Alaska Northern Development, Inc. v. Alyeska Pipeline Service Co.

666 P.2d 33, 36 U.C.C. Rep. Serv. (West) 1527, 1983 Alas. LEXIS 441
CourtAlaska Supreme Court
DecidedJune 10, 1983
Docket6353
StatusPublished
Cited by45 cases

This text of 666 P.2d 33 (Alaska Northern Development, Inc. v. Alyeska Pipeline Service Co.) is published on Counsel Stack Legal Research, covering Alaska Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Alaska Northern Development, Inc. v. Alyeska Pipeline Service Co., 666 P.2d 33, 36 U.C.C. Rep. Serv. (West) 1527, 1983 Alas. LEXIS 441 (Ala. 1983).

Opinion

OPINION

COMPTON, Justice.

Alaska Northern Development, Inc. (“AND”) appeals a judgment in favor of Alyeska Pipeline Service Co. (“Alyeska”) in a dispute involving contract formation and interpretation. For the reasons stated below, we affirm.

I. FACTUAL AND PROCEDURAL BACKGROUND

In late October or early November 1976, David Reed, a shareholder and corporate president of AND, initiated discussion with Alyeska personnel in Fairbanks regarding the purchase of surplus parts. The Alyeska employees with whom Reed dealt were Juel Tyson, Clarence Terwilleger and Donald Bruce.

After a series of discussions, Terwilleger indicated that Reed’s proposal should be put in writing so it could be submitted to management. With the assistance of AND’s legal counsel, Reed prepared a letter of intent dated December 10, 1976. In this letter, AND proposed to purchase “the entire Alyeska inventory of Caterpillar parts.” The place for the purchase price was left blank.

Alyeska responded with its own letter of intent dated December 11,1976. The letter was drafted by Bruce and Tyson in consultation with William Riekett, Alyeska’s manager of Contracts and Material Management. Again, the price term was absent. The letter contained the following language, which is the focus of this lawsuit: “Please consider this as said letter of intent, subject to the final approval of the owner committee.” (Emphasis added.)

Reed was given an unsigned draft of the December 11 letter, which was reviewed by AND’s legal counsel. Reed then met with Riekett, and they agreed on sixty-five percent of Alyeska’s price as the price term to be filled in the blank on the December 11 letter. Riekett filled in the blank as agreed and signed the letter. In March 1977, the owner committee rejected the proposal embodied in the December 11 letter of intent.

AND contends that the parties understood the subject to approval language to mean that the Alyeska owner committee 1 would review the proposed agreement only to determine whether the price was fair and reasonable. Alyeska contends that Reed was never advised of any such limitation on *36 the authority of the owner committee. In April 1977, AND filed a complaint alleging that there was a contract between AND and Alyeska, which Alyeska breached. The complaint was later amended to include counts for reformation and punitive damages.

Alyeska moved for summary judgment on the punitive damages and breach of contract counts. The superior court granted summary judgment in favor of Alyeska on the punitive damages count. The court initially denied Alyeska’s motion for summary judgment on the breach of contract claim; however, based on a review of the case after discovery had closed, the court announced at a hearing on September 26, 1980, that it would reverse its earlier ruling and grant Alyeska’s motion. The court confirmed this ruling at a hearing on November 5, 1980, after consideration of AND’s Motion for Clarification.

The superior court explained its rationale for granting summary judgment against AND on the breach of contract claim as follows. The court recognized that AND predicated its breach of contract claim on the theory that Reed’s letter of December 10th was an offer and that Rickett’s letter of December 11th was an acceptance of that offer. Viewed in that light, the court addressed “four theoretical possibilities in analyzing the interplay between the December 11th letter and the December 10th letter.” First, the writings could be construed as an offer with a responding promise to pass the offer on to the owner committee, which was responsible for making such determinations. Second, the letters could be construed as an offer and a counter-offer that AND rejected. Third, the letters could be considered as an offer with a responding counter-offer containing, among other things, the unlimited right of the owner committee to review and approve. The court ruled that if the letters were ultimately found to fall into one of these three categories, AND would not prevail, either because the offer embodied in the December 10 letter was never accepted, or because the owner committee never approved the proposal.

