Wah Chang Corporation v. United States

282 F.2d 728, 151 Ct. Cl. 41, 1960 U.S. Ct. Cl. LEXIS 146
CourtUnited States Court of Claims
DecidedOctober 5, 1960
Docket124-55
StatusPublished
Cited by28 cases

This text of 282 F.2d 728 (Wah Chang Corporation v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Wah Chang Corporation v. United States, 282 F.2d 728, 151 Ct. Cl. 41, 1960 U.S. Ct. Cl. LEXIS 146 (cc 1960).

Opinion

JONES, Chief Judge.

This action is brought pursuant to Private Law No. 997, 83d Cong., 2d Sess., c. 1251, 68 Stat. A288 (1954), which provides :

“That, notwithstanding any statute of limitations, lapse of time, or any prior court decision on this claim by any court of the United States, jurisdiction is hereby conferred upon the United States Court of Claims to hear, determine, and render judgment on the claim of Wah Chang Corporation against the United States for compensation for loss of property and for removal expenses incurred as a result of the acquisition in the year 1942 by the United States for military purposes of pier numbered 13, New York foreign trade zone, Staten Island, New York, which had theretofore been leased by said Wah Chang Corporation and upon which the said Wah Chang Corporation had erected and maintained a tungsten processing plant.”

There is also a provision that “nothing contained in this Act shall be construed as an inference of liability on the part of the United States Government.” This provision, coupled with the legislative history, indicates clearly that the Congress did not intend to waive any defenses the Government might have to the plaintiff’s claim other than “any statute of limitations, lapse of time, or any prior court decision.”

The plaintiff is a corporation engaged in refining and concentrating tungsten ore. In December 1940, the plaintiff, acting through an affiliate or subsidiary company, leased a part of pier 13 at Staten Island, New York. The pier was owned by the City of New York, but was held by a corporation named the New York Foreign Trade Zone Operators, Inc., under an arrangement with the city. A plant for the processing and refining of tungsten ore was established on the leased space, with plaintiff furnishing the machinery, the engineers, and the technical management of the operation. This was plaintiff’s only plant. The lease provided that it should run until November 30, 1942, and thereafter could be terminated at the option of either party upon giving 60 days’ notice.

The Reconstruction Finance Corporation (RFC), under the authority of section 5 of the Act of June 25, 1940, 54 Stat. 572, organized the Metals Reserve Company and vested it with power to *731 acquire tungsten and certain other strategic and critical materials. An acute shortage of tungsten existed in the year 1941, and it became necessary to purchase low-grade tungsten ore from South American countries and refine it in this country. Against this background the Metals Reserve Company entered into a contract with the plaintiff on August 1, 1941, under the terms of which the plaintiff agreed to handle and process tungsten ore for Metals Reserve. This tungsten ore was to be purchased in Bolivia and other South American countries by Metals Reserve and shipped to the plaintiff at its plant on pier 13 for treatment designed to eliminate the impurities and make it suitable for commercial use.

Metals Reserve agreed that the plaintiff should realize on its contract $391,-000 per year for the 3-year life of the contract. Included in this figure was $20 per ton, or $100,000 per year, for plant amortization. There was also allowed 8 percent per year interest on capital invested (a total of $49,200 over the 3-year period), in addition to the recovery of ordinary and necessary operating expenses.

For the $391,000 payment Metals Reserve was entitled to the beneficiation (preparation for smelting) of 5,000 tons of ore. Payment was also to be made at the rate of $50 per ton for ore beneficiated in excess of 5,000 tons. Additional compensation, at the rate of $4 per ton, was allowed for the handling of all ores, including ores not requiring beneficiating.

Tbe plaintiff, anticipating the successful conclusion of the negotiations with Metals Reserve, sought the rental of additional space on the pier to accommodate the contemplated enlargement of the plant and the expanded operations. The additional space was turned over to plaintiff by the lessor on August 18, 1941. All the terms of the original lease, including the November 30, 1942, expiration date, applied to the additional space. Thereafter the plaintiff commenced enlarging its plant and performing its contract with Metals Reserve.

