Municipality of Anchorage v. Baugh Construction & Engineering Co.

722 P.2d 919, 1986 Alas. LEXIS 356
CourtAlaska Supreme Court
DecidedJuly 18, 1986
DocketS-699, S-831
StatusPublished
Cited by20 cases

This text of 722 P.2d 919 (Municipality of Anchorage v. Baugh Construction & Engineering Co.) is published on Counsel Stack Legal Research, covering Alaska Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Municipality of Anchorage v. Baugh Construction & Engineering Co., 722 P.2d 919, 1986 Alas. LEXIS 356 (Ala. 1986).

Opinion

OPINION

RABINOWITZ, Chief Justice.

Introduction.

This case is on appeal from a jury verdict denying liability in a suit for damages by the Municipality of Anchorage (“the municipality”) against Baugh Construction & Engineering Company (“Baugh”). The primary issue in this appeal concerns whether the superior court erred in joining the municipality’s insurer as a party plaintiff. We conclude that the insurer should not have been joined. We hold, however, that the municipality has not made a sufficient showing of prejudice from the erroneous joinder to warrant overturning the verdict. Facts.

On April 27, 1978, the municipality and Baugh entered into a contract that required Baugh to design, construct and equip a facility to shred solid waste prior to landfill disposal. The contract also called for Baugh to prepare the facility for operation, to test the facility, to train municipal personnel to operate the facility, and to warrant the design and performance of the facility.

The contract provided for an “acceptance testing phase” to last at least 30 days, under actual working conditions. This phase was to continue until conditional or final acceptance by the municipality, whichever came first. The contract also stated that until conditional or final acceptance Baugh had “complete control of, and responsibility for, the operation of the facility.” The contract provided that during the acceptance testing phase the municipality would provide and pay for all necessary personnel to operate the facility, except for a supervisor to be provided by Baugh, but that until acceptance all municipal personnel employed in the operation of the facility would be “supervised and directed entirely by [Baugh].”

The contract also required Baugh to maintain a variety of insurance for the project, including builder’s risk insurance, and provided that if Baugh failed to maintain any of the required insurance, the mu *922 nicipality could procure such insurance and hold Baugh responsible for the premiums the municipality paid. Pursuant to the contract Baugh obtained builder’s risk insurance with the Allianz Insurance Company in April, 1978. The named insured were the municipality, Baugh and their subcontractors. The policy was extended several times by Baugh, with the last extension carrying an expiration date of February 6, 1980.

Construction commenced at the plant and the acceptance testing phase began in December, 1979. Apparently the “shredder mills” were working adequately, but the “ferrous recovery system,” which was supposed to recover metals from the solid waste, was not performing well enough to meet the performance criteria for acceptance set out in the contract.

During this period relations were strained between the municipality and Baugh. On January 21,1980 Baugh apparently removed its personnel from the plant, which the municipality interpreted as an attempt to transfer control of and responsibility for the facility to the municipality. The municipality resisted these actions, stating that it had not conditionally or finally accepted the facility. After negotiations, Baugh returned to the plant and testing continued. On March 24, 1980, there was an explosion and fire at the plant which caused considerable damage. On April 29, 1980, the municipality terminated the facility contract.

The municipality had obtained a $10 million insurance policy from the Lexington Insurance Company (“Lexington”) on January 1, 1980, insuring all of the municipality’s real and/or personal property against all risks of direct physical loss or damage, including buildings, contents, fixtures, equipment, and machinery. The Lexington policy also covered buildings or structures in the course of construction. This was a “contingency” insurance policy, providing that it did not cover loss or damage already covered by other insurance, except to the extent that the other insurance did not cover the loss. The named insured on the policy was described as the municipality and “all undeclared entities authorized by the Municipal Assembly, as their interests may appear.”

On February 1, 1980, Baugh had sent a letter to the municipality advising it that the builder’s risk insurance policy was scheduled to expire on February 6 and stating that it was assuming the municipality would assume coverage as of February 7. There is no evidence in the record as to whether the municipality responded to this letter before February 7. The builder’s risk policy expired on February 6. After the explosion occurred on March 24, 1980, the municipality informed Baugh that it did not consider Baugh covered under the Lexington “contingency” policy. On January 8, 1981, the municipality submitted a proof of loss statement for the explosion to Lexington, claiming $639,475.55 under the policy.