The only way in which AND might prevail was on the fourth possibility, i.e., the letters could be construed as an offer followed by a counter-offer limiting the authority of the owner committee to review only the contract price. The court ruled that AND could not establish a breach of contract claim under the fourth construction of the letters because the parol evidence rule barred the admission of extrinsic evidence that might limit the scope of the owner committee’s approval power. 2 The only recourse for AND, therefore, was to seek reformation of the December 11 letter that limited the owner committee approval clause.

The case proceeded to trial on the reformation claim. After a six-week trial, the superior court concluded that AND had failed to establish that a specific agreement was not properly reduced to writing and therefore rejected its request to reform the December 11 letter. Attorney’s fees were awarded to Alyeska.

On appeal, AND does not challenge the superior court’s denial of reformation. Instead, it contends that the superior court erred in granting summary judgment on the breach of contract and punitive damages counts, erred in denying a trial by jury on the reformation count, erred in not permitting cross-examination for purposes of impeachment, and erred in awarding attorney’s fees to Alyeska.

II. APPLICATION OF THE PAROL EVIDENCE RULE

The superior court held that the parol evidence rule of the Uniform Commercial Code, section 2-202, codified as AS 45.02.-202, 3 applied to the December 11 letter and *37 therefore no extrinsic evidence could be presented to a jury which limited the owner committee’s right of approval. AND contends that the court erred in applying the parol evidence rule. We disagree.

In order to exclude parol evidence concerning the inclusion of additional terms to a writing, a court must make the following determinations. First, the court must determine whether the writing under scrutiny was integrated, i.e., intended by the parties as a final expression of their agreement with respect to some or all of the terms included in the writing. Second, the court must determine whether evidence of a prior or contemporaneous agreement contradicts or is inconsistent with the integrated portion. If the evidence is contradictory or inconsistent, it is inadmissible. If it is consistent, it may nevertheless be excluded if the court concludes that the consistent term would necessarily have been included in the writing by the parties if they had intended it to be part of their agreement. AS 45.02.202; Braund, Inc. v. White, 486 P.2d 50, 56 (Alaska 1971); U.C.C. § 2-202 comment 3 (1977).

A. Was the December 11 Letter a Partial Integration?

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Brent McCormick v. Chippewa, Inc. and Louis Olson
459 P.3d 1172 (Alaska Supreme Court, 2020)
Apex LLC v. Sharing World, Inc.
206 Cal. App. 4th 999 (California Court of Appeal, 2012)
3-D & Co. v. Tew's Excavating, Inc.
258 P.3d 819 (Alaska Supreme Court, 2011)
Estate of Polushkin Ex Rel. Polushkin v. Maw
170 P.3d 162 (Alaska Supreme Court, 2007)
Marsingill v. O'MALLEY
128 P.3d 151 (Alaska Supreme Court, 2006)
RGJ Associates, Inc. v. Stainsafe, Inc.
338 F. Supp. 2d 215 (D. Massachusetts, 2004)
Still v. Cunningham
94 P.3d 1100 (Alaska Supreme Court, 2004)
City of Kodiak v. Samaniego
83 P.3d 1077 (Alaska Supreme Court, 2004)
Froines v. Valdez Fisheries Development Ass'n
75 P.3d 83 (Alaska Supreme Court, 2003)
Song v. Song
972 P.2d 589 (Alaska Supreme Court, 1999)
Little Susitna Construction Co. v. Soil Processing, Inc.
944 P.2d 20 (Alaska Supreme Court, 1997)
Anchorage Nissan, Inc. v. State
941 P.2d 1229 (Alaska Supreme Court, 1997)
Wasserman v. Bartholomew
923 P.2d 806 (Alaska Supreme Court, 1996)
City of Fairbanks v. Amoco Chemical Co.
836 F. Supp. 690 (D. Alaska, 1993)
Keffer v. Keffer
852 P.2d 394 (Alaska Supreme Court, 1993)

Cite This Page — Counsel Stack

Bluebook (online)
666 P.2d 33, 36 U.C.C. Rep. Serv. (West) 1527, 1983 Alas. LEXIS 441, Counsel Stack Legal Research, https://law.counselstack.com/opinion/alaska-northern-development-inc-v-alyeska-pipeline-service-co-alaska-1983.