v. The United States
This text of 375 F.2d 804 (Unicon Management Corporation v. The United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.
Opinion
ON PLAINTIFF’S MOTION AND DEFENDANT’S CROSS-MOTION FOR SUMMARY JUDGMENT
In March 1959 the contractor agreed with the Corps of Engineers to construct, for a fixed price, two phases of the Missile Master Facilities near-Pittsburgh. The current claim is that, the Government required plaintiff to install in one room a steel-plate flooring-which was not called for by the plans and specifications. The contracting officer and the Armed Services Board of Contract Appeals (65-1 BCA para. 4775) refused the demand for an equitable adjustment and this suit was *805 brought. The problem arises because the most pertinent specification, if read alone, could be said to contemplate a wholly concrete rather than a partial steel-plate floor, while the most pertinent drawings, if read alone, direct the steel-plate covering. The contractor resolves the difficulty by relying, mainly, on the contractual clause that “in case of difference between drawings and specifications, the specifications shall govern.” The Board and the defendant invoke another provision that “anything mentioned in the specifications and not shown on the drawings, or shown on the drawings and not mentioned in the specifications, shall be of like effect as if shown or mentioned . in both.” 1 Since the question is one of contract interpretation, we are free to decide the matter for ourselves.
The room was Equipment Room No. 1 (also designated as Room 117) in one of the buildings being erected by plaintiff. To secure heavy equipment, this space was to have pallets along the floor with parallel cable trenches for bringing electric current to the machines. Steel beams were to be used in and along the floor in connection with these pallets. It is agreed that the top cover of the floor, apart from the portions devoted to the pallets and the trenches, was to be a resilient floor tile. There was also to be a concrete base. The dispute is whether the tile was to be laid directly on this concrete or over a quarter-inch steel plate above the concrete. The specifications, in a section of the Technical Provisions on miscellaneous metalwork, contain a paragraph dealing with the floor of this room and with the pallets (TP 17-23). 2 By itself, this provision can be interpreted as implicitly envisioning an all-concrete floor; there is no reference to steel plate but there are references to “the concrete floor”, “a concrete floor”, “pouring of the floor”, “pouring of the floors”, and steel beams being “embedded” in the concrete floor.
The relevant drawings, by themselves, give a very different impression. The most significant sketch — a cross-section of the floor of Equipment Room No. 1— shows the trench covered by a removable steel cover plate, with a depression into which the plate’s handle is fitted flush with the floor level; the open-floor portion of the drawing shows the top of two steel beams covered by y^" steel plate and the resilient floor tile on top of this plate. This is a specific directive to use *806 steel plate immediately beneath the tile. To the same effect, another detail drawing of the trenches and beams in the room shows steel plate on top of an “I” beam and the resilient tile above the steel plate. The other drawings are uninformative or unclear on the point, but they do not contradict the sketches explicitly showing the steel plate. 3 The result is that the drawings as a whole affirmatively support the Government’s understanding as to the nature of the floor of Equipment Room No. I. 4
We agree with the Board that these plans need not, and should not, be construed as in conflict with specification TP 17-23 (footnote 2, supra) but, instead, as supplementing the latter. The parties directed in the contract that “anything * * * shown on the drawings and not mentioned in the specifications, shall be of like effect as if shown or mentioned in both” (footnote 1, supra). This rule is peculiarly applicable here because TP 17-23 obviously does not cover the entire subject of floor construction. For instance, it does not mention the important item of resilient floor tile, or the metal plates for the trenches, nor does it even describe fully the construction of the steel beams running transversely to the pallets. When the contract is viewed as a whole, the function of the paragraph is seen as calling attention to the steel beams set in the floor to support the pallets- — the references to concrete are in that connection and in that special light — not as drawing together all of the requirements on the make-up of the floor. Certainly, as the Board pointed out, the specification does not provide in terms or by necessary implication that the resilient tile is to rest directly on concrete; nothing is said about the tile or its placing. It is therefore proper to read TP 17-23 as open to complementation by the drawings (or by other specifications) insofar as these cover items or aspects other than the features of the steel beams discussed in the former provision. Plaintiff seems to insist that, if the specification can be read as conflicting with the drawings, that reading must be adopted even though a more harmonious interpretation is also reasonably available. The rule, however, which the courts have always preferred is, where possible, to interpret the provisions of a contract as coordinate not contradictory. See Thompson Ramo Wooldridge, Inc. v. United States, 361 F.2d 222, 228, 175 Ct.Cl. 527, 536 (1966). Contractors, too, have long been on notice that in reading contract documents they should seek to find concord, rather than discord, if they properly can.
This brings us to another reason why plaintiff’s position is weak. There is no evidence as to the view actually taken by the company’s estimators before it submitted its bid (plaintiff did not call them to the stand in the administrative proceeding). But assuming arguendo that they read TP 17-23 the way plaintiff now does, if they examined the plans and specifications carefully they could not have helped notice the drawings which specifically embodied the contrary requirement. If they were not aware of this fact they should have been. The contract provided that “in any case of discrepancy either in the figures, in the drawings, or in the specifications, the matter shall be promptly submitted to the Contracting Officer, who shall promptly make a determination in writing. Any adjustment by the Contractor without this determination shall be at his own risk and expense” (footnote 1, supra). A warning of this kind calls upon the bidder to bring to the Government’s attention any serious or patent discrepancy of signifi- *807 canee, of which he is or should be cognizant. See, e. g., Beacon Constr. Co. v. United States, 161 Ct.Cl. 1, 7, 314 F.2d 501, 504 (1963); Jefferson Constr. Co. v. United States, 364 F.2d 420, 423, 176 Ct.Cl. -, - (July 1966), cert. denied, 386 U.S. 914, 87 S.Ct.
Free access — add to your briefcase to read the full text and ask questions with AI
Related
Cite This Page — Counsel Stack
375 F.2d 804, 179 Ct. Cl. 534, 1967 U.S. Ct. Cl. LEXIS 207, Counsel Stack Legal Research, https://law.counselstack.com/opinion/unicon-management-corporation-v-the-united-states-cc-1967.