J. A. Jones Construction Company v. The United States

390 F.2d 886, 182 Ct. Cl. 615, 1968 U.S. Ct. Cl. LEXIS 59
CourtUnited States Court of Claims
DecidedFebruary 16, 1968
Docket337-61
StatusPublished
Cited by50 cases

This text of 390 F.2d 886 (J. A. Jones Construction Company v. The United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
J. A. Jones Construction Company v. The United States, 390 F.2d 886, 182 Ct. Cl. 615, 1968 U.S. Ct. Cl. LEXIS 59 (cc 1968).

Opinion

ON DEFENDANT’S MOTION AND PLAINTIFF’S CROSS-MOTION FOR SUMMARY JUDGMENT

DAVIS, Judge.

In mid-February 1956 the plaintiff contracted with the Army Corps of Engineers, acting as the construction agency for the Department of the Air Force, to build various facilities at the Air Force Missile Test Center at Cape Kennedy (then Cape Canaveral). This was the first (known as number “2003”) of twenty-eight contracts (aggregating about $55 million) awarded, prior to plaintiff’s completion of the agreement, as part of the Air Force’s Inter-Continental Ballistic Missile (ICBM) program in that geographic area. Twenty of the twenty-seven later contracts (including four with the Jones Company) had clauses requiring the use of overtime in addition to the standard provision (GC-5) allowing the contracting officer to require *887 extra shifts or overtime if the contractor fell behind schedule. 1 Plaintiff’s original contract, here involved, had only GC-5.

The company seeks to recover $122,-897.91, allegedly representing premium (overtime) wages paid by it and its subcontractors. The gravamen of the complaint, based on Bateson-Stolte, Inc. v. United States, 172 F.Supp. 454, 145 Ct.Cl. 387 (1959), Bateson-Stolte, Inc. v. United States, 305 F.2d 386, 158 Ct.Cl. 455 (1962); and Helene Curtis Indust., Inc. v. United States, 312 F.2d 774, 160 Ct.Cl. 437, (1963), is that the defendant knew but failed to divulge that the large, high priority ICBM construction program, premised in large part on the payment of premium wages, was to be initiated in that labor area 2 (including plaintiff’s project) while this contract was being performed. As a result, according to the company, the labor shortage following upon the immense ICBM program and its use of overtime forced the plaintiff to pay premium wages in order to acquire the labor necessary for timely performance, although after due inquiry on the site it had reasonably prepared its bid on the assumption that an adequate supply of straight time labor would be available.

This controversy has endured a long and tortuous journey before coming to us now for review, under the Wunderlich Act, 41 U.S.C. §§ 321-322 (1964), of the ASBCA’s ultimate decision against plaintiff. The case has already been subject to two decisions by the ASBCA, two recommendations by our commissioner, and two nondispositive orders of the court. In the view we take it is unnecessary to spell out these various steps and counter-steps, but for the historical record and the diligent we set them out in the Appendix.

We eliminate, too, certain points not now in the case. Plaintiff does not assert that the Government is liable merely for proceeding with an enormous construction program, utilizing mandatory overtime, in proximity to J. A. Jones’s project, thereby subjecting the company to the additional expense of keeping up with the wages paid by its neighbors. Any such assertion would collide with the sovereign-act doctrine. 3 Furthermore, the *888 Board in its first decision rejected, and plaintiff does not now reassert, any contention that the contract contained a provision rendering the defendant liable for the consequences of letting the subsequent contracts 4 or that defendant’s actions were intended to hinder plaintiff’s performance. 5 The claim now rests exclusively on the nondisclosure, prior to the award of plaintiff’s contract, of information known to the defendant about other Air Force-Corps of Engineers projects at Cape Kennedy.

In considering that problem, we need not elaborate the established rule that, while the defendant had no obligation to prevent (and, indeed, was free to precipitate) the avalanche that buried the contractor, it was not free, if it was aware of the impending avalanche and knew that J. A. Jones was not, to stand aside and let the bidder be overwhelmed without a warning. See United States v. Beuttas, 324 U.S. 768, 772-773, 65 S.Ct. 1000, 89 L.Ed. 1354 (1945); T. F. Scholes, Inc. v. United States, 357 F.2d 963, 970, 174 Ct.Cl. 1215, 1226 (1966); Helene Curtis Indust., Inc. v. United States, supra, 312 F.2d at 777-778, 160 Ct.Cl. at 442-445, and cases cited; Bateson-Stolte, Inc. v. United States, supra, 305 F.2d at 388, 158 Ct.Cl. at 457; S. T. G. Constr. Co. v. United States, 157 Ct. Cl. 409, 416 (1962); Bateson-Stolte, Inc. v. United States, supra, 172 F.Supp. at 456-457, 145 Ct.Cl. at 391. 6 The only real issue is whether the defendant — in the form of some agency of the Federal Government accountable to this plaintiff —did have such knowledge and therefore such a duty.

