Kaiser Industries Corporation v. The United States

340 F.2d 322, 169 Ct. Cl. 310, 1965 U.S. Ct. Cl. LEXIS 56
CourtUnited States Court of Claims
DecidedJanuary 22, 1965
Docket488-59
StatusPublished
Cited by62 cases

This text of 340 F.2d 322 (Kaiser Industries Corporation v. The United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Kaiser Industries Corporation v. The United States, 340 F.2d 322, 169 Ct. Cl. 310, 1965 U.S. Ct. Cl. LEXIS 56 (cc 1965).

Opinion

PER CURIAM:

This case was referred pursuant to former Rule 45(a) (now Rule 57(a)) to Trial Commissioner Saul Richard Gamer, with directions to make findings of fact and recommendations for a conclusion of law. The commissioner has done so in an opinion and report filed March 6, 1964. Exceptions to the commissioner’s findings were made by the parties, briefs were filed by the parties and the case was submitted to the court on oral argument by counsel. Since the court is in agreement with the opinion, findings and recommendation of the trial commissioner, with minor modifications as hereinafter set forth, it hereby adopts the same as the basis for its judgment in this ease. Therefore, plaintiff is entitled to recover of and from the United States in the amount of seventy-one thousand, five hundred nine dollars and four cents ($71,509.04), and judgment is entered for plaintiff in this matter in this amount.

Commissioner Gamer’s opinion, as modified by the court, is as follows:

A construction contractor here claims approximately $185,000 as an equitable adjustment under the “Changed Conditions” article of its contract with the Army Corps of Engineers. 1 This article *324 provides that the contractor shall receive such an adjustment in its contract price if it encounters either “(1) subsurface or latent physical conditions at the site differing materially from those indicated in the contract, or (2) unknown physical conditions at the site, of an unusual nature, differing materially from those ordinarily encountered and generally recognized as inhering in work of the character provided for” in the contract.

Plaintiff’s contract was for the repair of stone revetments at various locations along the shores of the McNary Dam Reservoir on the Columbia River in the States of Washington and Oregon. The embankment slopes were to be reshaped and riprap and random rock were to be placed thereon. The original contract amount, based on estimated quantities, was $1,028,466.

In this part of the country it is difficult to locate suitable rock for such a project. Most of the rock in the region is of basalt formation from lava flows and a considerable part of it is of a type that breaks too small for use as riprap of the size required. Defendant itself owned two quarries which the contract recited were “approved” as sources of rock for the project and which were made available to the successful bidder without charge. Other quarry sources could not be used without the permission of the contracting officer. In any event, as a practical matter there were no other known quarries which were believed to contain sufficient quantities of the kind of rock required and were so located as to be economically feasible for use under the contract. Defendant had spent considerable time over a period of years in making studies of potential sources of rock suitable for such work.

Plaintiff 2 selected one of the two quarries made available by defendant, known as the Hover Quarry. However, after a relatively short and difficult time during which, with an abnormal amount of waste, it was able to obtain some suitable rock, it abandoned the quarry. What rock that was in the quarry which could, in any economical fashion, be used to complete the requirements of the project was, insofar as any reasonably foreseeable successful operation was concerned, exhausted when plaintiff abandoned it. Outside of a satisfactory vein of rock which gave out within the first few weeks of operation, and from which plaintiff was able to produce the largest sized rock required by the contract, 3 most of the rock plaintiff handled shattered, crumbled, and pulverized on handling. As operations proceeded further into the original cut of satisfactory rock, as well as in other areas, it became increasingly difficult to find sound rock. Other areas probed in the face of the quarry produced rotten and decayed rock interspersed with boulders, some of which were not suitable for production purposes. When apparently sound rock faces were blasted, the rock would crumble. Powder blast reductions to absolute minima failed to cure the situation. Seemingly good rock simply flaked or deteriorated when dug or, when loaded with the shovel on to the trucks and the barges, would shatter and disintegrate. Although it was originally reasonable to assume waste of approximately 15-20 percent, plaintiff’s waste was over 60' percent. By the time plaintiff left Hover, the excavated perimeter constituting *325 the quarry face extended over the unusually large area of 1,350 feet. There was no reasonable prospect that further exploration would produce any substantially different results. In short, it turned out that the quarry was not a commercially operable one at all for the purposes of supplying any appreciable amount of rock for the project. Upon discovery of the situation and prior to abandoning the quarry, plaintiff made a timely request for an equitable adjustment under Article 4.