On February 7, 1942, a petition in condemnation was filed at the request of the Secretary of War in the United States District Court, Eastern District of New York, for the acquisition, for a term of two years, of the use and occupancy of approximately 55 acres of land on Staten Island, including pier 13. The Army subsequently notified the plaintiff that its operation must be removed from pier 13 not later than October 1, 1942. The plaintiff asserts that the Government promised to pay the removal costs. The facts concerning this alleged promise, which is one of the bases for the plaintiff’s claim, will be discussed later in the opinion.

Faced with the order to remove its operations from pier 13, the plaintiff, on April 10, 1942, exercised an option to purchase a plant site at Glen Cove, Long Island, and on May 9, 1942, submitted a plan to Metals Reserve whereby the Defense Plant Corporation 1 would buy plaintiff’s Glen Cove site, build a plant thereon, and rent it to the plaintiff. On June 16, 1942, the plaintiff and the Defense Plant Corporation (DPC) entered into an “Agreement of Lease,” in which it was agreed, among other things, that (1) DPC would purchase the Glen Cove site, (2) plaintiff would construct and equip the plant, (3) DPC would expend an amount not to exceed $360,000 (subsequently increased to $675,203.93) for the construction of the plant and the purchase of the site, (4) title to the site and the plant would be vested in DPC, (5) DPC would lease the site and the plant to the plaintiff, (6) plaintiff would have an option, on certain terms and conditions, to buy the site and the plant, and have the rent paid to DPC applied to the purchase price.

*732 After completing the removal of its operations from the pier on September 17, 1942, the plaintiff continued to refine and process tungsten for Metals Reserve at the new Glen Cove plant. The Government stipulated in this case that plaintiff “incurred a loss in the sum of $130,877.16 in removing its machinery, equipment and material from the plant on Pier 13, Staten Island, New York, and that no part of such loss has been repaid to * * [plaintiff] nor has it been otherwise reimbursed therefor * * The original August 1, 1941, contract with Metals Reserve was amended on February 15, 1943. On November 6, 1943, this contract, as amended, was revoked and a new contract was substituted. Thereafter, further contracts were entered into with Metals Reserve and the RFC extending into 1949. The plaintiff was paid over $2,700,000 for its services under these defense and wartime tungsten refining contracts with the Government; but the record does not indicate whether plaintiff made an over-all profit. The plaintiff ultimately purchased from DPC the Glen Cove plant, which it still owns.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Klamath Irrigation District v. United States
75 Fed. Cl. 677 (Federal Claims, 2007)
Transpace Carriers, Inc. v. United States
27 Fed. Cl. 269 (Federal Claims, 1992)
Winstar Corp. v. United States
25 Cl. Ct. 541 (Court of Claims, 1992)
Hughes Communications Galaxy, Inc. v. United States
37 Cont. Cas. Fed. 76,307 (Court of Claims, 1992)
Alaska American Lumber Co. v. United States
37 Cont. Cas. Fed. 76,286 (Court of Claims, 1992)
Ensign Financial Corp. v. Federal Deposit Insurance
785 F. Supp. 391 (S.D. New York, 1992)
Town of North Bonneville v. United States
11 Cl. Ct. 694 (Court of Claims, 1987)
Hedstrom Lumber Co. v. United States
32 Cont. Cas. Fed. 73,113 (Court of Claims, 1984)
South Louisiana Grain Services, Inc. v. United States
30 Cont. Cas. Fed. 70,493 (Court of Claims, 1982)
O'Neill v. United States
231 Ct. Cl. 823 (Court of Claims, 1982)
Petrofsky v. United States
616 F.2d 494 (Court of Claims, 1980)
Pauley Petroleum Inc. v. United States
591 F.2d 1308 (Court of Claims, 1979)
Sun Oil Co. v. United States
572 F.2d 786 (Court of Claims, 1978)
WRB Corp. v. United States
183 Ct. Cl. 409 (Court of Claims, 1968)
Wunderlich Contracting Company v. United States
351 F.2d 956 (D.C. Circuit, 1965)
Wunderlich Contracting Co. v. United States
351 F.2d 956 (Court of Claims, 1965)

Cite This Page — Counsel Stack

Bluebook (online)
282 F.2d 728, 151 Ct. Cl. 41, 1960 U.S. Ct. Cl. LEXIS 146, Counsel Stack Legal Research, https://law.counselstack.com/opinion/wah-chang-corporation-v-united-states-cc-1960.