On September 9, 1980, the municipality filed a complaint for damages against Baugh. The complaint, as subsequently amended, contained 14 counts. The only count that was tried and that is at issue here alleged that under the waste disposal facility contract Baugh bore the risk of loss for the explosion and fire because the municipality had never accepted the facility. 1

In its answer, Baugh asserted a variety of affirmative defenses including excuse of performance, conditional acceptance, comparative negligence, unclean hands, waiver, and coverage under the Lexington policy. *923 Baugh also asserted several counterclaims against the municipality. 2

Shortly after the final amended complaint was filed, the municipality and Lexington entered into a “Loan Receipt and Agreement” (“LRA”). Under the LRA Lexington “loaned” the municipality $583,-115.56, representing funds for damage and loss caused by the explosion and fire at the shredder facility. This did not equal the entire amount of damages claimed. The “loan” was to be repaid only in the event and to the extent that the municipality made any recovery in its suit against Baugh for damages from the explosion and fire. The agreement provided that Lexington would appoint, at its cost and expense, attorneys to prosecute the fire and explosion litigation up to the “loan” amount, and that these attorneys would have complete control of that litigation. The agreement also provided that Lexington would bear 82% of the costs of that litigation. Finally, Lexington ratified the municipality’s filing suit in its behalf and consented “to the Municipality’s representation of both Lexington’s and Municipality’s claims and interests ... in the sole name of the Municipality ... as plaintiff.”

Subsequently, Baugh moved under Alaska Civil Rule 19(a) to join Lexington as a party plaintiff on all claims relating to fire and explosion damages claims for relief. The municipality opposed the motion and submitted an Affidavit of Ratification from Lexington, stating that it agreed to be bound by the outcome of the municipality’s suit. The superior court ordered Lexington joined as a party plaintiff.

At trial the superior court ruled that the language of the facility contract initially placed the risk of loss from explosion on Baugh for damage to the facility.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Zoetec Partners LLC v. G Darrell Hulsey
Indiana Court of Appeals, 2025
In Re the Necessity for the Hospitalization of Jacob S.
384 P.3d 758 (Alaska Supreme Court, 2016)
Henrichs v. Chugach Alaska Corp.
250 P.3d 531 (Alaska Supreme Court, 2011)
Wooten v. Hinton
202 P.3d 1148 (Alaska Supreme Court, 2009)
Alderman v. Iditarod Properties, Inc.
32 P.3d 373 (Alaska Supreme Court, 2001)
Savage Arms, Inc. v. Western Auto Supply Co.
18 P.3d 49 (Alaska Supreme Court, 2001)
Laverty v. Alaska RR Corp.
13 P.3d 725 (Alaska Supreme Court, 2000)
Little Susitna Construction Co. v. Soil Processing, Inc.
944 P.2d 20 (Alaska Supreme Court, 1997)
Zerbetz v. Municipality of Anchorage
856 P.2d 777 (Alaska Supreme Court, 1993)
Bobich v. Stewart
843 P.2d 1232 (Alaska Supreme Court, 1992)
Bozarth v. Atlantic Richfield Oil Co.
833 P.2d 2 (Alaska Supreme Court, 1992)
Bohna v. HUGHES, THORSNESS, GANTZ
828 P.2d 745 (Alaska Supreme Court, 1992)
Nome 2000 v. Fagerstrom
799 P.2d 304 (Alaska Supreme Court, 1990)
Smith v. Lee
770 P.2d 754 (Alaska Supreme Court, 1989)
Benson v. City of Nenana
725 P.2d 490 (Alaska Supreme Court, 1986)

Cite This Page — Counsel Stack

Bluebook (online)
722 P.2d 919, 1986 Alas. LEXIS 356, Counsel Stack Legal Research, https://law.counselstack.com/opinion/municipality-of-anchorage-v-baugh-construction-engineering-co-alaska-1986.