Sunswick Corporation v. United States

75 F. Supp. 221, 109 Ct. Cl. 772
CourtUnited States Court of Claims
DecidedJanuary 5, 1948
Docket46696
StatusPublished
Cited by38 cases

This text of 75 F. Supp. 221 (Sunswick Corporation v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Sunswick Corporation v. United States, 75 F. Supp. 221, 109 Ct. Cl. 772 (cc 1948).

Opinions

LITTLETON, Judge.

Plaintiff sues to recover $11,492.93, plus overhead and profit, for increased labor costs incurred in the performance of a lump sum construction contract entered into with defendant September 21, 1944, covering a certain canal improvement and reconstruction project of the Corps of Engineers, War Department, on the St. Mary’s Falls Canal in Sault Ste. Marie, Michigan. The increased costs resulted from the payment by plaintiff of a higher wage rate to carpenters working on the .project than that specified in the contract specifications, by reason of plaintiff’s compliance with a directive order of the Wage Adjustment Board issued on January 10, 1945, directing plaintiff to pay such increased rate retroactively to the beginning of the project.

The contract specifications, prepared by defendant and upon which plaintiff relied in the preparation of its bid, fixed the minimum wage to be paid journeymen carpenters on this project at $1.25 per hour, and provided that the wage specified “shall be the maximum wages to be paid, subject, however, to Executive Order No. 9250 [50 U.S.C.A.Appendix, § 901 note], and the General Orders and Regulations issued thereunder.” Before submitting its bid plaintiff investigated the labor situation at Sault Ste. Marie, as the defendant had done, and found that the prevailing rate for carpenters was $1.25 per hour, as indicated in the specifications, and that an adequate supply of carpenters could be obtained at that rate. Relying upon this investigation and upon the wage and other provisions of the contract and specifications, plaintiff made no allowance in its bid for an increase in wage rates.

Article 17 of the contract entered into by plaintiff and defendant, following the acceptance of plaintiff’s bid, directed the contractor to pay all labor employed directly upon the site of the work at wage rates “not less or more than those stated in the specifications (subject to Executive Order Number 9250 and the General Orders and Regulations issued thereunder) regardless of any contractual relationship which may be alleged to exist between the contractor or subcontractor and such laborers and mechanics; and the scale of wages to be paid shall be posted by the contractor in a prominent and easily accessible place at the site of the work.” The contract also contained the standard Article 3, relating to changes and providing for an equitable adjustment in price.

Plaintiff commenced the contract work immediately upon the execution of the contract and during the first two weeks experienced no difficulty in obtaining a sufficient number of carpenters through the local union at $1.25 per hour. However, [223]*223on October 6, 1944, a demand was made by the union that plaintiff pay such of the carpenters as were employed on work which the union construed as “waterfront work” at the rate of $1.42% Per hour, notwithstanding there was no such classification of workers in the schedule contained in the specifications, and no such rate authorized by the contract to he paid carpenters on the project. The basis for the union’s contention that plaintiff’s carpenters were, for the most part, engaged in “waterfront work” and entitled to a higher rate of pay, is set forth in finding 10. However, the Government’s classification and the hourly wage rate fixed under the Act of August 30, 1935, 49 Stat. 1011, as amended by the Act of June 15, 1940, 54 Stat. 399, 40 U.S.C.A. §§ 276a, 276a — 1, included and covered all carpenters to be employed on the job.

Plaintiff disagreed with the union’s contention, in view of the fact that its carpenters were not working under conditions similar to those pertaining where certain other contractors on earlier occasions had agreed to the higher rate for so-called waterfront construction work, and refused throughout to agree to or to adopt a rale of pay at variance with the wage rate provisions of the specifications. The U. S. Conciliation Service of the Department of Labor having failed to negotiate a settlement of the controversy, the dispute was referred by the Secreiary of Labor to the National War Labor Board under the written stipulation of plaintiff and the union agreeing thereto, and the dispute was referred by said Board in turn to the Wage Adjustment Board in the Department of Labor to which it had delegated authority for determining such disputes. After a hearing attended by representatives of plaintiff and the local union, and by the defendant’s project manager representing the contracting officer, before a Hearing Officer, and a report by the latter to the Wage Adjustment Board, favorable to the union’s contention, the Wage Adjustment Board adopted the Hearing Officer’s recommendations over plaintiff’s objections thereto and on January 10, 1945, issued a directive order to plaintiff (finding 13) directing it to pay all carpenters employed on the project on waterfront work, as defined in said order, a wage rate of $1.42% per hour, retroactive to the beginning of the project.

