American Electric Power Co. v. Westinghouse Electric Corp.

418 F. Supp. 435, 23 Fed. R. Serv. 2d 758, 19 U.C.C. Rep. Serv. (West) 1009, 1976 U.S. Dist. LEXIS 14056
CourtDistrict Court, S.D. New York
DecidedJuly 19, 1976
Docket74 Civ. 1521
StatusPublished
Cited by119 cases

This text of 418 F. Supp. 435 (American Electric Power Co. v. Westinghouse Electric Corp.) is published on Counsel Stack Legal Research, covering District Court, S.D. New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
American Electric Power Co. v. Westinghouse Electric Corp., 418 F. Supp. 435, 23 Fed. R. Serv. 2d 758, 19 U.C.C. Rep. Serv. (West) 1009, 1976 U.S. Dist. LEXIS 14056 (S.D.N.Y. 1976).

Opinion

OPINION

ROBERT L. CARTER, District Judge.

Defendant Westinghouse Electric Corporation (“Westinghouse”) has moved, pursuant to Rule 56, F.R.Civ.P., for summary judgment dismissing plaintiffs’ claims in their entirety and awarding Westinghouse judgment on Count I of its counterclaim. In the alternative, Westinghouse has moved for partial summary judgment dismissing plaintiffs’ claims for consequential damages. Plaintiffs have moved, pursuant to Rule 15(a), F.R.Civ.P., for leave to amend their complaint and their reply to defendant’s counterclaim.

I

Facts

Beginning in September, 1965, plaintiff American Electric Power Company, Inc. (“AEP”) 1 and defendant Westinghouse commenced negotiations on the design, manufacture and construction of a new turbine generator which came to be known as Mitchell Unit I. AEP made an oral commitment to purchase that turbine generator on December 28, 1965. Subsequent negotiations over a period of more than two years culminated in the execution of a fully integrated written contract signed by plaintiff Appalachian Power Co. on April 26, 1968, and by Westinghouse on May 9, 1968.

The Mitchell Unit I Contract provides that Westinghouse will manufacture and deliver a steam turbine generator guaran *440 teed to produce 760,582 kilowatts of electrical energy under certain specified steam conditions. 2

By the express terms of the contract’s “Guarantee” provision, the parties excluded implied warranties and agreed that Westinghouse’s entire obligation for defects in Mitchell Unit I would be fulfilled by the repair or replacement of defective parts for one year after initial synchronization 3 with corrected parts thereafter carrying a new one-year warranty. In addition, the parties also agreed in a separate “Limitation of Liability” provision that Westinghouse would not be held liable for consequential damages. Furthermore, the Limitation of Liability clause limited the liability of Westinghouse with respect to the contract or anything done in connection therewith to the price of the equipment or part on which such liability is based.

Because of their importance to the disposition of the instant motions, these two provisions will be set out in full:

“GUARANTEE
“The turbine-generator as manufactured will be warranted against defects in materials and workmanship for a period of one year after date of initial synchronization in accordance with the following statement of warranty:
“The Seller warrants that the equipment to be delivered will be of the kind and quality described in this contract and will be free of defects in workmanship and material. Should any failure to conform to this warranty appear within one year after the initial date of synchronization, the Seller shall, upon notification thereof and substantiation that the equipment has been stored, installed, maintained and operated in accordance with the company’s recommendations and standard industry practice, correct such defects including non-conformance with the specification, by suitable repair or replacement at its own expense.
“Any component requiring repair or replacement should hereafter carry a one year warranty starting from the date the unit is again returned to service after such correction.
“This warranty is exclusive and is in lieu of any warranty of merchantability, fitness for purpose or other warranty of quality, whether express or implied, except of title and against patent infringement.
“Correction of non-conformities, in the manner and for the period of time provided above, shall constitute fulfillment of all liabilities of the Company to the purchaser, whether based on contract, negligence or otherwise with respect to, or arising out of such equipment.”
“LIMITATION OF LIABILITY
“Except as otherwise agreed herein, the Seller shall not be liable for special, *441 or consequential damages, such as, but not limited to, damage or loss of other property or equipment, loss of profits or revenue, loss of use of power system, cost of capital, cost of purchased or replacement power, or claims of customers of purchaser for service interruptions. The remedies of the purchaser set forth herein are exclusive, and the liability of Seller with respect to any contract, or anything done in connection therewith such as the performance or breach thereof, or from the manufacture, sale, delivery, resale, installation or technical direction of installation, repair or use of any equipment covered by or furnished under this contract whether in contract, in tort, under any warranty, or otherwise, shall not, except as expressly provided herein, exceed the price of the equipment of [or] part on which such liability is based.”

