Metrig Corp. v. United States

427 F.2d 778, 192 Ct. Cl. 515
CourtUnited States Court of Claims
DecidedJune 12, 1970
DocketNo. 318-65
StatusPublished

This text of 427 F.2d 778 (Metrig Corp. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Metrig Corp. v. United States, 427 F.2d 778, 192 Ct. Cl. 515 (cc 1970).

Opinion

Per Curiam:

This case was referred to Trial Commissioner Mastín Gr. White with directions to make findings of fact and recommendation for conclusions of law under the order of reference and Buie 134(h). The commissioner has done so in an opinion and report filed on September 18, 1969. Exceptions to the commissioner’s conclusions were filed by plaintiff which urged that his recommendations be reversed in their entirety. Defendant has requested that the court accept the commissioner’s report and dismiss the petition as recommended. The case has been submitted to the court on oral argument of counsel and the briefs of the parties. Since the court agrees with the commissioner’s opinion, findings and recommended conclusion of law, as hereinafter set forth, it hereby adopts the same as the basis for its judgment in this case. Therefore, plaintiff is not entitled to recover and the petition is dismissed.

OPINION OP COMMISSIONER

White, Commissioner: This case arose in connection with the performance by the plaintiff of Housing Contract No. DA-08-123-ENG-3261 (“the contract”), under which the plaintiff constructed for the defendant (represented by the Corps of Engineers, Department of the Army) a 150-unit housing project at Fort Allen, a military installation located near Ponce, Puerto Bico. The contract was entered into between the parties on April 28, 1961, in accordance with the provisions of the Capehart Act (42 TJ.S.C. §§ 1594-1594Í .and 12 TJ.S.C. §§ 1748-I748g (1958)).

It is my opinion that the plaintiff is not entitled to recover in the present action.

In attempting to state a cause of action, the plaintiff alleged in the petition that “the contract, as advertised for and as awarded by the defendant, contained a schedule of prevailing rates of wages * * * and represented that said scale of wages were the prevailing wages in the area”; that “the representations as made by the defendant were erroneous and, at the best, were mistaken; and at the worst, were a deliberate misrepresentation of the facts”; that the plaintiff “relied upon the representations * * * and based its bid and entered into the contract with the defendant in reliance upon the scale of [519]*519wages as therein set forth”; and that “after plaintiff entered into the contract, the defendant required plaintiff to pay a much higher scale of wages than that provided in the contract * *

The “schedule of prevailing rates of wages” referred to in the petition was set out in the contract specifications pursuant to the provisions of the Davis-Bacon Act. That act provided in part at the time (with exceptions not material here) that each Government construction contract should contain a provision requiring the contractor to pay all mechanics and laborers employed directly upon the site of the work wages computed at rates not less than those stated in the contract specifications, “which shall be based upon the wages that will be determined by the Secretary of Labor to be prevailing for the corresponding classes of laborers and mechanics employed on projects of a character similar to the contract work in the city, town, village, or other civil subdivision * * * in which the work is to be performed * * *” (40 U.S.C. § 276a (1958)).

On the basis of determinations made by the Secretary of Labor respecting the wage rates for laborers and mechanics prevailing in the locality where the work under the contract was to be performed, the contract specifications provided in paragraph SC-7 that the “minimum wages” to be paid laborers and mechanics on the project should be based upon “minimum rates” per hour of, mter alia, 77 cents for unskilled laborers, 90 cents for carpenters’ helpers, 90 cents for mason tenders, 90 cents for mortar mixers, and 90 cents for brush (water) painters.

The plaintiff did not, at the trial of the case, present any evidence to support the allegations in the petition that the determinations by the Secretary of Labor with respect to the prevailing wage rates in the vicinity where the work under the contract was to be performed were “erroneous,” or “mistaken,” or “a deliberate misrepresentation of the facts.” Therefore, since official actions are presumed to be correct, it must be concluded that the scale of minimum wage rates set out in paragraph SC-7 of the contract specifications was based upon correct determinations made by the Secretary of Labor with respect to the wage rates actually prevailing for [520]*520the respective classes of laborers and mechanics in the vicinity of Fort Allen.

The plaintiff did introduce at the trial evidence showing that while the work under the contract was in progress the Wage and Hour Division of the Department of Labor informed the plaintiff and Cross Construction Corporation (“Cross”), the plaintiff’s subcontractor for the concrete and masonry work, that their operations under the contract were subject to the provisions of the Fair Labor Standards Act of 1938; and that the plaintiff and Cross were ultimately required by the Wage and Hour Division to comply with the Fair Labor Standards Act by paying all their workmen wage rates at least equal to the minimum rate prescribed under that act.

At the time involved in this case, the Fair Labor Standards Act provided, inter alia, for the issuance from time to time by the Administrator of the Wage and Hour Division, Department of Labor, of wage orders prescribing the minimum rate or rates of wages which employers in Puerto Rico engaged in interstate or foreign commerce were required to pay their workmen (29 U.S.C. § 208 (1958)). The minimum wage rate prescribed by the Administrator for the construction industry in Puerto Rico was $1.00 per hour from the time when the work under the contract was commenced until November 3, 1961, when the minimum rate was increased to $1.15 per hour.

As previously indicated, certain of the minimum wage rates set out in the contract specifications, pursuant to determinations by the Secretary of Labor respecting the wage rates prevailing in the locality where the work was to be performed, were less than $1.00 per hour. Since the plaintiff and Cross had expected to pay their workmen wages in accordance with the minimum rates prescribed in the contract specifications, the requirement that they comply with the provisions of the Fair Labor Standards Act by paying at least $1.00 per hour up until November 3, 1961, and at least $1.15 per hour thereafter, increased the labor costs of the plaintiff and Cross with respect to certain classes of workmen.

It must be noted, however, that paragraph SC-7 of the contract specifications merely prescribed mvrwrvum wage rates [521]*521below which the plaintiff and its subcontractors could not go in employing laborers and mechanics for the performance of work under the contract. Paragraph SC-7 was not an assurance or a representation by the defendant that the plaintiff and its subcontractors would not have to pay any wage rates higher than those listed in the paragraph. Morrison-Hardeman-Perini-Leavell v. United States, 183 Ct. Cl. 938, 949, 392 F. 2d 988, 995 (1968).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Horowitz v. United States
267 U.S. 458 (Supreme Court, 1925)
United States v. Binghamton Construction Co.
347 U.S. 171 (Supreme Court, 1954)
Morrison-Hardeman-Perini-Leavell v. The United States
392 F.2d 988 (Court of Claims, 1968)
Clemmer Const. Co. v. United States
71 F. Supp. 917 (Court of Claims, 1947)
Anthony P. Miller, Inc. v. United States
161 Ct. Cl. 455 (Court of Claims, 1963)

Cite This Page — Counsel Stack

Bluebook (online)
427 F.2d 778, 192 Ct. Cl. 515, Counsel Stack Legal Research, https://law.counselstack.com/opinion/metrig-corp-v-united-states-cc-1970.