North Slope Technical Ltd. v. United States

34 Cont. Cas. Fed. 75,430, 14 Cl. Ct. 242, 1988 U.S. Claims LEXIS 6, 1988 WL 5080
United States Court of Claims·Decided January 21, 1988·No. No. 291-86C·Published·Cited by 10 cases

Opinion

OPINION

BRUGGINK, Judge.

This is a direct access government contracts case filed pursuant to 41 U.S.C. § 609(a)(1) (1982). Plaintiff North Slope Technical Limited, Inc. (“North Slope”) seeks an equitable adjustment for an alleged Type I differing site condition1 encountered during contract performance at Eielson Air Force Base near Fairbanks, Alaska. Specifically, North Slope claims that it encountered water conditions during excavation that were unanticipated in view of project plans and specifications, thus requiring a complex and costly dewatering system. Upon consideration of the evidence presented at trial,2 the parties’ submissions, and the applicable law, the court concludes for the reasons stated herein that plaintiff is entitled to judgment in the amount of $1,280,675.49.

FACTUAL BACKGROUND

On January 5,1985, the U.S. Army Engineer District, Alaska, issued Invitation for Bids (“IFB”) No. DACA85-85-B-0009 for the construction of an underground concrete utilidor3 at Eielson Air Force Base—the Extend Utilities Cool Home (Utilidor) project.4 The bidding documents specified that offers were due by February 5, 1985. On January 17, 1985, a pre-bid conference/site visit was held at Eielson. Although North Slope did not attend the conference, it did receive the minutes of the meeting.5 The minutes6 indicate that Ken Larson, the Fairbanks Resident Engineer for the U.S. Army Engineer District, Alaska, stated:

The plans and specifications indicate a high water table. Virtually every manhole and most of the concrete utilidor sections will involve work at or below the water table, so you should anticipate de-watering problems. Be sure to study the plans and specifications for borings and work elevations, and note the amount of snow (three to four feet) that is presently on the work site. We do not consider the present accumulation of snow to be abnormal, but it will certainly affect your onsite start date, as well as the water table. The dewatering aspect is probably the key to the whole job.

The plans and specifications for the Extend Utilities Cool Home utilidor project (the “Cool Home project”) contained detailed information as to the expectable sub[244] surface groundwater conditions at the construction site. This information was in the form of test hole soil boring logs, monitoring well data, snowfall data, and other hy-drologic information. Bidders were provided with two sets of boring logs. The first reflect borings taken in 1965. Eight of these borings were in the general area of the Cool Home construction site:

Hole Number Location7 Date Depth to Groundwater
AP-4009 MH 800 27 Aug. 1965 4.7 feet
AP-4010 MH A/MH B 27 Aug. 1965 3.7 feet
AP-4011 MH A/MH B 27 Aug. 1965 4.6 feet
AP-4012 MH A/MH B 27 Aug. 1965 4.8 feet
AP-40138 27 Aug. 1965 4.7 feet
AP-4069 MH P/MH 822 9 Sep. 1965 6.0 feet
AP-40719 MH P/MH 822 9 Sep. 1965 3.6 feet
AP-4072 MH P/MH 822 10 Sep. 1965 3.8 feet
AP-4076 MH M/MH P 10 Sep. 1965 4.8 feet

[245] FIGURE 1*

[[Image here]]

[246] Depth to groundwater signifies the number of feet from the top of the hole to the groundwater level. However, because the 1965 boring logs did not provide the elevation for the top of the hole (which would normally be expressed in feet above sea level), bidders could not readily determine the groundwater level from these logs.

Bidders were also provided with twenty-one soil boring logs taken in March 1984. Four of these logs were taken at test holes near Twin Lakes, approximately 1200 feet east of the Cool Home construction site. In addition, five of the logs did not provide the depth to groundwater measurement, thus preventing a determination of the groundwater level. The remaining boring logs contained the following groundwater level information:

Hole Number Location Date Groundwater Level
AP-4482 MH D/MH E 9 Mar. 1984 523.5 feet
AP-4483 MH E/MH P 9 Mar. 1984 523.5 feet
AP-4485 MH E/MH F 10 Mar. 1984 518.0 feet
AP-4486 MH P/MH G 11 Mar. 1984 526.5 feet
AP-4487P MH G/MH H 11 Mar. 1984 524.5 feet
AP-4488 MH H/MH J 11 Mar. 1984 522.0 feet
AP-4489 MH H/MH J 11 Mar. 1984 526.0 feet
AP-4490(P) MH J/MH K 12 Mar. 198310 525.0 feet
AP-4494 MH H/MH J 13 Mar. 1984 523.5 feet
AP-4497P MH E/MH P 14 Mar. 1984 524.0 feet
AP-4498 MH P/MH G 14 Mar. 1984 523.0 feet
AP-4501 MH H/MH J 15 Mar. 1984 525.0 feet
AP-4504 Twin Lakes 16 Mar. 1984 524.9 feet
AP-4505 Twin Lakes 16 Mar. 1984 518.0 feet
AP-4506 Twin Lakes 16 Mar. 1984 522.5 feet
AP-4507 Twin Lakes 16 Mar. 1984 526.0 feet

The bidding documents also contained the following information regarding dewater-ing and the boring logs:

Elevations of water table shown on the exploration logs were measured at the time of drilling and shall be considered as representative only for that specific location at that specific time. Additional data on subsurface conditions are available for review in the Office of the Alaska District Engineer [in Anchorage].
... Excavation shall be performed in the dry— Excavations shall be kept free from ponding until the permanent work in the excavations have been completely backfilled. Piezometric observations are provided below. Such ground water level information as appears in the contract documents is for general information only, and shall not constitute a basis for claim for differing site conditions. Actual water levels encountered may vary widely from those shown.

WATER TABLE OBSERVATIONS

Boring No, Date Elevation*

AP-4487 11 Mar 84 524.5

13 Mar 84 524.6

AP-4490 12 Mar 84 525.0

AP-4497 14 Mar 84 524.0

Free access — add to your briefcase to read the full text and ask questions with AI

North Slope Technical Ltd. v. United States, 34 Cont. Cas. Fed. 75,430, 14 Cl. Ct. 242, 1988 U.S. Claims LEXIS 6, 1988 WL 5080 (cc 1988).

34 Cont. Cas. Fed. 75,430 (North Slope Technical Ltd. v. United States) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

URS Group, Inc. v. Tetra Tech FW, Inc.
181 P.3d 380 (Colorado Court of Appeals, 2008)
George Sollitt Construction Co. v. United States
64 Fed. Cl. 229 (Federal Claims, 2005)
R.P. Richards Construction Co. v. United States
51 Fed. Cl. 116 (Federal Claims, 2001)
D.F.K. Enterprises, Inc. v. United States
45 Fed. Cl. 280 (Federal Claims, 1999)
Opinion No. (1997)
Oklahoma Attorney General Reports, 1997
Kit-San-Azusa J.V. v. United States
40 Cont. Cas. Fed. 76,732 (Federal Claims, 1995)
Municipality of Anchorage v. Frank Coluccio Construction Co.
826 P.2d 316 (Alaska Supreme Court, 1992)
Neal & Co. v. United States
36 Cont. Cas. Fed. 75,802 (Court of Claims, 1990)