Municipality of Anchorage v. Frank Coluccio Construction Co.

826 P.2d 316, 1992 Alas. LEXIS 16
CourtAlaska Supreme Court
DecidedFebruary 7, 1992
DocketS-3898, S-3844, S-4203 and S-4267
StatusPublished
Cited by15 cases

This text of 826 P.2d 316 (Municipality of Anchorage v. Frank Coluccio Construction Co.) is published on Counsel Stack Legal Research, covering Alaska Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Municipality of Anchorage v. Frank Coluccio Construction Co., 826 P.2d 316, 1992 Alas. LEXIS 16 (Ala. 1992).

Opinion

OPINION

BURKE, Justice.

This appeal arises from a contract dispute between Frank Coluccio Construction Company, on the one hand, and the Municipality of Anchorage, The Anchorage Water and Wastewater Utility, and CH2M Hill Northwest, on the other. The construction company sued the other parties after they denied its claim for equitable adjustment of contract price based on encountering differing site conditions. After both an arbitration proceeding and a jury trial, Frank Coluccio Construction obtained a verdict of breach of contract and an award of damages. The case comes before this court on various appeals and cross-appeals.

I

The facts of this contract dispute pertain to three rather discrete controversies. The first controversy concerns the conduct of a jury trial with Frank Coluccio Construction Company (FCCC) as plaintiff against defendants Municipality of Anchorage and The Anchorage Water and Wastewater Utility (collectively referred to as MOA). The second controversy involves the same parties, but concerns FCCC’s claims for costs and fees arising out of the trial and a prior arbitration proceeding. The final controversy is between FCCC and CH2M Hill Northwest, Inc. (CH2M Hill), who was originally a defendant in FCCC’s underlying suit; the present dispute arises from the award of costs and fees to CH2M Hill after it won summary judgment against FCCC.

A

In September 1986 FCCC was successful bidder on a $5 million, fixed-price contract for construction of an “effluent tunnel” at Point Woronzof. The 2700 foot tunnel was to be constructed through use of a tunnel boring machine. Because the project involved use of federal funds, the contract included a federally mandated “differing site conditions” (DSC) clause:

(a) The contractor shall promptly, and before such conditions are disturbed, notify the recipient in writing of:
(1) Subsurface or latent physical conditions at the site differing materially from those indicated in this subagreement, or
(2) Unknown physical conditions at the site, of an unusual nature, differing materially from those ordinarily encountered and generally recognized as inhering in work of the character provided for in this subagreement.
(b) The recipient shall promptly investigate the conditions. If it finds that conditions materially differ and will cause an increase or decrease in the contractor's cost or the time required to perform any part of the work under this subagreement, whether or not changed as a result of such conditions, the recipient shall make an equitable adjustment and modify the subagreement in writing.

Such clauses, which have long been staples of federal contracts, are intended “to prevent bidders from increasing their bid prices to protect against misfortunes resulting from unforeseen developments, and thus avoid turning a construction contract into a ‘gambling transaction.’ ” J.F. Shea Co. v. United States, 4 Cl.Ct. 46, 50 (1983) (citation omitted).

FCCC began preliminary work in January 1987 and began boring the tunnel on *319 March 26, 1987. On April 21, 1987, after completing about 850 feet of tunneling, FCCC encountered “running ground,” which it considered a DSC. 1 Similar conditions were encountered about 100 feet farther on. In order to deal with the running ground, FCCC modified its tunnel boring machine and changed its tunneling methods. Pursuant to the DSC clause, FCCC sought equitable price adjustments of more than $3.8 million for increased expenses caused by the running ground. MOA denied the claims in their entirety, apparently on the basis that FCCC encountered no ground condition that differed materially from what was indicated in the contract.

FCCC then sued MOA and CH2M Hill, which had provided design and construction management services to the municipality. FCCC alleged breach of contract by MOA in not making an equitable adjustment under the DSC clause and in failing to disclose all material information in regard to the contract; unjust enrichment by MOA in receiving the benefit of the extra work done by FCCC to deal with the running ground; breach of implied warranty of suitability of plans and specifications by MOA and CH2M Hill; negligence by MOA and CH2M Hill in designing the plans and specifications and in disclosing material information; and fraudulent misrepresentation by MOA of site conditions. The fraud claim was eventually dismissed by stipulation of the parties.

B

In September 1988 FCCC, MOA, and CH2M Hill entered into an “Agreement to Arbitrate.” They declared that they “entered into this Agreement in order to resolve the enumerated complex entitlement issues involved in this dispute expeditiously and dispositively, by submitting these issues to a panel of experts.” The agreement recited the parties’ intent that the arbitration panel’s resolution of “liability/entitlement issues” be “binding and nonappealable.” It provided that the arbitrators would be non-attorneys with “expertise in the field of tunneling technology and design and underground construction.”

After outlining fairly specific procedural guidelines, the agreement addressed the arbitrators’ product:

III. AWARD
The decision shall be in writing, signed by the arbitrators, and shall state the disposition of the case, identifying the prevailing party. It shall not allocate fault, if any, by percentage between the defendants. Dissent may be noted and identified.
[[Image here]]
3.2 Findings of Fact and Conclusions of Law. The panel shall enter formal Findings of Fact and Conclusions of Law to identify its decision-making process. The participants shall each, after the panel renders its written decision, prepare and submit proposed Findings of Fact and Conclusions of Law to the panel, from which the panel shall assemble an appropriate document. All members of the panel shall execute the adopted Findings of Fact, noting and identifying dissent, if appropriate. The executed Findings of Fact and Conclusions of Law shall be the arbitrators’ final decision for purposes of AS 09.43, et seq.
[[Image here]]
3.5 Disposition of Decision. Upon application of a party, the decision may be filed with the Superior Court of the State of Alaska, to become an official part of the record of proceedings. Upon application of a party, the Court shall confirm the decision pursuant to AS 09.-43.110 unless, within the time limits imposed by AS 09.43.120 and AS 09.43.130, grounds are urged for vacating or modifying or correcting the decision.

*320 The superior court approved and ratified the arbitration agreement on December 2, 1988.

The arbitration took place shortly thereafter. As specified by the arbitration agreement, the proceedings were fairly formal: extensive discovery was undertaken prior to the hearings; counsel represented the parties; the witnesses testified under oath; and each side presented engineering and tunneling experts.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
826 P.2d 316, 1992 Alas. LEXIS 16, Counsel Stack Legal Research, https://law.counselstack.com/opinion/municipality-of-anchorage-v-frank-coluccio-construction-co-alaska-1992.