The final contract price of the Mitchell Unit I turbine-generator was $12,260,580.08. To date, the purchaser has made payments totalling $10,868,656.00. The balance due— $1,391,924.08 — is sought by Westinghouse in Count I of its counterclaim.

II

Operational History of the Generator

On April 22, 1970, Mitchell Unit I was hooked up, or “initially synchronized” with the AEP system. The first major failure of the generator occurred in July, 1971, when Mitchell Unit I suffered a line-to-ground fault (similar to a short circuit). 4 It is alleged that inspection following this failure revealed cracked copper strands and insulation material which had become soaked by water leaks. A rewinding of the generator was required, during the course of which the Unit was out of service for almost five months. The rewind work was completed in November, 1971, and the Unit returned to service.

On March 1, 1972, the generator suffered a three-phase short circuit at the turbine end which burned out all three phases and necessitated a complete rewinding which required almost five months to complete. It is alleged that an inspection of the generator after this fault revealed dusting at the exciter end of the generator end winding, dusting indicating loose strain blocks, and dusting between the coils and diamond spacer blocks. All these problems, it is claimed, are evidence of loose bracing.

Since completion of the second generator rewind in July, 1972, Westinghouse has recommended full load operation (i. e., at the 760 mw level or higher), 5 but AEP has limited the Unit’s load to 690 mw, or 90 percent of the guaranteed contract capacity. The reason given by plaintiffs for this limitation is that the generator is unable to absorb continuously the high vibration developed in the generator when the Unit is operated at or near the warranted capacity. See Tillinghast Tr., p. 1055. Thus, John E. Dolan, the AEP Vice President who determined Mitchell Unit I’s present load limit of 690 mw, related that:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

KSW Mechanical Services v. Johnson Controls, Inc.
992 F. Supp. 2d 135 (E.D. New York, 2014)
Fluor Intercontinental, Inc. v. IAP Worldwide Services, Inc.
533 F. App'x 912 (Eleventh Circuit, 2013)
JAZME, LLC v. Wendt Corp.
809 F. Supp. 2d 957 (D. Minnesota, 2011)
Baney Corp. v. AGILYSYS NV, LLC
773 F. Supp. 2d 593 (D. Maryland, 2011)
In Re Cbgb Holdings, LLC
439 B.R. 551 (S.D. New York, 2010)
Airfreight Express Ltd. v. Evergreen Air Center, Inc.
158 P.3d 232 (Court of Appeals of Arizona, 2007)
In Re Access Cardiosystems, Inc.
361 B.R. 626 (D. Massachusetts, 2007)
Mercury Marine v. CLEAR RIVER CONST. CO.
839 So. 2d 508 (Mississippi Supreme Court, 2003)
Pierce v. Catalina Yachts, Inc.
2 P.3d 618 (Alaska Supreme Court, 2000)
Eastman Chemical Co. v. Niro, Inc.
80 F. Supp. 2d 712 (S.D. Texas, 2000)
United States Ex Rel. Roby v. Boeing Co.
79 F. Supp. 2d 877 (S.D. Ohio, 1999)
Rheem Manufacturing Co. v. Phelps Heating & Air Conditioning, Inc.
714 N.E.2d 1218 (Indiana Court of Appeals, 1999)
International Financial Services, Inc. v. Franz
534 N.W.2d 261 (Supreme Court of Minnesota, 1995)
International Financial Services, Inc. v. Franz
515 N.W.2d 379 (Court of Appeals of Minnesota, 1994)
TBG, INC. v. Bendis
841 F. Supp. 1538 (D. Kansas, 1993)

Cite This Page — Counsel Stack

Bluebook (online)
418 F. Supp. 435, 23 Fed. R. Serv. 2d 758, 19 U.C.C. Rep. Serv. (West) 1009, 1976 U.S. Dist. LEXIS 14056, Counsel Stack Legal Research, https://law.counselstack.com/opinion/american-electric-power-co-v-westinghouse-electric-corp-nysd-1976.