Haskell/Davis Joint Venture v. TAKRAF USA, Inc.

CourtDistrict Court, D. Alaska
DecidedOctober 28, 2022
Docket3:20-cv-00234
StatusUnknown

This text of Haskell/Davis Joint Venture v. TAKRAF USA, Inc. (Haskell/Davis Joint Venture v. TAKRAF USA, Inc.) is published on Counsel Stack Legal Research, covering District Court, D. Alaska primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Haskell/Davis Joint Venture v. TAKRAF USA, Inc., (D. Alaska 2022).

Opinion

IN THE UNITED STATES DISTRICT COURT FOR THE DISTRICT OF ALASKA

HASKELL/DAVIS JOINT VENTURE, a joint venture consisting of Haskell Corporation and Davis Constructors and Engineers, Inc.,

Plaintiff, Case No. 3:20-cv-00234-SLG v. TAKRAF USA, INC., and NORTH AMERICAN SPECIALTY INSURANCE COMPANY, Defendants. ORDER ON DEFENDANTS’ MOTION FOR PARTIAL SUMMARY JUDGMENT Before the Court at Docket 36 is Defendants’ Motion for Partial Summary Judgment. The motion is opposed.1 Oral argument was not requested and was not necessary for the Court’s decision. For the reasons set forth in this order, Defendants’ motion is granted in part and denied in part. BACKGROUND This dispute relates to a Material Handling System (“System”) that Defendant TAKRAF USA, Inc., (“TAKRAF”) sold to Plaintiff Haskell/Davis Joint Venture (“HDJV”) as part of a construction project at the University of Alaska

1 Docket 46 (Opposition); Docket 53 (Reply). Fairbanks (“UAF”). Many of the relevant undisputed facts in this case are set out in the Court’s previous order at Docket 55 and are not repeated here.

The parties’ contractual agreement is set out in a Purchase Order that contains two provisions relevant to this motion. First, the Purchase Order contains the following clause waiving both parties’ claims for consequential damages: Seller and Buyer hereby waive any claim, other than the [liquidated damages] provided by this agreement, in contract or in tort, for any indirect, special or consequential damages, including but not limited to lost revenues, lost financing, loss or delay in production, increased costs of operations, reservoir damage and other type of consequential damages in connection with any claim arising under or in connection with this Purchase Order.2 Second, the Purchase Order contains a “Backcharge Procedure” that the parties agreed to use to remedy any defaults in TAKRAF’s performance. The provision states: “If a default in performance by Seller or its sub-suppliers causes Buyer to incur costs to correct the default, Buyer and Seller agree to utilize [TAKRAF]’s attached Backcharge Procedure to document the default and the remedy.”3 The Purchase Order defines a “backcharge” as follows: A backcharge is a cost sustained by the Buyer and chargeable to the Seller for performance of work by the Buyer or by others on behalf of the Buyer which is the responsibility of the Seller. Without limitation and by way of example only, backcharges may result from:

2 Docket 48-3 at 17, § 10(G). The Purchase Order also provides that “[l]iquidated damages . . . for seller’s failure to deliver equipment by the date or dates specified in this purchase order shall be assessed at the rate of $16,000 per day,” with a “total aggregate maximum Liquidated Damage liability” of 5 percent of the Purchase Order price. Docket 48-3 at 11–12, §§ 4(C) & (D). 3 Docket 48-3 at 6. i. Work performed by Buyer or by others on behalf of Buyer, to correct Seller’s non-compliance with the Purchase Order, acts of omission, or negligence. ii. Work performed by Buyer or by others on behalf of the Buyer, to correct warranty issues that have been properly tendered to the Seller in a timely manner but have not been cured. iii. The backcharge procedure shall be as stipulated in the Purchase Order attachments to. [sic]4 The Backcharge Procedure attached to the Purchase Order provides that TAKRAF “reserves the right to self-correct” any reported problems with the System, and that if it self-corrects a problem, TAKRAF would only be responsible for its own costs.5 The Backcharge Procedure further specifies that if TAKRAF requested the buyer to correct a problem with the System instead of self-correcting it, TAKRAF would reimburse the buyer for “direct material and labor costs involved with the re-work plus a Ten Percent 10% fee for administration, overhead and profit,” but that “[i]n no case” will TAKRAF be liable for “overtime rates, [or] special, indirect, or consequential damage costs, including the loss of construction efficiency or construction productivity.”6 The Backcharge Procedure also provides that the parties would settle all backcharges within 30 days of their presentation and that “[u]nresolved backcharges will be escalated per the dispute resolution clause in the Purchase Order.”7

4 Docket 48-3 at 13. 5 Docket 48-4 at 3, ¶ 5. 6 Docket 48-4 at 3, ¶ 6. 7 Docket 48-4 at 3, ¶¶ 11, 13. This is apparently a reference to Section 7 of the Purchase The Material Handling System was delivered in late 2016. After installing and testing the System, HDJV concluded that it did not meet project specifications.

