Clemmer Const. Co. v. United States

71 F. Supp. 917, 108 Ct. Cl. 718, 1947 U.S. Ct. Cl. LEXIS 38
CourtUnited States Court of Claims
DecidedJune 2, 1947
Docket47576
StatusPublished
Cited by16 cases

This text of 71 F. Supp. 917 (Clemmer Const. Co. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Clemmer Const. Co. v. United States, 71 F. Supp. 917, 108 Ct. Cl. 718, 1947 U.S. Ct. Cl. LEXIS 38 (cc 1947).

Opinion

MADDEN, Judge.

The Government has demurred to the plaintiff’s petition. According to the petition, the plaintiff, after competitive bidding, was awarded a contract for the erection of a war housing project at Akron, Ohio. The project was to contain 90 buildings, with 500 apartment units. The contract was dated February 6, 1943, and the plaintiff’s compensation was to be two fixed sums, one for labor and one for materials. The Government’s invitation for bids, and the contract, when signed, specified the wage rates to be paid on the contract, and the contract required that time and one-half be paid for work in excess of 40 hours per week.

The petition says that on February 9, 1943, the President of the United States issued Executive Order Feb. 9, 1943, No. 9301, the full text of which is given in a *918 footnote. 1 Its effect was to fix a minimum work week of 48 hours for the duration of the war, to direct all agencies of the Federal Government to require their contractors to comply with the order, and with the further directives of the Chairman of the War Manpower Commission pursuant to the Executive Order. Section 5 of the Executive Order said that it should not be construed as superseding any statute or contract requiring the payment of overtime after a specified number of hours worked in a week.

The War Manpower Commission specified the Akron, Ohio, area as one in which the 48 hour week should be worked, commencing April 1, 1943. The Government’s contracting officer, who had signed the contract with the plaintiff, notified the plaintiff that it must comply with the orders described above. The plaintiff protested because the payment of time and one-half for the eight hours of work in excess of 40 hours would increase its costs. In computing its bid for the contract the plaintiff anticipated a 40' hour work week with no overtime requiring premium pay. The plaintiff, however, complied with the orders fixing a 48, hour work week and the additional cost of compliance was $40,459.-68, for which the plaintiff sues.

The petition also says that the complete control of the allocation, purchase and use of the materials and supplies necessary to complete the contract was vested in the United States, by virtue of certain statutes; that it bid upon and entered into the contract relying on its ability to purchase the necessary supplies in the open market; that it was issued a priority rating of “A. A. 3”, which was not sufficiently high to enable it to secure its required lumber and fibre board from wholesale dealers in the regular way; that it repeatedly requested the contracting officer to obtain a higher priority rating for the project, but that that officer failed to do so. The petition says that because of its low priority rating it had to purchase lumber and fibre board in small quantities from retainers and haul them to the project, at an additional cost of $9,190.17.

*919 The plaintiff says that the United States, by its conduct in regard to the minimum work week, and the priority rating of materials, violated its implied obligation in the contract not to do anything to make more burdensome or expensive the performance of the contract by the plaintiff. It says that it protested these matters to the contracting officer, who ruled against the plaintiff, and that, under Article 15 of the contract, it appealed in writing to the head of the department, which affirmed this adverse ruling. It says that both these decisions were “arbitrary, erroneous, unfair and contrary to law and constituted the taking of property without due process of law.”

The full text of the contract is attached to the petition as an exhibit.

The Government’s demurrer is based upon the proposition that the acts of the Government which are alleged to have harmed the plaintiff are acts done by the Government in its sovereign capacity, rather than in its capacity as a contractor.

