Piggly Wiggly Corporation v. United States

81 F. Supp. 819, 112 Ct. Cl. 391, 1949 U.S. Ct. Cl. LEXIS 13
CourtUnited States Court of Claims
DecidedJanuary 3, 1949
Docket46249
StatusPublished
Cited by25 cases

This text of 81 F. Supp. 819 (Piggly Wiggly Corporation v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Piggly Wiggly Corporation v. United States, 81 F. Supp. 819, 112 Ct. Cl. 391, 1949 U.S. Ct. Cl. LEXIS 13 (cc 1949).

Opinion

HOWELL, Judge.

This is an action arising out of a contract dated February 22, 1943, between plaintiff and defendant, acting through the Quartermaster Corps, War Department, whereby plaintiff agreed to furnish and deliver 50,000 plywood lockers ifor a cost of $4.60 each, or a total of $230,000.00. On August 23, 1943, the parties entered into a supplemental agreement, which modified the delivery schedule in .the original contract and extended the final date of delivery .from August 31, 1943, to November 30, 1943. On September 30, 1943, .pursuant to Article 12 of the contract (set forth in finding 3), the contract was terminated for the convenience of the Government. Prior to the 'effective date of .termination, the plaintiff had delivered 45,027 of the lockers called for in the contract and the agreement was terminated as to the balance of 4,973 lockers.

Plaintiff seeks recovery on three separate claims in the aggregate amount of $15,403.82. The first claim is on an alleged breach of contract arising out of def'endanf's failure to make timely allocations of plywood from manufacturers. Plaintiff asks judgment for $4,034.43 on this claim. Plaintiff’s second claim is to recover $4,567.32, which represents the additional cost of plywood due to an increase in the ceiling prices 'authorized by the Office of Price Administration .after .the contract was entered into. Plaintiff’s third claim is for termination costs, expenses, and prospective profits on -the unfinished portion of the terminated contract in the ■amount of $6,802.07. Defendant ha-d allowed plaintiff the sum of $2,544.50 on its termination claim but plaintiff refused to accept .that amount, and, pursuant to Section 13(b) of the Contract Settlement Act of 1944, 41 U.S.C.A. § 113(b), brings its ■suit in this court with respect to its termination claim. In addition, plaintiff asks judgment for certain legal and accounting 'fees incurred in connection with its suit in this court.

Claim ifor additional cost of plywood .panels bought at distribution warehouses

Plaintiff’s first claim is for damages in the amount of $4,034.43 resulting from .the alleged failure of defendant to make plywood panels available from manufacturers by allocation when needed. The amount of damages represents the increased cost to plaintiff of plywood purchased from distribution warehouses where plaintiff purchased the material in order to meet the contract delivery schedule. Plaintiff’s 'bid was .based on the price of plywood at the mills, which was 20% less than at the •distribution warehouses.

Plaintiff alleges that defendant specifically obligated itself in the contract to make plywood available to the plaintiff 'from the manufacturers, and .that its delay in so doing constituted a breach of the contract. 1

In passing on plaintiff’s claim we must first determine what defendant promised, ■either expressly or impliedly, to do, and *821 second, - whether defendant delayed in carrying out its undertaking.

Plaintiff’s bid contained the following statement:

Offering of making these boxes is contingent upon the supply of fir plywood required being made available through 'allocation to those plywood manufactureros making these type panels.

This statement contains two important elements : first,- it expects the government to make the plywood available through allocation, and second, it expects such plywood to come only from manufacturers.

The government’s letter accepting plaintiff’s bid responded to plaintiff’s condition quoted above, as follows:

This office will obtain for your suppliers of the plywood necessary for you to perform this contract, a release from the Chief of Engineers, in the event that any ■of your suppliers find that such action is necessary. If such a release is -necessary, •it is requested that such supplier wire this -office the amount and -description of board feet contracted for by you for your performance -of the above numbered contract.

The above acceptance is clearly not in the terms of plaintiff’s offer. At .best it is a promise that the government would, upon request -of plaintiff’s suppliers, obtain -releases to en-able such suppliers to deliver the plywood to plaintiff. It -does not promise to supply -the plaintiff with plywood, nor does it -promise that the supplier shall be the manufacturers of plywood rather than some other type of supplier. Plaintiff did not object to the form of defendant’s acceptance. The formal contract -contained no provision embodying the matters referred to.

