Utah Const. and Development Co., Inc. v. Reynolds Elec. & Engineering Co., Inc.

951 F.2d 1261, 1991 U.S. App. LEXIS 32526, 1991 WL 268805
CourtCourt of Appeals for the Tenth Circuit
DecidedDecember 12, 1991
Docket90-4127
StatusPublished

This text of 951 F.2d 1261 (Utah Const. and Development Co., Inc. v. Reynolds Elec. & Engineering Co., Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Tenth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Utah Const. and Development Co., Inc. v. Reynolds Elec. & Engineering Co., Inc., 951 F.2d 1261, 1991 U.S. App. LEXIS 32526, 1991 WL 268805 (10th Cir. 1991).

Opinion

951 F.2d 1261

NOTICE: Although citation of unpublished opinions remains unfavored, unpublished opinions may now be cited if the opinion has persuasive value on a material issue, and a copy is attached to the citing document or, if cited in oral argument, copies are furnished to the Court and all parties. See General Order of November 29, 1993, suspending 10th Cir. Rule 36.3 until December 31, 1995, or further order.

UTAH CONSTRUCTION AND DEVELOPMENT COMPANY, INC., a Utah
corporation, Plaintiff-Appellee,
v.
REYNOLDS ELECTRICAL & ENGINEERING CO., INC., a Texas
corporation, Defendant-Appellant,
and
XYZ Surety Corportion, Defendant.

No. 90-4127.

United States Court of Appeals, Tenth Circuit.

Dec. 12, 1991.

Before HOLLOWAY, MCWILLIAMS and TACHA, Circuit Judges.

ORDER AND JUDGMENT*

TACHA, Circuit Judge.

Defendant-appellant Reynolds Electrical & Engineering Company, Inc. (REECo) appeals the district court's order granting summary judgment to plaintiff Utah Construction and Development Company, Inc. (UCD) and denying REECo's motion for summary judgment. On appeal, REECo argues that the district court misinterpreted the contract's language and that, interpreted correctly, the contract required UCD to absorb the cost of increased wages caused by REECo's renegotiation of wage rates. We exercise jurisdiction under 28 U.S.C. § 1291, and we affirm the district court's order.

REECo is a Management and Operating Contractor under contract with the United States Department of Energy. At issue in this case are two subcontracts between REECo and UCD, a REECo subcontractor. During the course of UCD's performance of the subcontracts, REECo negotiated an increase in the wage rates paid to several classes of workers. UCD paid the increased wage rates and informed REECo that it considered the payment to be pursuant to a "change order" under the terms of the subcontracts. When REECo refused to compensate UCD for the increased costs, UCD sued for equitable reimbursement. After reviewing the contract provisions, the district court entered summary judgment in favor of UCD, holding that UCD was entitled to reimbursement.

We review summary judgment orders de novo, using the same standards the district court applies. Osgood v. State Farm Mut. Ins. Co., 848 F.2d 141, 143 (10th Cir.1988). Summary judgment is appropriate "if the pleadings, depositions, answers to interrogatories, and admissions on file, together with affidavits, if any, show that there is no genuine issue as to any material fact and that the moving party is entitled to a judgment as a matter of law." Fed.R.Civ.P. 56(c); see Anderson v. Liberty Lobby, 477 U.S. 242, 247-48 (1986). We review de novo legal questions of contract interpretation. Teton Exploration Drilling, Inc. v. Bokum Resources Corp., 818 F.2d 1521, 1526 (10th Cir.1987).

Three contract provisions, identical in both subcontracts, are at issue in this case. The first is referred to as the firm price clause:

The above price is firm and not subject to escalation from or on account of any cost or matter whatsoever, and shall be inclusive of all elements of profit, overhead, wages, fringe benefits, transportation, equipment supplies, materials, insurance, licenses, taxes and costs of whatever kind, including final clean-up of the premises, applicable to this transaction.

The second clause, quoted in relevant part, is the subcontracts' "changes clause":

a. The contractor may at any time, without notice to the sureties, by written order designated or indicated to be a change order, make any change in the work within the general scope of the subcontract including, but not limited to, changes:

1. In the specifications (including drawings and designs);

2. In the method or manner of performance of the work;

3. In the government-furnished facilities, equipment, materials, services or site; or

4. Directing acceleration in the performance of the work.

b. Any other written order or an oral order (which terms as used in this paragraph (b) shall include direction, instruction, interpretation or determination) from the contractor, which causes any such change, shall be treated as a change order under this article; provided that the subcontractor gives the contractor written notice stating the date, circumstances and source of the order and that the subcontractor regards the order as a change order.

....

d. If any change under this article causes an increase or decrease in the subcontractor's cost of, or the time required for, the performance of any part of the work under this subcontract whether or not changed by any order, an equitable adjustment shall be made and the subcontract modified in writing accordingly.

Finally, a rider--Rider No. 9--was attached to the subcontracts and reads in pertinent part as follows:

The Subcontractor agrees to comply fully with the terms and provisions of the following Project Labor Agreements for Construction between REYNOLDS ELECTRICAL & ENGINEERING CO., INC., and the Unions listed hereafter. Under the terms of this Rider No. 9, the Subcontractor is required to pay in strict accordance with the amounts listed in said Labor Agreements for hourly wages, fringe benefits, and subsistence. The Subcontractor also agrees to comply strictly with all other terms and conditions of said Labor Agreements.

REECo contends that the firm price clause, which specifically mentions wages and fringe benefits, requires UCD to absorb the increased wages. When read alone, the clause may support such a contention. However, when interpreting a contract, we read the contract as a whole and attempt to construe the various contract clauses consistently. See D. Moody & Co., Inc. v. United States, 5 Cl.Ct. 70 (1984). We agree with the district court that, when the clauses are read together, the changes clause is a specific exception to the broader firm price clause. To read the two clauses otherwise would deprive the changes clause of any meaning.

We next address whether the increase in wage rates constituted a "change" that was "ordered" by REECo. The changes clause contains a nonexclusive list of things that constitute "changes," including requests by the contractor to alter specifications, the method or manner of performance, equipment or materials used, or the rate of performance of the subcontract. Although the changes clause does not specifically mention wage increases, we conclude that wage increases ordered by the contractor fall into paragraph (b)'s general category of "[a]ny other written order or an oral order ...

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Anderson v. Liberty Lobby, Inc.
477 U.S. 242 (Supreme Court, 1986)
Sunswick Corporation v. United States
75 F. Supp. 221 (Court of Claims, 1948)
D. Moody & Co. v. United States
32 Cont. Cas. Fed. 72,390 (Court of Claims, 1984)

Cite This Page — Counsel Stack

Bluebook (online)
951 F.2d 1261, 1991 U.S. App. LEXIS 32526, 1991 WL 268805, Counsel Stack Legal Research, https://law.counselstack.com/opinion/utah-const-and-development-co-inc-v-reynolds-elec-engineering-co-ca10-1991.