Little Susitna Construction Co. v. Soil Processing, Inc.

944 P.2d 20, 1997 Alas. LEXIS 111
CourtAlaska Supreme Court
DecidedAugust 1, 1997
DocketS-7451
StatusPublished
Cited by33 cases

This text of 944 P.2d 20 (Little Susitna Construction Co. v. Soil Processing, Inc.) is published on Counsel Stack Legal Research, covering Alaska Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Little Susitna Construction Co. v. Soil Processing, Inc., 944 P.2d 20, 1997 Alas. LEXIS 111 (Ala. 1997).

Opinion

OPINION

BRYNER, Justice.

This appeal arises from a dispute centering on a “turn-key” provision in an equipment lease.

*22 I. FACTS AND PROCEEDINGS BELOW

In September of 1992, Little Susitna Construction Company, Inc. (LSC) negotiated ■with the United States Army Corps of Engineers and the Small Business Administration (SBA) for the award of a contract to remediate fuel-contaminated soil at Fort Richardson. On September 4,1992, in contemplation of being awarded the contract, LSC entered into a “turn-key” lease agreement with Soil Processing, Inc. (SPI).

The agreement called for SPI to provide LSC with thermal soil-remediation equipment on-site at Fort Richardson “at the turn key price of $44.00 per ton” of soil processed. SPI was also to receive $5,500.00 for mobilizing its equipment and an equal sum for demobilizing. In addition, the agreement provided that LSC would pay SPI $3,000.00 for each day of stopped production. 1

LSC originally planned to begin processing soil in mid-October and to complete the project in the first week of December. On September 28, 1992, the Corps of Engineers and SBA formally awarded LSC the Fort Richardson contract. On October 5, LSC. notified SPI to proceed with mobilization. SPI had its equipment on-site by October 15.

Before actually getting underway, however, the project encountered significant delay. LSC did not begin remediating soil until the first week of January 1993. This delay forced operations to be carried out in adverse conditions. Freezing weather led to numerous equipment breakdowns and reduced the productivity of the workforce; the soil became much more difficult to process when frozen. Repairs and a five-month esctension in the period of operation significantly increased LSC’s costs on the project.

As a result, LSC withheld payments from SPI. LSC claimed that SPI was responsible for the delays, repairs, and all related costs. LSC also claimed that SPI failed to provide equipment and services it had contracted to supply. LSC eventually received contract payments of $681,647.99 but paid SPI nothing.

SPI sued LSC for breach of contract, seeking damages of $189,692.92 under the terms of the lease agreement. LSC counterclaimed for negligence and breach of contract, seeking damages of $312,843.00. The case came to trial before a jury in Anchorage. Upon conclusion of .the evidence, the trial court entered a directed verdict for SPI on its equipment lease claim, determining that, at the contract rate of $44.00 per ton of soil processed, SPI was due $178,200. The court submitted all remaining issues to the jury. The jury returned a special verdict finding in SPI’s favor and rejecting all but a minor portion of LSC’s counterclaim. The trial court entered judgment for SPI in the principal amount of $176,133, to which it added pre-judgment interest of $47,275 and attorney’s fees of $24,840.81. LSC appealed.

II. DISCUSSION

A. Meaning of Agreement’s “Turrir-Key” Provision

On appeal, LSC focuses initially on the “turn-key” provision of the September 4, 1992, lease agreement.

;At trial, LSC requested a jury instruction defining the term “turn-key” to require SPI to assume all risks arising from weather-related and other job-site problems. The trial court declined to define turn-key, instead leaving the jury to decide the term’s meaning:

In order to find for [LSC] on this claim, you must find that it is more likely than not that both parties understood and intended, or reasonably should have understood and intended, that “turn key” as used in this lease meant that SPI would pay for all damages to [LSC] resulting from weather or other problems on the job.

*23 The jury’s special verdict concluded that SPI did not breach its contract by failing to pay for labor costs incurred by LSC as a result of job-site equipment problems.

LSC challenges the trial court’s failure to define turn-key, arguing that “turn-key is a legal term of art and a legal term with legal meaning.” In LSC’s view, “ ‘a turn-key job’ is any job or contract in which a contractor agrees to complete the work to a specified point and to assume all risks.” LSC maintains that by agreeing to furnish thermal remediation equipment to LSC “at the turn key price of $44.00 per ton,” SPI bound itself as a matter of law to absorb all added costs resulting from equipment breakdowns or freezing weather throughout the course of the soil remediation project. LSC insists that the trial, court should have determined that this is what turn-key meant, that the court should have instructed the jury accordingly, and that there was no evidence to support the jury’s verdict declining to find a turn-key breach.

Interpreting a written contract is generally a task for the trial court; however, interpretation becomes a task for the trier of fact when the parties present extrinsic evidence to clarify a contract’s meaning, when this evidence points toward conflicting interpretations of the contract, and when the contract itself is reasonably susceptible of either meaning. Alaska Diversified, Contrs., Inc. v. Lower Kuskokwim Sch. Dist., 778 P.2d 581, 584 (Alaska 1989); Restatement (Second) of Contracts § 212(2). In such cases, the trial court initially determines whether the extrinsic evidence meets the criteria to create a jury question; when the court finds that the extrinsic evidence does not conflict or is incompatible with the terms of the written contract, interpretation remains a question of law for the court’s determination. Alaska Diversified, 778 P.2d at 584; Alaska N. Dev., Inc. v. Alyeska Pipeline Serv. Co., 666 P.2d 33, 39 (Alaska 1983).

This court exercises its independent judgment when reviewing a trial court’s decision to leave interpretation of a contract to the jury. Cf. Alyeska Pipeline Serv. Co. v. O’Kelley, 645 P.2d 767, 771 (Alaska 1982). In contrast, we give deferential review to the jury’s verdict interpreting the contract: we do not reweigh the evidence but ask only whether it creates room for diversity of opinion among reasonable people. Municipality of Anchorage v. Baugh Constr. & Eng’g. Co., 722 P.2d 919, 927 (Alaska 1986). We must affirm the verdict unless the evidence to support it is completely lacking or so slight and unconvincing as to make it manifestly unreasonable and unjust. United Bonding Ins. Co. v. Castle, 444 P.2d 454, 455 (Alaska 1968).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Pelletier v. Bottari
D. Nevada, 2021
Andrew B. v. Abbie B.
494 P.3d 522 (Alaska Supreme Court, 2021)
Davin J. Anderson v. Alaska Housing Finance Corporation
462 P.3d 19 (Alaska Supreme Court, 2020)
AAA Valley Gravel, Inc. v. Totaro
325 P.3d 529 (Alaska Supreme Court, 2014)
Zamarello v. Reges
321 P.3d 387 (Alaska Supreme Court, 2014)
Hussein-Scott v. Scott
298 P.3d 179 (Alaska Supreme Court, 2013)
Rude v. Cook Inlet Region, Inc.
294 P.3d 76 (Alaska Supreme Court, 2012)
Cook v. Cook
249 P.3d 1070 (Alaska Supreme Court, 2011)
Estate of Polushkin Ex Rel. Polushkin v. Maw
170 P.3d 162 (Alaska Supreme Court, 2007)
Kay v. Danbar, Inc.
132 P.3d 262 (Alaska Supreme Court, 2006)

Cite This Page — Counsel Stack

Bluebook (online)
944 P.2d 20, 1997 Alas. LEXIS 111, Counsel Stack Legal Research, https://law.counselstack.com/opinion/little-susitna-construction-co-v-soil-processing-inc-alaska-1997.