Plaintiff rightly regarded the order to be obligatory upon it, notwithstanding it had consistently opposed the union’s demand from beginning to end and had submitted to the Board in writing its objections to the Hearing Officer’s recommendations. Nevertheless plaintiff, on January 22, 1945, sought the contracting officer’s formal advice on this point (finding 14), and requested confirmation from the contracting officer that plaintiff would be compensated for the extra payments ordered to be made to carpenters on the project. The contracting officer’s reply of February 27, 1945, was entirely noncommittal as regards the question of whether plaintiff was obligated to comply with the order of the Wage Adjustment Board. There was no suggestion that the order to pay the increased wages was not obligatory upon plaintiff. The contracting officer rejected any adjustment in the contract price to cover such increased costs, but the letter of rejection was not responsive to the issues raised by plaintiff’s letter and in our view did not amount to a decision on those issues by the contracting officer adverse to plaintiff’s claim. Coming from the representative of the defendant to whom the contract granted power to make equitable adjustments in the amount payable to the contractor in the event changes should be made by the Government in the specifications, it evidenced little more than indifference to the problem confronting the contractor. The contracting officer said:

Your inquiry was referred by this office to the Office, Qiief of Engineers, and that office has advised that the action of the Wage Adjustment Board is no basis for an adjustment in the price of subject contract.

This office regrets that it, therefore, has-no choice but to advise you that no adjustment can be made to compensate you for the increased wage rates of carpenters on the job.

The increased wage rate which plaintiff proceeded to pay its carpenters in com[224]*224pliance with the Wage Adjustment Board’s order increased its cost of performing its contract by a total of $11,222.91, disregarding any allowance for overhead and profit based on such additional cost.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Laudes Corp. v. United States
84 Fed. Cl. 298 (Federal Claims, 2008)
Sinclair v. United States
49 Fed. Cl. 274 (Federal Claims, 2001)
United States v. Winstar Corp.
518 U.S. 839 (Supreme Court, 1996)
Walter Dawgie Ski Corp. v. United States
39 Cont. Cas. Fed. 76,583 (Federal Claims, 1993)
Winstar Corp. v. United States
25 Cl. Ct. 541 (Court of Claims, 1992)
Hughes Communications Galaxy, Inc. v. United States
37 Cont. Cas. Fed. 76,307 (Court of Claims, 1992)
Emerald Maintenance, Inc. v. The United States
925 F.2d 1425 (Federal Circuit, 1991)
IBI Security Service, Inc. v. United States
35 Cont. Cas. Fed. 75,740 (Court of Claims, 1989)
Chevron Chemical Corp. v. United States
32 Cont. Cas. Fed. 72,756 (Court of Claims, 1984)
South Louisiana Grain Services, Inc. v. United States
30 Cont. Cas. Fed. 70,493 (Court of Claims, 1982)
Meaott Construction Corp. v. Ross
76 A.D.2d 137 (Appellate Division of the Supreme Court of New York, 1980)
Morrison-Hardeman-Perini-Leavell v. The United States
392 F.2d 988 (Court of Claims, 1968)
J. A. Jones Construction Company v. The United States
390 F.2d 886 (Court of Claims, 1968)
Amino Brothers Company, Inc. v. The United States
372 F.2d 485 (Court of Claims, 1967)
Black, Raber-Kief & Associates v. The United States
357 F.2d 355 (Court of Claims, 1966)
Black, Raber-Kief & Associates v. United States
357 F.2d 355 (Court of Claims, 1966)
Air Terminal Services, Inc. v. The United States
330 F.2d 974 (Court of Claims, 1964)
Freedman v. United States
162 Ct. Cl. 390 (Court of Claims, 1963)

Cite This Page — Counsel Stack

Bluebook (online)
75 F. Supp. 221, 109 Ct. Cl. 772, Counsel Stack Legal Research, https://law.counselstack.com/opinion/sunswick-corporation-v-united-states-cc-1948.