Gerhardt F. Meyne Co. v. United States

76 F. Supp. 811, 110 Ct. Cl. 527, 1948 U.S. Ct. Cl. LEXIS 37
CourtUnited States Court of Claims
DecidedApril 5, 1948
Docket45926
StatusPublished
Cited by14 cases

This text of 76 F. Supp. 811 (Gerhardt F. Meyne Co. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Gerhardt F. Meyne Co. v. United States, 76 F. Supp. 811, 110 Ct. Cl. 527, 1948 U.S. Ct. Cl. LEXIS 37 (cc 1948).

Opinion

WHITAKER, Judge.

Plaintiff sues the defendant for damages for delaying it in the carrying out of its contract for the construction of 156 tempo--rary buildings at Fort Sheridan, Illinois. It also sues for an additional amount to *812 which it claims it is entitled for certain concrete foundations and for the cost of road construction and maintenance. It has' waived its claim for extra work on the Theater Building, its claim for interference with the carrying out of its contract by certain excavation for utilities, and its claim for overtime.

The first claim is for a delay caused by the defendant as a result of making a change in the drawings for the Theater Building. While work was proceeding on the foundations for this building the defendant gave plaintiff revised drawings for this building and requested a proposal for the doing of the work according to them. Plaintiff on February 7, 1941, proposed to do the work for an extra amount of $11,836.00. Its letter read in part:

“Complying with your request dated January 22nd, 1941, and received by this office on January 23rd, 1941, we propose to furnish the additional labor, material and equipment to build the Theatre Building— Type TH — 3, at Fort Sheridan, Illinois, in accordance with drawings #700 — 1212.1 and #700 — 1224.1 as altered and approved by you on January 28th, 1941, for the sum of Eleven Thousand Eight Hundred and Thirty-six ($11,836.00) Dollars.”

A month later, on March 6, 1941, it was advised that its proposal was accepted and it was ordered to proceed. The following day, however, plaintiff advised the defendant that since its proposal was submitted the ground had frozen and that access to the site had been made more difficult by an open ditch dug by the defendant adjacent to the building, and it requested an additional amount of $3,000 for the resulting increased costs and for damages due to the delay. Before getting a reply to this last request it resumed work.

Since its offer of $11,836 was still outstanding at the time the defendant accepted it, we are of opinion plaintiff is bound by it, and is not entitled to recover any more than the amount of it. Defendant did not accede to its request for additional compensation, and plaintiff proceeded with the work without .insisting upon it. Instead, a little over a month after work had been resumed and about a month before the work was. completed plaintiff submitted a revised proposal of $11,826 on account of the changes made in the drawings, which was $10 less than its original proposal; and it did not include anything for the additional cost claimed on account of the frozen ground or for the damages incident to the delay.

Defendant’s acceptance of plaintiff’s proposal was informal, but it was nevertheless accepted. Formal action was deferred until after completion and acceptance of all of .the buildings. This was on November 28, 1941, when Change Order “M” was issued, covering this item as well as other items. The statement of the facts with reference to the issuance of this Change Order is reserved until after the facts with reference to the other claims have been stated.

Plaintiff’s next claim is for delay incident to a change in the location of buildings 155, 156, Í57, and 158.

After the foundations for buildings 155, 156, 157, and 158 had been substantially completed, the defendant ordered the work on these buildings to be stopped and presented plaintiff with a plan showing new locations for these buildings, and requested a proposal for the additional cost due to this change. Plaintiff on February 7, 1941, submitted a proposal for $2,972. A month later, on March 6, 1941, it was advised that its proposal was accepted, and it was ordered to proceed. As in the case of the Theater Building, plaintiff then advised the defendant that it would need additional compensation of $1,000 for the delay and because in the meantime the ground had frozen. Before receiving any reply thereto it resumed work.

Nearly a month later it submitted a revised proposal for the additional work required incident to the change of location in these buildings in the amount of $2,-417. This was about $500'less than its original proposal, and it did not include anything on account of the $1,000 claimed for the delay and for the additional work reqúired incident to the freezing of the ground.

*813 For the reasons stated in connection with the change on the Theater Building, we think it is bound by its offer.

Plaintiff’s next claim is for additional concrete work incident to the location of some of the buildings adjacent to ravines. The plans and specifications accompanying •the request for bids made it possible to compute the quantities of excavation and concrete only if the buildings were located on level ground; the exact location for the buildings was not given until after the contract had been awarded. Some of them were actually located on level ground, but others were located at places where they projected partly into deep ravines. This necessitated higher foundations than plaintiff had bid upon. Defendant advised plaintiff that the additional work required by these locations would be paid for at the unit prices set forth in the contract.

On April 16, 1941, plaintiff submitted a proposal of $39,354.36 for the extra work, but since it was not itemized by quantities no action was taken thereon. No further proposal was submitted until after all the work had been completed, when plaintiff uibmitted a proposal covering this claim as well as its other claims. This was followed by issuance of Change Order “M,” above referred to.

Plaintiff’s last claim is for the cost of road maintenance made necessary by the closing of the entrance to Patten Road over which it had planned to haul its materials.

In paragraph SC-13 the specifications provided:

“Entrance for trucks shall be at South Gate of reservation, over Walker Avenue, Highwood, Illinois, via Patten Road to site. If necessary, contractor shall reinforce the steel bridges on Patten Road over which the trucks must pass by the installation of vertical posts, struts, etc., sufficient to support the truck loads.”

Patten Road was a paved highway. It led to other paved highways which provided ready ingress and egress to the project. Just about the time plaintiff was about to begin work on the project the military authorities ordered the south entrance to Patten Road closed. This made it necessary for plaintiff to construct a temporary road from the substituted entrance to an existing unpaved road, and it also made it necessary for it to put surfacing material on this unpaved road. On April 15, 1941, plaintiff presented a claim of $2,500 for the cost of this roadway construction and maintenance. No action was taken on this claim until after all the work had been completed and plaintiff had submitted a claim covering all items.

The above is a brief statement of the facts in connection with the several claims on which plaintiff sues.

After all the work had been completed plaintiff submitted a claim on August 27, 1941, in the sum of $97,511.35 covering the above items and also others.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Santana v. United States
476 F. Supp. 2d 300 (S.D. New York, 2007)
United States v. Winstar Corp.
518 U.S. 839 (Supreme Court, 1996)
Walter Dawgie Ski Corp. v. United States
39 Cont. Cas. Fed. 76,583 (Federal Claims, 1993)
Hughes Communications Galaxy, Inc. v. United States
37 Cont. Cas. Fed. 76,307 (Court of Claims, 1992)
United States v. Board of Educ. of City of Chicago
588 F. Supp. 132 (N.D. Illinois, 1984)
Amino Brothers Company, Inc. v. The United States
372 F.2d 485 (Court of Claims, 1967)
Commercial Metals Co. v. United States
176 Ct. Cl. 343 (Court of Claims, 1966)
Wah Chang Corporation v. United States
282 F.2d 728 (Court of Claims, 1960)
Wunderlich v. United States
117 Ct. Cl. 92 (Court of Claims, 1950)

Cite This Page — Counsel Stack

Bluebook (online)
76 F. Supp. 811, 110 Ct. Cl. 527, 1948 U.S. Ct. Cl. LEXIS 37, Counsel Stack Legal Research, https://law.counselstack.com/opinion/gerhardt-f-meyne-co-v-united-states-cc-1948.