Barnes v. United States

105 F. Supp. 817, 123 Ct. Cl. 101
CourtUnited States Court of Claims
DecidedJuly 15, 1952
Docket46774
StatusPublished
Cited by5 cases

This text of 105 F. Supp. 817 (Barnes v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Barnes v. United States, 105 F. Supp. 817, 123 Ct. Cl. 101 (cc 1952).

Opinion

JONES, Chief Judge.

Plaintiff sues for increased costs and other damages which it claims were caused by delay, and also for damages on account of alleged misrepresentation on the part of officials of the Government in connection with a construction contract.

Defendant denies liability and files a counterclaim alleging overpayment.

On February 9, 1943, plaintiff entered into a contract with the defendant agreeing to build 1,080 dwelling units near' Tooele, Utah, for a consideration of $2,470,000. It was a war housing project to be completed within 160 days after the date fixed in the notice to proceed. The date set in the notice was February 24, 1943, but plaintiff actually began work a few days earlier. Later the contract was amended to provide for the construction of some additional buildings for an added consideration of $190,000.

There were delays in the completion of the work, but extensions of time were granted, the work accepted, and no liquidated damages were assessed.

Prior to the execution of the contract, the President, on October 3, 1942, issued Executive Order 9250, providing, inter alia, that except for certain corrective adjustments, no increase or decrease in wages should be authorized until after notice to and approval by the War Labor Board.

On October 23, 1942, on request of the National Housing Agency of the Federal Public Housing Authority (hereinafter called the Housing Authority), the Secretary of Labor made a predetermination of wage rates under the Davis-Bacon Act with respect to this and another housing project to be constructed at Tooele, Utah. These rates had been furnished the Secretary of Labor by the appropriate labor unions.

Invitations for bids, issued on December 10, 1942, contained these specifications as minimum rates and by addendum in January 1943 made them maximum rates of pay as well.

The bids were opened February 1, 1943. At that time the three lowest bidders were requested to submit bids for completion within 90 days instead of 160. Plaintiff was the lowest bidder on the original invitation. It submitted also the bid for the shorter completion period as requested.

Later the Housing Authority decided that it wanted only a part of the dwelling units finished within 90 days. It requested a bid on 340 specified units which it desired finished within 90 days. On February 10, 1943, plaintiff complied with this request offering to complete the 340 specified units within the shorter period for an additional amount of $110,000. This offer was conditioned on acceptance before February 26, 1943, but after an exchange o'f messages plaintiff agreed to an acceptance a few days later. A change order was issued, which provided among other things, that plaintiff was to assume all additional cost, such as overtime, extra equipment, additional supervision, etc., that might be required to complete that portion of the work within 90 days.

Before submitting its bid for the whole project plaintiff had received bids from proposed subcontractors for doing certain portions of the work. Portions of the work aggregating $721,363 were subcontracted. These subcontracts were executed on February 24, 1943, by plaintiff and the various subcontractors. All of these subcontracts stipulated the time of performance as 90 days from date for 340 units, and 160 days from date for all work. Before executing these contracts plaintiff had been advised of the desire of defendant to have 340 units completed within 90 days’ time, but at the time their bids were submitted the subcontractors had not been advised of the pro *819 posed change in the time limit of plaintiff’s contract.

Prior to submitting its bid plaintiff made inquiry of an official of the bricklayers’ union in Salt Lake City as to the availability of bricklayers at $1.50 per hour, and was told that while that was the official union scale no assurance could be given that the project could be properly manned at that rate. The trades council of Salt Lake City o-n January 27, 1943, had protested to the Secretary of Labor the wage rates set forth in the invitation to bid and had requested the Housing Authority to adopt higher wage rates which it claimed were actually being paid at that time.

Plaintiff ran into many difficulties in endeavoring to secure bricklayers for the project. It requested the bricklayers’ union to furnish a supply of labor, but the requested numbers were not supplied by the union officials.

It had been the prevailing custom for laborers who were working on projects removed from urban centers to be paid travel or subsistence allowances, or both, in addition to the hourly rates. One of the subcontractors at first made payments of $2.50 per day for this purpose, but when this became known plaintiff’s project manager directed the subcontractor to stop such payments since it was thought by plaintiff that this practice would subject it to penalties. There was considerable delay in connection with the securing of both bricklayers and plumbers. It developed that in the same locality some bricklayers were being paid at a higher rate.

Plaintiff ran into so many difficulties that on March 18, 1943, it requested the Housing Authority to suspend the work until such time as adequate manpower could be furnished pending a possible adjustment in the wage rates. About March 26, 1943, a formal application was made to the Wage Adjustment Board for an increased rate for several trades. On April 23, 1943, the bricklayers’ wages were increased by the board from $1.50 per hour to $1.58 per hour, subj ect to certain conditions set out in finding 10. The plaintiff on May 5, 1943, was advised by the Housing Authority of the authorization of the increased rates.

Plaintiff was well organized and if sufficient labor had been available it could probably have finished the work within the 90-day period for the 340 units and the 160-day limit for the entire project. Plaintiff advertised for labor but was advised that since there was a manpower allocation this course should not be taken. Many of the laborers who were secured were not properly skilled.

Because of the shortage of labor and the delay in the work, certain materials, especially gypsum board which had been timely purchased could not be accepted by plaintiff when ready for delivery because this particular board deteriorates when stored in the open and there was no place in that area for proper storage. When the time came to use gypsum board and certain other materials there was delay in delivery.

Originally plaintiff had planned to start construction on the eastern edge of the project and work westward as this would permit grading from a higher to a lower area, which would facilitate the work generally. However, in view of the selection of the 340 units specified this plan was interrupted to some degree.

At a later date, as set out in finding 15, the Housing Authority determined that the delays were not due to the fault or negligence of the plaintiff, and that the time for the completion of both portions of the contract should be extended so as to- bring the completion within the date specified. Accordingly appropriate extensions of time for completion were granted, and no liquidated damages were assessed.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Klamath Irrigation District v. United States
75 Fed. Cl. 677 (Federal Claims, 2007)
Tony Downs Foods Co. v. United States
530 F.2d 367 (Court of Claims, 1976)
Bruno New York Industries Corp. v. The United States
342 F.2d 75 (Court of Claims, 1965)
Wah Chang Corporation v. United States
282 F.2d 728 (Court of Claims, 1960)

Cite This Page — Counsel Stack

Bluebook (online)
105 F. Supp. 817, 123 Ct. Cl. 101, Counsel Stack Legal Research, https://law.counselstack.com/opinion/barnes-v-united-states-cc-1952.