Amino Brothers Company, Inc. v. The United States

372 F.2d 485, 178 Ct. Cl. 515, 1967 U.S. Ct. Cl. LEXIS 58
CourtUnited States Court of Claims
DecidedFebruary 17, 1967
Docket158-62
StatusPublished
Cited by37 cases

This text of 372 F.2d 485 (Amino Brothers Company, Inc. v. The United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Amino Brothers Company, Inc. v. The United States, 372 F.2d 485, 178 Ct. Cl. 515, 1967 U.S. Ct. Cl. LEXIS 58 (cc 1967).

Opinion

OPINION

SKELTON, Judge *

In this case, the plaintiff sues to recover damages in the sum of $301,530 incident to two washouts of a low-water crossing and the delay of work resulting therefrom. It claims entitlement to such amount as an equitable adjustment under the “Suspension of Work” and “Changed Conditions” clauses of a contract which it executed with the United States Army Corps of Engineers for the construction of a flood control project, and as damages for an alleged breach of such contract. The defendant interposed the sovereign act doctrine, and the finality of findings of fact determined in its favor by the Corps of Engineers Board of Contract Appeals (hereinafter referred to as the “Board”) under the “Disputes” clause of the contract. Before reaching the merits of the claim, we face a threshold procedural inquiry which necessitates relating the chronology of the administrative and judicial proceedings in this case.

Plaintiff’s claim was denied by the contracting officer and ultimately by the Corps of Engineers Board of Contract Appeals in a written opinion dated April 18, 1961 (Eng. BCA No. 1582). Plaintiff’s motion for reconsideration and/or rehearing was denied on January 25, 1962 (Eng. BCA No. 1582). Thereupon, plaintiff filed his petition in this court on May 14, 1962, and on June 9, 1964, the defendant’s motion for an order restricting the trial to a review of the record of the Board was denied by the trial commissioner. The defendant appealed within the procedures for review afforded it by Rule 55(a) (3), 1 but we denied defendant’s request for review, without prejudice, on July 29, 1964, and the case was scheduled for a de novo trial. The report of the commissioner was rendered on March 25, 1966, after a de novo hearing, accompanied by his findings of fact.

We wish to point out that our denial of the defendant’s request for review without prejudice, and the hearing before the commissioner was prior to the decisions of the Supreme Court in United States v. Utah Construction Co., 384 U.S. 394, 86 S.Ct. 1545,16 L.Ed.2d 642 (1966), and United States v. Anthony Grace & Sons, 384 U.S. 424, 86 S.Ct. 1539, 16 L.Ed.2d 662 (1966), and we and the commissioner did not have the benefit of those decisions. In view of the holding in those cases, we recognize that we are bound by the Board’s findings of fact *487 if they are supported by substantial evidence, and we hold that they are, and that our decision must be, and is accordingly, based thereon.

We feel, however, that in view of the opinion of the parties and the commissioner to the effect that the evidence adduced at the trial de novo was the same as the evidence presented to the Board, it would not be productive to undertake the laborious task of searching each and every subsidiary finding to ascertain whether it is supported, or can be supported, solely on evidence presented to the Board. Since our conclusions and critical findings all rest upon the Board proceedings and the judicial record, it is unnecessary to engage in the useless and burdensome process of combing each of the preliminary findings. Cf. Hunt and Willett, Inc. v. United States, 351 F.2d 980, 982, 168 Ct.Cl. 256, 260 (1964).

The facts giving rise to plaintiff’s complaint are as follows:

Plaintiff, a corporation and a general contractor, experienced in flood control work, entered into a contract with the United States Army Corps of Engineers on February 4, 1957, to build a cutoff channel and to construct a flood control levee for the total sum of $202,316 on the Smoky Hill River at Salina, Kansas. The contract required the plaintiff to make an excavation of 3,948 feet and to use the excavated materials to construct a flood control levee of approximately 15,000 feet. This construction required that the excavated materials be transported across Smoky Hill River. The contract provided that the plaintiff “may construct for his own use” low-water crossings on the Smoky Hill River as follows :