Both parties presented the case to the Board and to us as if the only responsible entity was the Corps of Engineers. They dispute whether accountability can be pinned to the Office of the Chief of Engineers or only to the local District Engineer at Jacksonville, Florida. Plaintiff maintains that, despite the Board’s second determination (see Appendix infra), the administrative record compels the conclusion that, before Jones’ contract 2003 was awarded, the Office of the Chief of Engineers had enough knowledge of the premium-time plans (even though the Jacksonville District personnel may not have) to come under a duty to pass this information on to the local officials, who in turn had an obligation to divulge it to plaintiff before its bid. The defendant insists that the Chief of Engineers’ Office did not have sufficient *889 knowledge, and in any event that the Government can be held only for the information available to the local Engineer representatives who dealt with plaintiff in Florida.

We decline to resolve these opposing contentions as to the knowledge of the Chief of Engineers, and the validity of the Board’s findings on that point, because we believe that (a) the knowledge of the Air Force (the agency for which all the work was being done) is decisive in this case, and (b) there is no doubt that the Air Force knew enough about the probability of the use of premium-time at Cape Kennedy (as well as the off-chance that contractors like plaintiff would realize the likely extensive incidence of premium-time payments) to put the Air Force and its agents under an obligation to plaintiff.

We take this position even though plaintiff did not contend (and indeed specifically disclaimed) that the Government should be held liable for what the Air Force knew but failed to disclose. This is an issue of law and, moreover, not the kind of legal issue as to which a litigant can perhaps bind the court by his failure to raise or press the point.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Allen Engineering Contractor Inc. v. United States
611 F. App'x 701 (Federal Circuit, 2015)
Griffin & Griffin Exploration, LLC v. United States
116 Fed. Cl. 163 (Federal Claims, 2014)
Allen Engineering Contractor, Inc. v. United States
115 Fed. Cl. 457 (Federal Claims, 2014)
Massachusetts v. Mylan Laboratories
608 F. Supp. 2d 127 (D. Massachusetts, 2008)
Renda Marine, Inc. v. United States
66 Fed. Cl. 639 (Federal Claims, 2005)
Northrop Grumman Corp. v. United States
63 Fed. Cl. 12 (Federal Claims, 2004)
Data Marketing Co. of Virginia v. United States
107 F. App'x 187 (Federal Circuit, 2004)
Data Marketing Co. v. United States
55 Fed. Cl. 685 (Federal Claims, 2003)
Hardwick Bros. v. United States
41 Cont. Cas. Fed. 76,972 (Federal Claims, 1996)
Midfirst Bank v. C.W. Haynes & Co. a South Carolina Corp.
893 F. Supp. 1304 (D. South Carolina, 1994)
Miller Elevator Co. v. United States
39 Cont. Cas. Fed. 76,635 (Federal Claims, 1994)
McDonnell Douglas Corp. v. United States
27 Fed. Cl. 204 (Federal Claims, 1992)
Wm. T. Thompson Co. v. United States
38 Cont. Cas. Fed. 76,311 (Court of Claims, 1992)
Hercules Inc. v. United States
37 Cont. Cas. Fed. 76,291 (Court of Claims, 1992)
Granite Construction Co. v. United States
37 Cont. Cas. Fed. 76,240 (Court of Claims, 1991)
Wyler v. Korean Air Lines Company, Ltd.
928 F.2d 1167 (D.C. Circuit, 1991)
Wyler v. Korean Air Lines Co.
928 F.2d 1167 (D.C. Circuit, 1991)

Cite This Page — Counsel Stack

Bluebook (online)
390 F.2d 886, 182 Ct. Cl. 615, 1968 U.S. Ct. Cl. LEXIS 59, Counsel Stack Legal Research, https://law.counselstack.com/opinion/j-a-jones-construction-company-v-the-united-states-cc-1968.