Bateson-Stolte, Inc. v. The United States

305 F.2d 386, 158 Ct. Cl. 455, 1962 U.S. Ct. Cl. LEXIS 190
CourtUnited States Court of Claims
DecidedJuly 18, 1962
Docket141-57
StatusPublished
Cited by26 cases

This text of 305 F.2d 386 (Bateson-Stolte, Inc. v. The United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Bateson-Stolte, Inc. v. The United States, 305 F.2d 386, 158 Ct. Cl. 455, 1962 U.S. Ct. Cl. LEXIS 190 (cc 1962).

Opinions

WHITAKER, Judge.

This is a suit for $193,637.95, additional expenses alleged to have been incurred by plaintiff in the performance of a contract for the construction of a power house and appurtenant structures at the Clark Hill Project in Georgia and South Carolina.

Under the Davis-Bacon Act, as amended (40 U.S.C.A. § 276a et seq.), plaintiff was required to pay not less than the prevailing wage rate in the vicinity of the project, as determined by the Secretary of Labor. In addition, for a short period of time, plaintiff was not only required to pay not less than this minimum wage rate but also was prohibited from paying any more. However, plaintiff admits that it suffered no damage during this period.

At the time of the execution of the contract for the Clark Hill Project, on October 11, 1950, the Government, acting through the Atomic Energy Commission (hereinafter, AEC), was planning the construction of a major project, involving expenditures estimated at over a billion dollars. While the AEC at that time had not selected a site for its project, a site 40 miles down the Savannah River from the Clark Hill Project was one of several under serious consideration. This site was finally selected on [388]*388November 24, 1950, and the project was constructed at this point. This AEC project required a very large labor force, much larger than could be obtained in the immediate neighborhood of the project, necessitating the recruiting of labor from the larger municipalities in the area. This made it necessary for the AEC to pay considerably higher wages than the wages established by the Secretary of Labor as the prevailing wage in the vicinity of the Clark Hill Project. Since the AEC project was only 40 miles downstream from the Clark Hill Project, this great demand for labor, and the payment of wages higher than the prevailing wage, made it necessary for plaintiff to pay its workers, as soon as permission to do so could be obtained, wages higher than the prevailing wages, and higher than it would have been required to pay had the AEC project not been in competition with it.

Plaintiff sues for the difference in the wages predetermined by the Secretary of Labor and the wages it was required to pay.

This case was previously before us on defendant’s motion for judgment on the pleadings. In an opinion rendered on April 8, 1959, 172 F.Supp. 454, 145 Ct.Cl. 387, we expressed the opinion that if the Corps of Engineers knew that this project was to be located in this vicinity and that this large labor force would be necessary to construct the AEC project, to secure which wages considerably higher than the prevailing wage rate would have to be paid, the Corps of Engineers was under the duty to disclose it. Although the United States was the contractor both for the Clark Hill Project and for the AEC project, we nevertheless held that, in view of the vastness of the business engaged in by the United States Government, with its multitudinous departments and bureaus and independent agencies scattered all over the world, the knowledge of the AEC could not be imputed to the Corps of Engineers. We stated that the Government was liable only if the Corps of Engineers had knowledge that the AEC pi'oject was to be located in the immediate vicinity of the Clark Hill Project, and that it would require a very large labor force, who would have to be paid a higher wage than that prevailing in the vicinity.

The case was remanded to the Trial Commissioner to take proof on these questions. The case is now before us upon the Commissioner’s report. That report shows that the Corps of Engineers was requested by the AEC to survey more than 100 sites in Arkansas, Louisiana, Texas, Mississippi, Alabama, Georgia, Tennessee, Kentucky, West Virginia, Missouri, Illinois, Indiana and Ohio as possibly suitable locations for the erection of this project. The Corps of Engineers was told by the AEC the location would have to be in the vicinity of a town of not less than 25,000 to 50,000 inhabitants, in order to secure the necessary labor force. The Corps of Engineers was not advised of the immensity of the project, nor of the large labor force that would be required, but it was told that an area of from 100,000 to 150,000 acres would be required.