****•»
2-13. Channel Crossings. The contractor may construct for his own use within the right-of-way, low water crossings on the Smoky Hill River in strict accordance with the following:
a. Provide for not less than 64 square feet of effective opening in the channel at each crossing.
b. The flow line of the openings shall be set at the flow line of the existing channel.
c. The Contractor shall remove the crossings whenever in the opinion of the Contracting Officer the river stage would be adversely affected.
d. The crossings shall be used for the sole purpose of the Contractor’s hauling equipment.
e. The Contractor shall remove the crossings upon completion of the work or whenever its use is no longer required.
* * * * *

The specifications which formed a part of the contract contained a clause showing approximate weather conditions at the site with monthly precipitation in inches, but provided that:

* * * each bidder should satisfy himself before submitting his bid as to the hazards likely to arise from weather conditions. Complete weather records and reports may be obtained from the U. S. Weather Bureau. * *

Such specifications also contained a provision with reference to site investigation which stated that the contractor had satisfied himself as to the nature and location of the work, the general and local conditions, roads and uncertainties of weather, river stages, tides or similar physical conditions at the site.

The contract contained “Suspension of Work”, “Changed Conditions” and “Disputes” clauses usually found in government contracts of this kind. 2

*488 The title pages of the specifications of this project were headed by the words, “Flood-Protection Project, Kansas River Basin, Smoky Hill River, Kansas.” It appears from the evidence that during the 6 years immediately preceding the beginning of this project there had been a severe drought along this part of the river, although in 1950, about 6 years before plaintiff started work on this contract, there had been a disastrous flood along Smoky Hill River where plaintiff was required to work under the contract involved here.

Also, there was a flood control dam, known as Kanopolis Dam, located 88 miles upstream from the work site, and several miles further upstream was Cedar Bluff Dam. Both of these dams were being operated by the United States Army Corps of Engineers as flood control dams and the Kanopolis Dam was built primarily for flood control purposes. Water was retained in these reservoirs during periods of excessive rain and as conditions permitted, flood waters were released until the flood storage capacity of the reservoirs was restored.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Pure Wafer Inc. v. City of Prescott
845 F.3d 943 (Ninth Circuit, 2017)
Klamath Irrigation District v. United States
75 Fed. Cl. 677 (Federal Claims, 2007)
Centex Corp. v. United States
395 F.3d 1283 (Federal Circuit, 2005)
Biodiversity Associates v. Cables
357 F.3d 1152 (Tenth Circuit, 2004)
William O. Schism and Robert Reinlie v. United States
316 F.3d 1259 (Federal Circuit, 2002)
Sinclair v. United States
49 Fed. Cl. 274 (Federal Claims, 2001)
United States v. Winstar Corp.
518 U.S. 839 (Supreme Court, 1996)
Alaska v. United States
35 Fed. Cl. 685 (Federal Claims, 1996)
Walter Dawgie Ski Corp. v. United States
39 Cont. Cas. Fed. 76,583 (Federal Claims, 1993)
Winstar Corp. v. United States
994 F.2d 797 (Federal Circuit, 1993)
Winstar Corporation v. United States
994 F.2d 797 (Federal Circuit, 1993)
Winstar Corp. v. United States
25 Cl. Ct. 541 (Court of Claims, 1992)
Hughes Communications Galaxy, Inc. v. United States
37 Cont. Cas. Fed. 76,307 (Court of Claims, 1992)
James v. United States
760 F.2d 590 (Fifth Circuit, 1985)
Everett Plywood Corp. v. United States
651 F.2d 723 (Court of Claims, 1981)
Sornsin Construction Co. v. State
26 Cont. Cas. Fed. 83,215 (Montana Supreme Court, 1978)

Cite This Page — Counsel Stack

Bluebook (online)
372 F.2d 485, 178 Ct. Cl. 515, 1967 U.S. Ct. Cl. LEXIS 58, Counsel Stack Legal Research, https://law.counselstack.com/opinion/amino-brothers-company-inc-v-the-united-states-cc-1967.