Bruno New York Industries Corp. v. The United States

342 F.2d 75, 169 Ct. Cl. 999, 1965 U.S. Ct. Cl. LEXIS 76
CourtUnited States Court of Claims
DecidedMarch 12, 1965
Docket393-59
StatusPublished
Cited by9 cases

This text of 342 F.2d 75 (Bruno New York Industries Corp. v. The United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Bruno New York Industries Corp. v. The United States, 342 F.2d 75, 169 Ct. Cl. 999, 1965 U.S. Ct. Cl. LEXIS 76 (cc 1965).

Opinion

*76 PER CURIAM:

In this contract case, which is to be considered on the record made before the Armed Services Board of Contract Appeals, both parties have moved for summary judgment. These motions were referred to Trial Commissioner William E. Day, under Rule 54(b), for his opinion and recommendation for a conclusion of law. Commissioner Day has submitted an opinion holding for the plaintiff on the first claim of the petition and for the defendant on the second claim. He has recommended that (a) the defendant’s motion should be allowed as to the second claim and the petition dismissed as to that claim, and (b) the plaintiff’s motion should be allowed as to the first claim and judgment entered for plaintiff for $31,-000. The plaintiff has not sought review of the Commissioner’s opinion and recommendation as to the second claim, and the court adopts them as the basis for its judgment on that claim.

On the first claim, the defendant has sought review, oral argument before the court has been had, and the court has considered the briefs filed by the parties. On that claim, too, the court agrees with the Commissioner’s recommendation and opinion, and adopts them, as supplemented by the remainder of this opinion, as the basis for its judgment on the claim.

Since the filing of the Commissioner’s opinion, the court has reiterated the ruling that issues of interpretation of the language of contract specifications are issues of law on which the decision of the Board of Contract Appeals is in no way binding, even though those issues may be involved in a proceeding to obtain an equitable adjustment under the Changes article of the contract. Kaiser Industries Corp. v. United States, Ct.Cl., 340 F.2d 322, decided Jan. 22, 1965; C. J. Langenfelder & Son, Inc. v. United States, Ct.Cl., 341 F.2d 600, decided Feb. 19, 1965. The Commissioner’s opinion fully accords with that position.

The defendant contends that the parties’ stipulation before the Board of Contract Appeals, to which Commissioner Day refers, should not be read as conceding that the only issue left in the case was whether CCN No. 1 had effected a change in the contract within the ambit of the Changes article, but, rather, as fixing the litigable issue to be whether or not there was a compensable change in the contractor’s work requirements or actual work obligation. We have reviewed the pertinent wording of the stipulation as well as the proceedings before the Board (including the parties’ briefs at that stage of the litigation), and we cannot accept defendant’s present interpretation of the stipulation. In our view, the stipulation should properly be read (just as it is worded) as leaving for decision only the question of whether CCN No. 1 effected a change within the purview of the Changes article. 1 If that issue is answered affirmatively, the parties have entirely removed the issue of compensability by stipulating that the plaintiff would be entitled to $31,000. We agree with Commissioner Day, for the reasons he gives, that an affirmative answer is required. It follows that under the parties’ arrangement the plaintiff should have judgment in the agreed amount.

Plaintiff’s motion for summary judgment is granted and defendant’s cross-motion for summary judgment is denied as to the first claim of the petition. On that claim, the plaintiff is entitled to recover the sum of thirty-one thousand dollars ($31,000) and judgment is entered for plaintiff in that amount. Defendant’s motion is granted and plaintiff’s motion is denied as to the second claim of the petition, and that claim is dismissed.

OPINION OP THE COMMISSIONER

This is a contract case which is before the court on cross-motions for summary judement. The plaintiff’s petition is in two counts. By the first count it claims an eauitable adjustment in the contract *77 price on account of an alleged change in the contract requirements by reason of a written order amending the contract specifications. The contracting officer refused to increase the contract price on account of this specification change. The plaintiff appealed this refusal to the Armed Services Board of Contract Appeals (hereinafter referred to as ASBCA) and was there unsuccessful.

The second count of the petition relates to a claimed interference by the defendant with plaintiff’s production in the operation of priority controls on needed electrical components and by the defendant’s failure to assist the plaintiff by expediting the delivery of such components from the plaintiff’s supplier. The claims made in the second count of the petition had not been made the subject of an appeal under the “disputes” clause of the contract.

The plaintiff’s motion attacks the ASB CA decision (1) as an erroneous and incorrect interpretation of the contract between the parties, (2) that it is based on findings of fact not supported by the record, and (3) that it is not based upon substantial evidence. Further, the plaintiff says that the failure of the defendant to render an equitable adjustment in price under the “changes” article in the contract for costs resulting from the issuance of Contract Change Notification No. 1 (hereinafter called CCN No. 1), insofar as it changed the capacitor specification of the contract in suit, constituted a breach of contract. The defendant argues that the plaintiff has failed to show a lack of substantial evidence supporting the findings of the ASB CA, thus rendering final the decision based on the findings by that Board.

The plaintiff has filed in support of its motion the entire administrative record, including the contract file, the transcript of the testimony of witnesses, and the exhibits which were considered by the ASBCA in arriving at its decision. In addition, the plaintiff supported the motion by an affidavit of the plaintiff’s president and also by an affidavit of plaintiff’s counsel of record.

The “changes” and the ‘disputes articles, incorporated into the general provisions of the contract in suit, were the usual articles contained in Standard Form 32, General Provisions (Supply Contract).

The plaintiff on March 27, 1956, was awarded a contract to furnish to the Air Materiel Command at Wright-Patterson Air Force Base, Ohio, 16,283 headset adapters (electronic devices) at a unit price of $26.16. The award was made pursuant to competitive bids.

Three prototypes of the contract item, called “first articles,” were to be submitted for qualification tests within 60 days of the date of award. Production deliveries were to commence 60 days after Government approval of the “first articles.” The contract required that the contract items be produced in accordance with the specification* described as Spec. MIL-A-8416A, dated March 17, 1955. This specification incorporated therein, by reference, Spec. MIL-E-5400. The latter specification provided:

“3.1.3.2 Electrolytic

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
342 F.2d 75, 169 Ct. Cl. 999, 1965 U.S. Ct. Cl. LEXIS 76, Counsel Stack Legal Research, https://law.counselstack.com/opinion/bruno-new-york-industries-corp-v-the-united-states-cc-1965.