Ford Motor Co. v. United States

56 Fed. Cl. 85, 2003 U.S. Claims LEXIS 75, 2003 WL 1848655
CourtUnited States Court of Federal Claims
DecidedApril 1, 2003
DocketNo. 99-121C
StatusPublished
Cited by2 cases

This text of 56 Fed. Cl. 85 (Ford Motor Co. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ford Motor Co. v. United States, 56 Fed. Cl. 85, 2003 U.S. Claims LEXIS 75, 2003 WL 1848655 (uscfc 2003).

Opinion

OPINION

MEROW, Senior Judge.

Ford Motor Company has commenced this suit against the United States, based on a World War II contract, to obtain a judgment for the over $7,000,000.00 it has paid as its share of the environmental clean-up costs for the Willow Run, Michigan factory site where it built B-24 bombers from 1942 — 1944. The parties have filed dispositive motions.

FACTS

On September 26, 1941, a cost-plus-fixed-fee supply contract (No. W535-ac-21216) (“Contract No. 21216”) to manufacture and deliver 795 B-24E airplanes with spare parts at a total estimated cost of $218,625,000.00 was entered into between the Army Air Force and Ford Motor Company. By supplemental agreement the number of airplanes was increased to 1,495 and the total estimated cost increased to $429,812,500.00. The contract was to be performed at the Willow Run Site where Ford commenced to build a manufacturing facility which it conveyed to the Government. The Government, in turn, leased the facility back to Ford for its completion and operation. At the site, [87]*87Ford also built a dual purpose waste water treatment plant to handle both industrial and sanitary wastes. In 1942, Ford built a sludge lagoon formed by constructing an earthen dam at the end of a natural ravine to accept sludge, from acid-cyanide plating, which was deposited from waste water treatment plant operations.

Article 3 “Consideration” of Contract No. 21216 provided for the payment of the costs incurred by Ford in performing the contract plus a fixed fee. Article 3(b) provided, “[f]or purposes of determining the amounts payable to Contractor under this contract, allowable items of cost will be determined by the Contracting Officer in accordance with regulations for the determination of the cost of performing a Government contract as promulgated by the Treasury Department in Section 26.9 of Chapter I of Title 26 of Code of Federal Regulations, as contained in T.D. 5000 and approved by the Secretary of War August 2nd, 1940,----”1

Article 3(b), as amended by Supplemental Agreement No. 4, dated April 11, 1942, also listed some fourteen categories of costs which would be allowable, such as:

¿k ijc >}c

(12) If upon the termination or completion of this contract, the Contractor shall be required to pay additional taxes or contributions pursuant to the Unemployment Compensation Act of the State of Michigan, by reason of the effect on the experience index of the Contractor, arising out of the discharge of persons on account of such termination or completion, then such additional taxes or contributions shall, to the extent that such allowance may be lawful, be allowable as an item of cost hereunder;
(13) Cost of such bonds and insurance as the Contracting Officer may approve or require and cost and expenses incurred in the defense and/or discharge of such claims of others on account of death or bodily injury of persons or loss or destruction of or damage to property as may arise out of or in connection with the performance of the work under this contract shall be an allowable item of cost hereunder, provided that such reimbursement shall not include any amount for which the Contractor is indemnified or compensated by insurance or otherwise, or any amount for which it would have been so indemnified or compensated except for the failure of the Contractor to procure or maintain bonds or insurance in accordance.with the requirements of the Contracting Officer. The foregoing shall not restrict the right of the Contractor to be reimbursed for the cost of insurance covering the Contractor’s property or property for which the Contractor is responsible to someone other than the Government and which is used or to be used in the performance of this contract.

$ $ ^

Article 9 of Contract No. 21216, “Termination of Contract by Government” provided, upon termination action by the Government, for the payment of Ford’s unreimbursed incurred costs, as determined in accordance with Article 3 of the contract, and a portion of the fixed fee to be determined on the basis of a ratio between incurred costs and estimated net costs to fully perform the contract. Upon a failure of the Contractor and the Contracting Officer to agree on the estimated net costs to perform the contract, Article 9 provided that, “said estimate shall be determined in the manner provided in this contract for the adjustment of claims and disputes.” With respect to costs, Article 9(b)-(c) provided:

(b) Upon the termination of this contract as hereinbefore provided, full and complete settlement of all claims of the Contractor arising out of this contract shall be made as follows:
(1) The Government shall assume and become liable for all obligations, commitments and claims that the Contractor may have theretofore in good faith undertaken or incurred in connection with said work and in accordance with the provisions of this contract; and the Con[88]*88tractor shall, as a condition to receiving the payments mentioned in this Article, execute and deliver all such papers and take all such steps as the Contracting Officer may require for the purpose of assuring to the Government, so far as possible, the rights and benefits of the Contractor under such obligations or commitments.
(2) The Government shall reimburse the Contractor for all costs incurred by the Contractor in the partial performance of this contract as determined in accordance with Article 3 and not previously reimbursed.
(3) The Government shall reimburse the Contractor for such further expenditures after the date of termination for the protection of Government property and for accounting services in connection with the settlement of this contract as the Contracting Officer may approve.
^ ^
(5) The obligation of the Government to make any of the payments required by this Article shall be subject to any unsettled claims for labor or material or any claim the Government may have against the Contractor.

(c) Upon the making of said payments all obligations of the Government to make further payments or to carry out other undertakings hereunder shall cease forthwith and forever, except that all rights and obligations of the respective parties under the articles, if any, of this contract applicable to Patent Infringements and Reproduction Rights shall remain in full force and effect.

Contract No. 21216 contained a “Disputes” article as follows:

Article 16 Disputes

Except as otherwise specifically provided in this contract, all disputes concerning questions of fact arising under this contract shall be decided by the Contracting Officer, subject to written appeal by the Contractor within 30 days to the head of the department concerned or his duly authorized representative, whose decision shall be final and conclusive upon the parties hereto. In the meantime, the Contractor shall diligently proceed with performance.

Finally, Article 20 of Contract No. 21216, included a notification provision as follows:

Article 20 Insurance

* * *

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Ford Motor Company v. United States
378 F.3d 1314 (Federal Circuit, 2004)

Cite This Page — Counsel Stack

Bluebook (online)
56 Fed. Cl. 85, 2003 U.S. Claims LEXIS 75, 2003 WL 1848655, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ford-motor-co-v-united-states-uscfc-2003.