After plaintiff moved from Hover to the other “approved” quarry, known as Cold Springs, there was no further difficulty. This was an excellent quarry that easily supplied approximately 300,000 tons of rock with a waste factor of approximately 10 percent, and indeed plaintiff completed the entire project, even as enlarged by change orders, 2 months ahead of time.

Plaintiff’s claim for an equitable adjustment was denied both by the contracting officer and the Corps of Engineers Board of Contract Appeals.

Certainly, encountering a condition in a “quarry” — let alone an “approved” quarry — which makes it not a usable quarry at all for the purposes involved, should, it seems clear, normally be considered an “unusual” one not “ordinarily encountered and generally recognized as inhering in” quarrying operations. Thus, it seems almost self-evident that plaintiff would be entitled to an equitable adjustment under this plain language of the above-quoted second part of Article 4. Cf. Tobin Quarries, Inc. v. United States, 84 F.Supp. 1021, 114 Ct.Cl. 286 (1949), where the claimant was held to be entitled to an equitable adjustment under Article 4 when it turned out that the quarry rock “was quite friable, and it proved impossible to get rock of the required size without excessive waste.” (84 F.Supp. p. 1021, 114 Ct.Cl. p. 332)

The reasons why defendant denied plaintiff such an adjustment appear to lie primarily in the language of the first part of Article 4. Defendant contends that the conditions plaintiff encountered at Hover did not differ “materially from those indicated in the contract” and that, instead, an intelligent and knowledgeable reading and interpretation of the specifications and drawings would have disclosed these very conditions. This defense also carries over to the second part of the article, the provisions of which apply only to “unknown” physical conditions of the kind described. Defendant argues that plaintiff should have known of or reasonably anticipated the conditions encountered by what it contends the specifications and drawings clearly indicated, as well as by what should have been obvious had plaintiff made a careful investigation of the quarry sites and certain core borings therefrom which were available for inspection by bidders.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Magnus Pacific Corporation v. United States
133 Fed. Cl. 640 (Federal Claims, 2017)
Renda Marine, Inc. v. United States
66 Fed. Cl. 639 (Federal Claims, 2005)
Fru-Con Construction Corp. v. United States
43 Cont. Cas. Fed. 77,449 (Federal Claims, 1999)
Sutton Corp. v. Metropolitan District Commission
667 N.E.2d 838 (Massachusetts Supreme Judicial Court, 1996)
Youngdale & Sons Construction Co. v. United States
38 Cont. Cas. Fed. 76,467 (Federal Claims, 1993)
A.S. McGaughan Co. v. United States
37 Cont. Cas. Fed. 76,239 (Court of Claims, 1991)
Gardner-Zemke Co. v. State
790 P.2d 1010 (New Mexico Supreme Court, 1990)
Lathan Co. v. United States
36 Cont. Cas. Fed. 75,842 (Court of Claims, 1990)
Servidone Construction Corp. v. United States
36 Cont. Cas. Fed. 75,797 (Court of Claims, 1990)
North Slope Technical Ltd. v. United States
34 Cont. Cas. Fed. 75,430 (Court of Claims, 1988)
PT & L. CONST. v. Dept. of Transp.
531 A.2d 1330 (Supreme Court of New Jersey, 1987)
P.T. & L. Construction Co. v. State, Department of Transportation
531 A.2d 1330 (Supreme Court of New Jersey, 1987)
Shank-Artukovich v. United States
34 Cont. Cas. Fed. 75,372 (Court of Claims, 1987)
Baltimore Contractors, Inc. v. United States
34 Cont. Cas. Fed. 75,267 (Court of Claims, 1987)
Erickson-Shaver Contracting Corp. v. United States
33 Cont. Cas. Fed. 74,191 (Court of Claims, 1985)
BCM Corp. v. United States
31 Cont. Cas. Fed. 71,110 (Court of Claims, 1983)
L.G. Everist, Inc. v. United States
30 Cont. Cas. Fed. 70,356 (Court of Claims, 1982)
Pleasant Excavating Co. v. United States
229 Ct. Cl. 654 (Court of Claims, 1981)
Mitsui & Co. v. Puerto Rico Water Resources Authority
528 F. Supp. 768 (D. Puerto Rico, 1981)
Glynn v. City of Gloucester
401 N.E.2d 886 (Massachusetts Appeals Court, 1980)

Cite This Page — Counsel Stack

Bluebook (online)
340 F.2d 322, 169 Ct. Cl. 310, 1965 U.S. Ct. Cl. LEXIS 56, Counsel Stack Legal Research, https://law.counselstack.com/opinion/kaiser-industries-corporation-v-the-united-states-cc-1965.