3-D & Co. v. Tew's Excavating, Inc.

258 P.3d 819, 2011 Alas. LEXIS 88, 2011 WL 3795508
CourtAlaska Supreme Court
DecidedAugust 26, 2011
DocketS-13425
StatusPublished
Cited by6 cases

This text of 258 P.3d 819 (3-D & Co. v. Tew's Excavating, Inc.) is published on Counsel Stack Legal Research, covering Alaska Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
3-D & Co. v. Tew's Excavating, Inc., 258 P.3d 819, 2011 Alas. LEXIS 88, 2011 WL 3795508 (Ala. 2011).

Opinion

*822 OPINION

STOWERS, Justice.

I. INTRODUCTION

This case involves a contract dispute between 8-D & Co. and Tew's Excavating, Inc. The dispute is over the terms of a construction contract for two roads in Scenic View Subdivision of the Matanuska-Susitna Borough. 3-D & Co. contends that the superior court applied the wrong legal standards and arrived at the wrong factual conclusions regarding the terms of the contract by: (1) admitting extrinsic evidence to determine the meaning of the contract, (2) applying the preponderance of the evidence standard of proof rather than a clear and convincing evidence standard, (3) finding no material breach of the contract, (4) finding that the contract was for a fixed price, (5) finding that both parties assented to constructing a T-intersection rather than a cul-de-sac, (6) finding that a construction change would likely be accepted by the Matanuska-Susitna Borough, (7) awarding damages for the culvert work, (8) finding that there was not sufficient proof for damages on road width deficiencies, (9) finding that there was no breach of contract in not meeting the contract deadline, (10) erroneously applying theories of estoppel or waiver in awarding no damages, (11) considering the duty to notify and provide an opportunity to cure, and (12) failing to award damages for the incidental cost of removing the lien placed on the property. We affirm the superior court's decisions in all respects.

II. FACTS AND PROCEEDINGS

3-D & Co. (Derr) is an Alaskan realty development corporation wholly owned by Daniel Derr. Derr purchased 40 acres of land within the Matanuska-Susitna Borough (the Borough) intending to develop it into Scenic View Subdivision. The land was located just beyond the developed portion of Foothills Boulevard.

Tew's Excavating, Inc. (Tew) is an Alaskan corporation whose business involves road maintenance, contracting work, and road construction. Prior to his contract with Derr, Tew had completed two road construction projects: one for the City of Houston and another for a private subdivision. Both jobs utilized three inch minus gravel" 1 In addition Tew had at least three contracts with the Borough to provide road maintenance.

In late 2005 or early 2006 Derr contacted Tew about constructing roads in his new subdivision. Tew provided Derr with an estimate for the work on one of these roads, Foothills Boulevard. This estimate set a price of $30 per linear foot to construct the road to Borough standards. The price estimate indicated, "This will not include any gravel, engineering, culverts or clearing." At the time of the estimate, Derr anticipated performing the clearing and grubbing on Foothills Boulevard himself. Derr was unable to complete the clearing and grubbing because he was arrested for felony DUI. Derr spent the next two years in jail and residential treatment. Due to the arrest Tew and Derr discussed whether the project would continue. Tew visited Derr multiple times to discuss various options for the project. In May 2006 Derr and Tew orally agreed that Tew would clear and grub the road-charging hourly-and construct Foothills Boulevard pursuant to the terms and conditions of the estimate. The parties did not create a written agreement about the price for the clearing and grubbing.

In May 2006 Derr and Tew began discussing the construction of Range View Drive. By July 2006 Tew provided an oral estimate for the work and Derr agreed to the terms. Tew was now responsible for building both Foothills Boulevard and Range View Drive.

Tew billed Derr periodically for the work on Derr's land in the spring of 2006. Disputes arose about the bills during this period. Tew provided Derr with invoices detailing the equipment used and hours worked. Derr believed that the work was taking too long and he was paying too much. The parties negotiated and revised several versions of a *823 contract before they agreed to sign a written contract on August 14, 2006.

The written contract specified: "All gravel for road{s] will be taken from Tract A. Per [the Borough's] preliminary plat." Derr wanted to turn the gravel pit in Tract A from which road gravel was to be removed into a pond, and had specific instructions for how the gravel should be removed. Tew did not inspect the gravel prior to the formation of the contract. The available gravel was sufficient to meet the Borough's standards for the bottom 18 inches of the road but insufficient for the top six inches. 2 Tew requested that Derr rent screening equipment needed to ensure three inch minus gravel was used for the top of the road and offered to do the physical labor involved in sereening the gravel. Derr did not want to incur the costs of this process, so Tew suggested he could try processing the gravel using graders and gird-rollers to crush smaller rocks and remove larger rocks. Tew explained that this processing would take longer than screening and would not produce true three inch minus gravel. Tew said that the Borough would probably approve the road anyway and indicated that he had used the same process on a previous job that passed the Borough's inspection. Derr agreed to process the gravel using Tew's equipment.

Tew processed the gravel as he and Derr agreed, completing the project in late October 2006. When he completed the processing, he informed Wayne Whaley, Derr's on-site representative, that the project was complete; Whaley agreed. Whaley inspected the project and determined that it was ready for the Borough's inspection. After Whaley's inspection Tew moved his equipment off of Derr's property.

Derr never informed Tew that he felt that Tew's work was incomplete or insufficient. Derr measured random road widths and determined the road was not uniformly 24 feet wide. He felt some of the culvert installations were incomplete or in need of repair. He noted that some of the rocks in the road were not three inch minus and some of the rocks in the ditches were not six inch minus, thus not meeting Borough standards. He felt that the angle of the road slope was improper at various points. He was also unsatisfied with the intersection of Range View and Rolling Hills because it formed a T-intersection rather than a cul-de-sac.

The only information that Tew received about potential problems was a communication from Whaley indicating that minor culvert repairs or modifications might be required. Tew was willing to make the repairs if needed.

In the fall of 2006, while Tew was still working on the project, Derr solicited bids from other companies to complete work on the roads. Derr received bids from Northern Dame (Fall 2006 oral estimate), 3 Kenner-son Excavation (October 12, 2006) and Steppers Construction (October 17, 2006) 4 to complete road construction. He chose not to use any of these contractors and did not inform Tew that Tew had not completed the job to his satisfaction.

Tew submitted a final written invoice to Derr for the remaining $50,000 Derr owed. When Derr did not pay this final invoice, Tew phoned Derr several times about the money but still did not receive payment.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
258 P.3d 819, 2011 Alas. LEXIS 88, 2011 WL 3795508, Counsel Stack Legal Research, https://law.counselstack.com/opinion/3-d-co-v-tews-excavating-inc-alaska-2011.