Fletcher v. Trademark Construction, Inc.

80 P.3d 725, 2003 Alas. LEXIS 146, 2003 WL 22871928
CourtAlaska Supreme Court
DecidedDecember 5, 2003
DocketS-10609
StatusPublished
Cited by8 cases

This text of 80 P.3d 725 (Fletcher v. Trademark Construction, Inc.) is published on Counsel Stack Legal Research, covering Alaska Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Fletcher v. Trademark Construction, Inc., 80 P.3d 725, 2003 Alas. LEXIS 146, 2003 WL 22871928 (Ala. 2003).

Opinion

OPINION

CARPENETI, Justice.

I. INTRODUCTION

Alaska Electric Company appeals the superior court’s dismissal of its contract action against Trademark Construction, contending that the court made insufficient findings of fact and conclusions of law when it dismissed the case under Alaska Rule of Civil Procedure 41(b) for failure to prove damages with sufficient certainty. Alaska Electric also contends that the trial court made various errors in its application of Civil Rule 41(b). Because the superior court’s findings of fact are sufficient to indicate the legal and factual bases for its ruling, and because its interpretation of Civil Rule 41(b) was proper, we affirm.

*727 II. FACTS AND PROCEEDINGS

A. Facts

Appellee Trademark Construction entered into a contract with the State of Alaska to renovate the seventh and eighth floors of the Bank of America Center in Anchorage in December 1998. Trademark’s successful bid included a subcontract bid of $74,724 for electrical work by appellant Alaska Electric. The general contract called for the work to be completed by January 31,1999. The subcontract specified that time was of the essence, and that if changes or additional work were ordered by the state, Alaska Electric would have to obtain a written order from Trademark specifying and approving the work. The subcontract also governed how costs would be proved if the contract was changed:

6.1.2 In the event that [Trademark], or [the State of Alaska] shall order changes in Subcontract work, or order additional work, the Subcontractor shall furnish a price breakdown with his proposal in connection with the change order, itemized as required by [Trademark], or the [State of Alaska]. Unless otherwise directed, the breakdown shall be in sufficient detail to permit an analysis of all material, labor, equipment, and overhead costs as well as profit, and shall cover all work involved to accomplish the change, whether deleted, added, or changed.

Based on its certified payroll' records, it appears that Trademark worked on the project from approximately December 28, 1998 to March 6, 1999. Various changes were made to the project, and the parties initially sought to authorize every change.

On December 22, 1998 the state issued drawings and a list of changes known as “Revision No. 2,” which made various changes, additions, and deletions to the original project. The parties submitted to the state an initial proposal of $40,824 to cover the extra electrical subcontract work on January 8, 1999; in a January 25 meeting between the parties and the state, this was reduced verbally to $24,096 because the state decided that the initial proposal had included work not required by Revision No. 2. The state requested further substantiation of the details of the reduced proposal at that time, but none was provided. In a January 28, 1999 document apparently drafted by Alaska Electric, Trademark promised to compensate Alaska Electric for additional work including “[a]ll revisions of #2 dated December 22, 1998, [a]ll extras associated with liebert units, ... i.e., additional work that was not clearly defined on the original prints ,.. plus all additionally incurred administrative services.” In this document Trademark agreed “to pay Alaska Electric for all time and materials expended in completing this work, plus profit.” On March 30, 1999 Alaska Electric sent an invoice to Trademark totaling $92,835 for labor alone on the additional parts of the contract. Trademark demurred, and attorneys for the parties worked for some time to try to resolve the dispute. By March of 2001 Alaska Electric’s final invoice for labor and materials reached $154,475; with profit and interest, its final bill totaled $230,476.

B. Proceedings

Alaska Electric filed suit against Trademark in September 2000, alleging that Trademark owed at least $200,000 on the unpaid “extra” and revised parts of the contract, and also alleging business damage, a claim that was later dismissed. A bench trial commenced before Superior Court Judge Peter A. Michalski in early December 2001, and plaintiff Alaska Electric called two witnesses: David Fletcher, the head of the business and negotiator of the above contracts, and Terrance Hix, a volunteer data manager at the Alaska Electric office.

1. Evidence at trial

Fletcher and Hix testified extensively about the project and its expenses and explained numerous documents relating to their labor and materials costs. Three exhibits and one handwritten chart were especially important at trial. The first was plaintiffs Exhibit 10. This was the certified payroll for the entire project submitted by Alaska Electric to the Alaska Department of Labor, which Hix created from time cards filled out by foremen at the job site. The certified *728 payroll documented regular and overtime hours worked, hourly pay rates, and the type of benefits set by the union, although not the union benefits themselves. The certified payroll did not distinguish between hours worked on the contents of the original contract and hours worked to fulfill “extra” or “Revision No. 2” requirements.

The second important exhibit was plaintiffs Exhibit 59. This was a spreadsheet that purported to differentiate between hours worked on the original contract and hours worked on the additional and Revision No. 2 requirements. Hix prepared this spreadsheet during the completion of the project partly from time cards completed by foremen at the job site and partly on the basis of when the work was completed. “Work order numbers” on the spreadsheet reflected different job codes assigned by Fletcher and Hix to the two sets of contracts. The final row of the spreadsheet totaled the total regular and overtime hours worked on the two aspects of the project. On cross-examination, the witnesses testified that the foremen who filled out the time cards had not always been provided with the project codes that differentiated between work on the original contract and work on the revisions, and that not all of the time cards contained those differentiated codes. There was also testimony that this exhibit listed more work hours for certain workers in certain weeks than could be substantiated from the time cards.

The third important exhibit was plaintiffs Exhibit 43. This was also a spreadsheet, and it was created by Hix and Fletcher during February 1999 for the purpose of determining changes in materials needed as a result of the revisions and changes to the original contract. Pricing for the materials was not included. Although the spreadsheet included a “manhours” component for every change, these figures were only Fletcher’s estimates as to how much time each job would take.

The fourth important document was a chart compiled by Fletcher in the courtroom during the trial. Apparently this was how Alaska Electric sought to tie the additional hours from the exhibits described above to the amount of damages sought by Alaska Electric. Fletcher testified that one week before trial Hix had provided him with Quickbooks software that showed that his total labor costs for the contract, including gross wages and benefits paid to the union, totaled $117,656. This software had not been entered into evidence or viewed by Trademark.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Tyler Cue v. Desiree Challans
Alaska Supreme Court, 2026
Michael Johnson v. Mandy Wilson
Alaska Supreme Court, 2019
Lentine v. State
282 P.3d 369 (Alaska Supreme Court, 2012)
3-D & Co. v. Tew's Excavating, Inc.
258 P.3d 819 (Alaska Supreme Court, 2011)
Foster v. Professional Guardian Services Corp.
258 P.3d 102 (Alaska Supreme Court, 2011)
Crowley v. State, Department of Health & Social Services
253 P.3d 1226 (Alaska Supreme Court, 2011)
Azimi v. Johns
254 P.3d 1054 (Alaska Supreme Court, 2011)
US Ex Rel. Poong lim/pert v. Dick pacific/ghemm
399 F. Supp. 2d 1040 (D. Alaska, 2005)

Cite This Page — Counsel Stack

Bluebook (online)
80 P.3d 725, 2003 Alas. LEXIS 146, 2003 WL 22871928, Counsel Stack Legal Research, https://law.counselstack.com/opinion/fletcher-v-trademark-construction-inc-alaska-2003.