Assuming (without deciding) the language in defendant’s acceptance letter .to be -a -contract commitment to obtain .the necessary -releases or allocations from suppliers -designated by plaintiff, we now turn to -the question as to whether or not -defendant wa-s guilty of delay in carrying -out such -commitment so as to damage the .plaintiff. After acceptance of its .bid, plaintiff, equipped with a AA-1 priority, and without requesting defendant to make an allocation, attempted to purchase plywood directly from the western manufacturers. On being informed that no plywood was then available for ¡shipment, plaintiff -bought -a carload -of plywood -from a distribution warehouse, in Chicago at a ■price approximately 20 percent higher than the -mill price. On January 28, 1943, .plaintiff asked the contracting officer at Memphis, Tennessee, to assist it in obtaining the plywood from the mills. The -contracting officer -assured plaintiff that every effort would be made t-o help it, and certain information was requested which plaintiff supplied. On February 27, 1943, one month following plaintiff’s request, the Central Procuring Agency succeeded in obtaining a .bid -from a supplier and issued a -purchase allocation in favor of -plain-tiff for 249,000 of the 1,062,400 square feet of plywood needed by ¡plaintiff. Because -of the acute shortage -of plywo-od at that time -and the large number of requests for allocations, the average time between a request and the issuance of an allocation was from 40 to 45 days. It thus appears that plaintiff’s first allocation was -issued in considerably less than the average time. In late April of that year, three additional allocations were issued -for the balance of the plywood needed by plaintiff, one of which was 'cancelled -on June 25th -because the mill in question was unable to make delivery.

We -see nothing in the .facts just related indicating any delay on ¡the part -of the government in obtaining allocations of .plywood for the .benefit of .plaintiff. Plaintiff, however, ¡says that 25,000,000 -feet of plywood per month was 'allocated in February or March 1943, to various -government contractors. From this, plaintiff argues that defendant could have made the •requested allocations -in time to enable plaintiff to meet its deliveries promptly without resorting to purchases from warehouses. Plaintiff -bases this argument -on *822 the .premise that defendant was obligated to make allocations of plywood to plaintiff without regard .to the needs of other contractors for this material. We find nothing in the contract nor in the government’s acceptance of the plaintiff’s bid to indicate any such unqualified obligation on the part of the government.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Lake Borgne Basin Levee District v. United States
127 Fed. Cl. 321 (Federal Claims, 2016)
First Federal Savings & Loan Ass'n v. United States
88 Fed. Cl. 572 (Federal Claims, 2009)
Chevron U.S.A., Inc. v. United States
71 Fed. Cl. 236 (Federal Claims, 2006)
Ford Motor Co. v. United States
56 Fed. Cl. 85 (Federal Claims, 2003)
Franklin Federal Savings Bank v. United States
55 Fed. Cl. 108 (Federal Claims, 2003)
LaSalle Talman Bank, F.S.B. v. United States
45 Fed. Cl. 64 (Federal Claims, 1999)
Winstar Corp. v. United States
994 F.2d 797 (Federal Circuit, 1993)
Winstar Corporation v. United States
994 F.2d 797 (Federal Circuit, 1993)
Reliance Insurance v. United States
36 Cont. Cas. Fed. 75,892 (Court of Claims, 1990)
Tony Downs Foods Co. v. United States
530 F.2d 367 (Court of Claims, 1976)
Calhoun v. United States
453 F.2d 1385 (Court of Claims, 1972)
J. A. Jones Construction Company v. The United States
390 F.2d 886 (Court of Claims, 1968)
Anthony P. Miller, Inc. v. United States
161 Ct. Cl. 455 (Court of Claims, 1963)
Byrns v. United States
121 Ct. Cl. 266 (Court of Claims, 1952)
Hanson v. United States
92 F. Supp. 972 (Court of Claims, 1950)
Edelman v. United States
91 F. Supp. 729 (Court of Claims, 1950)

Cite This Page — Counsel Stack

Bluebook (online)
81 F. Supp. 819, 112 Ct. Cl. 391, 1949 U.S. Ct. Cl. LEXIS 13, Counsel Stack Legal Research, https://law.counselstack.com/opinion/piggly-wiggly-corporation-v-united-states-cc-1949.