The Government invokes the ruling of the Supreme Court in Horowitz v. United States, 267 U.S. 458, 45 S.Ct. 344, 69 L.Ed. 736, and the decisions of this court in the early cases of Deming v. United States, 1 Ct.Cl. 190, and Jones v. United States, 1 Ct. Cl. 383, to the effect that no action lay for such conduct of the Government. It also cites our recent decisions in Gothwaite v. United States, 102 Ct.Q. 400; Standard Accident Insurance Co. v. United States, 59 F.Supp. 407, 103 Ct.Cl. 607, certiorari denied 326 U.S. 729, 66 S.Ct. 37, 90 L.Ed. 434; Barbour & Sons v. United States, 63 F.Supp. 349, 104 Ct.Cl. 360, and Hall-man et al. v. United States, 68 F.Supp. 204, 107 Ct.Cl. 555.

We think that the Government’s defense is valid. The President’s Executive Order No. 9301 relating to the work week was applied by the War Manpower Commission to some 150 areas within the United States. We suppose that so many areas, of which Akron was one, would include all of the areas of industrial importance in the country. There was, then, no lack of generality in its application. It was law for those parts of the country where such law was needed or useful. The plaintiff and no doubt many others who had contracts with governments or private enterprises were harmed by it. Persons are frequently subjected to increased costs by regulatory laws. But, under the doctrine asserted here by the Government, and now apparently well settled, the Government is not liable for such harms.

The same observations apply to the plaintiff’s difficulties about priorities. The application of a system of priorities in the uses to which materials could be put in wartime was a necessary and sovereign act of the Government which, no doubt, harmed countless persons, who, like the plaintiff, have no right to recover for their harms.

The plaintiff’s allegation that the decisions of the Government officers on its claim were arbitrary "and unfair are mere conclusions which are not borne out by the allegations of fact in its petition.

The, plaintiff, in its brief, points to Section 27 of the General Conditions of its contract, which said: If any sales tax, processing tax, adjustment charge, or other taxes or charges are imposed or charged by the Congress after the date stated in this contract, and made applicable directly upon the production, manufacture or sale of the supplies covered by this contract, and are paid by the Contractor * * *, then the prices named in this contract will be increased * * *.

The plaintiff urges that, because Congress had authorized the President to issue Executive orders such'as the ones here in question, the contract required that the additional costs resulting therefrom be added to the contract price. We think that the quoted section of the contract was not applicable. Apart from the question of whether this was an action of Congress, within the meaning of the contract, we think it cannot be said that any additional charges were imposed and were made “applicable directly” upon the production, manufacture or sale of the supplies covered by the contract. The additional labor cost, if any, would result from the Executive order only if a contractor had planned to work only 40 hours a week and then *920

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Walter Dawgie Ski Corp. v. United States
39 Cont. Cas. Fed. 76,583 (Federal Claims, 1993)
The Metrig Corporation v. The United States
427 F.2d 778 (Court of Claims, 1970)
Metrig Corp. v. United States
427 F.2d 778 (Court of Claims, 1970)
Borg-Warner Corp. v. United States
89 F. Supp. 1013 (Court of Claims, 1950)
Ottinger v. United States
88 F. Supp. 881 (Court of Claims, 1950)
J. B. McCrary Co. v. United States
84 F. Supp. 368 (Court of Claims, 1949)
Piggly Wiggly Corporation v. United States
81 F. Supp. 819 (Court of Claims, 1949)
Edward P. Stahel & Co. v. United States
78 F. Supp. 800 (Court of Claims, 1948)
Beuttas v. United States
77 F. Supp. 933 (Court of Claims, 1948)
E. & F. Construction Co. v. United States
75 F. Supp. 460 (Court of Claims, 1948)
Sunswick Corporation v. United States
75 F. Supp. 221 (Court of Claims, 1948)
Alger-Rau, Inc. v. United States
75 F. Supp. 246 (Court of Claims, 1948)
C. B. Ross Co. v. United States
74 F. Supp. 420 (Court of Claims, 1947)

Cite This Page — Counsel Stack

Bluebook (online)
71 F. Supp. 917, 108 Ct. Cl. 718, 1947 U.S. Ct. Cl. LEXIS 38, Counsel Stack Legal Research, https://law.counselstack.com/opinion/clemmer-const-co-v-united-states-cc-1947.