Among the 100 sites surveyed was the one in the neighborhood of the Clark Hill Project, and the Corps of Engineers recommended it as one of a number of suitable sites. However, it was still surveying sites, in Wisconsin, Michigan, and Minnesota, when bids were opened. It was not until November 10, 1950, that the contractor for the AEC project finally made its selection of the site to be recommended to the AEC, and the AEC did not make the final selection until November 24, 1950. Our Trial Commissioner has found, which finding we have adopted:

“On October 11, 1950, when the plaintiff and a contracting officer of the Corps of Engineers entered into the contract for the construction of the powerhouse and appurtenant works at the Clark Hill Project, neither the plaintiff nor the Corps of Engineers knew, or could have known through the exercise of reasonable diligence, that the new pro[389]*389duetion plant of the Atomic Elnergy Commission would be located and constructed within the same geographical area that included the Clark Hill Project of the Corps of Engineers. * * * ”

Furthermore, when the contract for the Clark Hill Project was awarded, the Corps of Engineers had no knowledge of the large amount of labor that would be required.

In view of these findings of the commissioner, which we have adopted as the findings of fact of the court, we do not think the Corps of Engineers was in possession of any information which it was under the duty to disclose to plaintiff prior to the execution of the contract.

On oral argument we understood plaintiff to say that it no longer relied upon the failure of the Corps of Engineers to disclose pertinent information, but relied, rather, on the defendant’s breach of its implied promise not to hinder or delay plaintiff in the performance of its contract. It says the establishment of the AEC project in the vicinity of the Clark Hill Project and the fixing of a minimum wage for this project higher than the minimum plaintiff was required to pay was a breach of this implied condition.

Let it be remembered that the provision for the payment of a minimum wage was not for the benefit of the contractor and was no warranty that he would not be required to pay a higher wage. United States v. Binghamton Construction Co., 347 U.S. 171, 74 S.Ct. 438, 98 L.Ed. 594. But if the defendant directly required the contractor to pay a higher wage, it is liable for the increase. Sunswick Corp. v. United States, 75 F.Supp. 221, 109 Ct.Cl. 772. Also, if the defendant required the contractor to pay increased wages by the doing of some act it had explicity or impliedly agreed not to do, it would be liable. Absent such an agreement, the defendant was at liberty to do what it pleased.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Fireman's Fund Insurance v. United States
92 Fed. Cl. 598 (Federal Claims, 2010)
L'Enfant Plaza Properties, Inc. v. United States
645 F.2d 886 (Court of Claims, 1981)
Turnkey Enterprises, Inc. v. United States
597 F.2d 750 (Court of Claims, 1979)
Truong Xuan Truc v. United States
22 Cont. Cas. Fed. 80,065 (Court of Claims, 1976)
Glasgow Associates v. United States
495 F.2d 765 (Court of Claims, 1974)
H. N. Bailey & Associates v. The United States
449 F.2d 376 (Court of Claims, 1971)
United States v. Willard E. Fraser Co.
308 F. Supp. 557 (D. Montana, 1970)
L. W. Foster Sportswear Co., Inc. v. The United States
405 F.2d 1285 (Court of Claims, 1969)
Morrison-Hardeman-Perini-Leavell v. The United States
392 F.2d 988 (Court of Claims, 1968)
J. A. Jones Construction Company v. The United States
390 F.2d 886 (Court of Claims, 1968)
United States v. Sherman Gardens Company
298 F. Supp. 1332 (D. Nevada, 1967)
Amino Brothers Company, Inc. v. The United States
372 F.2d 485 (Court of Claims, 1967)
Black, Raber-Kief & Associates v. The United States
357 F.2d 355 (Court of Claims, 1966)
Black, Raber-Kief & Associates v. United States
357 F.2d 355 (Court of Claims, 1966)
Fort Sill Gardens, Inc. v. United States
355 F.2d 636 (Court of Claims, 1966)
Fort Sill Gardens, Inc. v. The United States
355 F.2d 636 (Court of Claims, 1966)
Wunderlich Contracting Company v. United States
351 F.2d 956 (D.C. Circuit, 1965)
Wunderlich Contracting Co. v. United States
351 F.2d 956 (Court of Claims, 1965)
Town of Kure Beach v. United States
168 Ct. Cl. 597 (Court of Claims, 1964)
Air Terminal Services, Inc. v. The United States
330 F.2d 974 (Court of Claims, 1964)

Cite This Page — Counsel Stack

Bluebook (online)
305 F.2d 386, 158 Ct. Cl. 455, 1962 U.S. Ct. Cl. LEXIS 190, Counsel Stack Legal Research, https://law.counselstack.com/opinion/bateson-stolte-inc-v-the-united-states-cc-1962.