WHITAKER, Judge.

Plaintiffs sue to recover extra costs incurred due to a suspension of the work for 69 days during which a change in the plans and specifications was being considered. It is stipulated that they are entitled to recover $8,727.44 on this account.

They also sue to recover for increased wages which they were required to pay common laborers, carpenters, cement finishers, and hoisting engineers.

Plaintiffs had a contract for the construction of the foundations of the Jane Addams Houses in Chicago. It was a relief project; it was intended to relieve unemployment, to provide a living wage for laborers and so to increase their purchasing power. What a living wage was, was fixed by the contract. The contractor was required to pay a minimum wage for common laborers of 82% cents an hour, and for carpenters, cement finishers, and hoisting engineers of $1.31% cents an hour. It was recognized, however, that the cost of living might increase during the progress of the work or for some other reason that the Government might find it desirable that even higher wages should be paid, and so it was provided in article 19 of the specifications that if the Federal Emergency Administrator of Public Works “establishes different wage rates, the contract price shall be adjusted accordingly. * * * ”

The contract was entered into on November 26, 1935, but defendant held up the [779]*779work until February 17, 1936, when it gave plaintiffs notice to start work; however, work was not begun until February 28, 1936, due to bad weather. While the work was under suspension the defendant on February 15, 1936, asked for bids on the construction of the building above the foundation. (Plaintiffs’ contract was for the foundation only.) This advertisement for bids required bidders to pay a minimum wage to the before-mentioned laborers higher than was provided for in plaintiffs’ contract. A successful bidder on this part of the building could not pay common laborers less than 95 cents an hour, instead of the 82% cents on the foundation contract, and could not pay carpenters, cement finishers, and hoisting engineers less than $1.50 per hour, instead of the minimum of $1.31% on the foundation contract.

Whereas on November 26, 1935, the Government thought not less than $1.31% was a fair wage for carpenters, cement finishers, and hoisting engineers, and 82% cents for common laborers, by February 15, 1936, conditions had changed to such an extent that it no longer considered these fair wages and demanded of the superstructure contractor the payment of higher wages.

Plaintiffs’ work did not commence until after this change in the wage rate. So, when they offered to pay their carpenters, cement finishers, and hoisting engineers $1.-31% and common laborers 82% cents, these men very naturally said, no, the Government has said that no less than $1.50 and 95 cents is fair; and when plaintiffs would pay no more, they struck. In order to induce them to work plaintiffs had to pay the $1.50 and 95 cents.

All the proof goes to show the laborers would not have struck except for the Government’s action in establishing a higher minimum wage on the very same building on which plaintiffs’ laborers were employed.

That they should have struck was well-nigh inevitable. They had no contract with plaintiffs to work at any fixed wage and, so, when their Government said that the least that ought to be paid for such labor was more than plaintiffs offered, of course they demanded the amount fixed by the Government as fair and refused to work for less.

So, while the defendant did not expressly demand of these plaintiffs that they pay a higher minimum wage on their contract, it nevertheless brought about conditions that made this almost inevitable, and it must have known that this would be the necessary consequence of its act. Just as effectively as though it had directly ordered plaintiffs to pay a higher wage, it indirectly required them to do so.

In LeVeque et al. v. United States, 96 Ct.Cls. 250, we held that the establishment by the Government of higher wages on another project in another part of the city did not require it to pay plaintiffs the increased wages they had to pay on their project. In that case we concluded the increase in wages paid by plaintiffs was not a necessary result of defendant’s act. Here we think it was. The increased wages in this case were on the very same building on which plaintiffs were working. The Administrator did not directly establish different minimum rates to be paid by plaintiffs, but this was the necessary consequence of what he did. He did indirectly that which if done directly would have rendered the Government liable. We are of opinion that the defendant in fact established different wage rates on plaintiffs’ job, and, therefore, it is obligated to pay the increase under article 19.

But whether or not this is so, it is an implied condition of every contract that neither party will hinder the other in his discharge of the obligations imposed upon him, nor increase his cost of performance. Restatement of the Law of Contracts, sec. 315(1); Williston on Contracts, sec. 1293A;' Anvil Mining Co. v. Humble, 153 U.S. 540, 551, 14 S.Ct. 876, 38 L.Ed. 814. It was an implied condition of this contract that the Government would not do any act that as a necessary consequence would make performance by the plaintiffs more expensive. The Government breached that implied condition by increasing the minimum wage to be paid on a part of this building, which as a necessary consequence required plaintiffs to pay more wages than those specified.

It follows that the defendant is liable for the increased wages plaintiffs had to pay.

It is said, however, that the contracting officer and head of the department have decided that the Government has fully performed its obligations under the contract, and that this decision is final under article 15 of the contract and that, therefore, this court has no jurisdiction to determine the matter.

[780]*780The defendant’s position, otherwise stated, is that the parties agreed in advance of the dispute to waive their right to sue for this breach of the contract and to leave the final determination of the controversy to the decision of one of the contracting parties.

We do not think the parties intended article 15 to have such broad scope. If they did, it is clearly illegal under numerous decisions of the Supreme Court of the United States and of other Federal courts and of the State courts. It has long been settled that any agreement made in advance of the controversy which deprives a party of recourse to the courts is contrary to public policy and, therefore, void. Home Ins. Co. v. Morse, 20 Wall. 445, 450, 22 L.Ed. 365, et seq.; Doyle v. Continental Ins. Co., 94 U.S. 535, 537, 24 L.Ed. 148; Guaranty Trust & Safe Deposit Co. v. Green Cove R. R., 139 U.S. 137, 142, 11 S.Ct. 512, 35 L.Ed. 116; Martin v. Baltimore & O. R. R., 151 U.S. 673, 684, 14 S.Ct. 533, 38 L.Ed. 311; Terral v. Burke Construction Co., 257 U.S. 529, 42 S.Ct. 188, 66 L.Ed. 352, 21 A.L.R. 186.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Fort Sill Gardens, Inc. v. United States
355 F.2d 636 (Court of Claims, 1966)
Fort Sill Gardens, Inc. v. The United States
355 F.2d 636 (Court of Claims, 1966)
Utah Construction & Mining Co. v. United States
339 F.2d 606 (Court of Claims, 1964)
Bateson-Stolte, Inc. v. The United States
305 F.2d 386 (Court of Claims, 1962)
Bateson-Stolte, Inc. v. United States
172 F. Supp. 454 (Court of Claims, 1959)
42nd Street Fotoshop, Inc. v. United States
137 F. Supp. 313 (S.D. New York, 1955)
Sunswick Corporation v. United States
75 F. Supp. 221 (Court of Claims, 1948)
Dorsey v. Oregon Motor Stages
194 P.2d 967 (Oregon Supreme Court, 1947)
George F. Driscoll Co. v. United States
63 F. Supp. 657 (Court of Claims, 1945)
United States v. Beuttas
324 U.S. 768 (Supreme Court, 1945)
York Engineering & Construction Co. v. United States
62 F. Supp. 546 (Court of Claims, 1945)
Beuttas v. United States
60 F. Supp. 771 (Court of Claims, 1944)

Cite This Page — Counsel Stack

Bluebook (online)
60 F. Supp. 771, 101 Ct. Cl. 748, Counsel Stack Legal Research, https://law.counselstack.com/opinion/beuttas-v-united-states-cc-1944.