HDJV concluded that, “[a]mong other things, the Material Handling System was unable to meet minimum throughput requirements, had undersized and failing parts, and allowed excessive and dangerous amounts of coal dust and coal to spill and/or escape the system.”8 HDJV notified TAKRAF of these problems in October 2018, and it delivered TAKRAF a formal notice of breach in June 2019.9

In April 2020, HDJV delivered TAKRAF a backcharge notice advising it of the extra costs it had incurred up to that date.10 HDJV also provided notice of TAKRAF’s alleged breach to Defendant North American Specialty Insurance Company (“NASIC”), which had provided the bond for TAKRAF’s performance.11 On September 22, 2020, HDJV filed the present suit against TAKRAF and NASIC under this Court’s diversity jurisdiction. HDJV’s complaint alleged breach

of contract and breach of the implied covenant of good faith and fair dealing (Claim 1), breach of express warranty (Claim 2), breach of UCC warranty

Order’s General Conditions. See Docket 48-3 at 13–14. However, the contract appears to have no escalation clause. 8 Docket 1 at 5, ¶ 13. 9 Docket 1 at 5, ¶ 14. 10 HDJV’s Complaint alleges that it submitted a backcharge to TAKRAF and that TAKRAF refused to accept it. Docket 1 at 5, ¶¶ 15–16. TAKRAF admits that HDJV submitted the backcharge, but it denies any related refusal or breach of contract. Docket 6 at 7–8. TAKRAF has provided a copy of the backcharge notice in question. See Docket 38-7 at 4–9. 11 Docket 6 at 7–8, ¶¶ 14–15. (Claim 3), and a claim against the performance bond (Claim 4).12 The parties later stipulated to dismissal of the breach of warranty claims (Claims 2 and 3) with prejudice.13 On the remaining two claims, Claims 1 and 4, HDJV seeks

compensatory damages for TAKRAF’s alleged breach of contract, an order declaring the judgment recoverable against NASIC’s bond, and an award of its fees and costs.14 LEGAL STANDARD

Under Rule 56 of the Federal Rules of Civil Procedure, a court “shall grant summary judgment if the movant shows that there is no genuine dispute as to any material fact and the movant is entitled to judgment as a matter of law.”15 DISCUSSION TAKRAF moves for partial summary judgment on the ground that the Purchase Order’s exclusion of consequential damages bars “every category of

damages” HDJV’s complaint seeks.16 TAKRAF asserts generally that “[a]ll of the damages sought by HDJV in this lawsuit are outside of what they contracted with TAKRAF to obtain in the Purchase Order. Thus, they are consequential, and not direct, damages.”17 TAKRAF reasons that “[a]ll the claimed consequential

12 Docket 1 at 7–10, ¶¶ 22–45. 13 Docket 39. 14 Docket 1 at 11–12. 15 Fed. R. Civ. P. 56(a). 16 Docket 36 at 14. 17 Docket 36 at 10–11. damages arose after TAKRAF performed under the Purchase Order and involve aspects of the System that are outside the scope of the Purchase Order,” because

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Clevo Co. v. Hecny Transportation, Inc.
715 F.3d 1189 (Ninth Circuit, 2013)
Peterson v. Wirum
625 P.2d 866 (Alaska Supreme Court, 1981)
Little Susitna Construction Co. v. Soil Processing, Inc.
944 P.2d 20 (Alaska Supreme Court, 1997)
Bendix Home Systems, Inc. v. Jessop
644 P.2d 843 (Alaska Supreme Court, 1982)
Stepanov v. Homer Elec. Ass'n, Inc.
814 P.2d 731 (Alaska Supreme Court, 1991)
National Bank of Alaska v. J. B. L. & K. of Alaska, Inc.
546 P.2d 579 (Alaska Supreme Court, 1976)
Dowling Supply & Equipment, Inc. v. City of Anchorage
490 P.2d 907 (Alaska Supreme Court, 1971)
Guard v. P & R ENTERPRISES, INC.
631 P.2d 1068 (Alaska Supreme Court, 1981)
Moore Construction Co. v. Clarksville Department of Electricity
707 S.W.2d 1 (Court of Appeals of Tennessee, 1986)
Gasperini v. Center for Humanities, Inc.
518 U.S. 415 (Supreme Court, 1996)
Norville v. Carr-Gottstein Foods Co.
84 P.3d 996 (Alaska Supreme Court, 2004)
Graham v. Municipality of Anchorage
446 P.3d 349 (Alaska Supreme Court, 2019)
Freund v. Nycomed Amersham
347 F.3d 752 (Ninth Circuit, 2003)

Cite This Page — Counsel Stack

Bluebook (online)
Haskell/Davis Joint Venture v. TAKRAF USA, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/haskelldavis-joint-venture-v-takraf-usa-inc-akd-2022.