Andritz Hydro Canada, Inc. v. Rochester Gas & Electric Corporation

CourtDistrict Court, W.D. New York
DecidedJuly 22, 2021
Docket6:20-cv-06772
StatusUnknown

This text of Andritz Hydro Canada, Inc. v. Rochester Gas & Electric Corporation (Andritz Hydro Canada, Inc. v. Rochester Gas & Electric Corporation) is published on Counsel Stack Legal Research, covering District Court, W.D. New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Andritz Hydro Canada, Inc. v. Rochester Gas & Electric Corporation, (W.D.N.Y. 2021).

Opinion

UNITED STATES DISTRICT COURT WESTERN DISTRICT OF NEW YORK

Andritz Hydro Canada, Inc., the successor to VA Tech Hydro Canada, Inc.,

Plaintiff, Case # 20-CV-6772-FPG v. DECISION AND ORDER Rochester Gas & Electric Corporation,

Defendant.

INTRODUCTION On September 29, 2020, Plaintiff Andritz Hydro Canada, Inc. (“Andritz”) filed this action against Defendant Rochester Gas & Electric Corporation (“RG&E”) asserting claims for breach of contract, declaratory judgment, implied-in-fact contract, unjust enrichment, and promissory estoppel. ECF No. 1. On December 18, 2020, RG&E filed a motion to dismiss Andritz’s complaint pursuant to Federal Rule of Civil Procedure 12(b)(6). ECF No. 9. RG&E’s motion to dismiss Andritz’s complaint is GRANTED IN PART and DENIED IN PART. RELEVANT FACTS1 Andritz is a foreign corporation organized under the laws of New Brunswick, Canada with a principal place of business of Quebec, Canada. ECF No. 1 ¶ 2. RG&E is a New York corporation with a principal place of business in Rochester, New York. Id. ¶ 3. Andritz designs, manufactures, and supplies equipment and services to hydropower plants in Canada and the United States. Id. ¶ 8. RG&E provides utility service to nearly 700,000 electric and natural gas customers in Rochester, New York and the surrounding communities. Id. ¶ 9.

1 Except where noted, the Court takes the following allegations from Andritz’s complaint, ECF No. 1, and accepts them as true to evaluate RG&E’s motion to dismiss. In 2008, RG&E decided to upgrade and expand a hydroelectric power station it operates in Rochester by installing a new turbine generator. Id. ¶¶ 10–11. To that end, RG&E contracted with Andritz’s predecessor2 for the purchase of such a generator (the “Agreement”). Id. ¶ 12. The Agreement is dated February 5, 2008 and provides that:

[RG&E] may suspend or terminate this order in whole or in part for its own convenience by giving [Andritz] twenty-four (24) hours notice. In such event [RG&E] shall make payment to [Andritz] for all costs incurred prior to such termination reasonably allocable to this order, under recognized accounting practice, together with a reasonable allowance for overhead and profit on work performed, plus all costs reasonably incurred by [Andritz] as a result of the termination (such as cancellation fees of suppliers or wrap-up costs), less disposal or retention value of termination inventory. This provision shall not be deemed to limit or otherwise affect [RG&E]’s right to terminate this Agreement for breach or default by [Andritz]. Id. ¶¶ 12, 18; ECF No. 1-1 § 18. The Agreement provides that payment will be made in United States Dollars. ECF No. 1 ¶ 14. In connection with the Agreement, Andritz purchased foreign currency heading contracts to reduce or eliminate its risk that fluctuations in the value of the United States Dollar relative to the Canadian Dollar would reduce the value of the Agreement. Id. ¶¶ 15, 16. Andritz alleges that it is standard practice in international contracting to use foreign currency hedging contracts to protect against fluctuations in currency value. Id. ¶ 15. Later that year, in October 2008, RG&E provided written notice to Andritz that the project was suspended and directed Andrtiz “to stop incurring any additional cost for th[e] project.” Id. ¶ 19; ECF No. 1-2 at 2. RG&E requested that Andritz provide it with the costs Andritz had incurred from the beginning of the contract up to the suspension date, excluding costs associated with the

2 Andritz Group acquired VA Tech Hydro Canada, Inc. ECF No. ¶¶ 12, 20. After the acquisition, on December 31, 2008, VA Tech changed its name to Andritz. Id. Because it has no impact on the relevant analysis, the Court simply refers to both Andritz and VA Tech as “Andritz.” foreign currency hedging contracts. ECF No. 1 ¶ 22. Andritz ceased all activities related to the manufacture and supply of the generation unit. Id. ¶ 21. In February 2009, Andritz sent a letter to RG&E detailing the requested costs, which totaled $1,342,315, but explained that such costs did not include any costs associated with foreign currency hedging contracts and that such costs would

continue to accrue. Id. ¶¶ 24–25; ECF No. 1-3. Andritz explained that, if the project were to be canceled and it were to unwind the hedging contracts, “the current real cost to Andritz Hydro is approximately $450-500,000 USD.” ECF No. 1 ¶ 25; ECF No. 1-3 at 5. Andritz further clarified that that figure was “an approximate cost based on market rates of Feb. 5/09 and w[ould] fluctuate until the date actual instructions [we]re given to cancel the contracts.” ECF No. 1 ¶ 25; ECF No. 1-3 at 5. In March 2009, Andritz provided RG&E with supplemental information regarding the $1,342,315 in costs incurred by Andritz prior to October 24, 2008, but again Andritz specified that the total did not include costs associated with foreign currency hedging contracts. ECF No. 1 ¶ 26. In December 2009, RG&E paid Andritz the amount requested. Id. ¶ 27.

In December 2011, RG&E advised that it was unable to lift the suspension but planned to proceed with the project in 2014. Id. ¶ 28. On April 23, 2012, Andritz sent a letter to RG&E reminding it of the foreign currency hedging costs incurred during the suspension period “and proposed how the equipment costs and foreign currency hedging costs would be treated at the time the suspension was lifted.” Id. ¶ 29. In that letter, Andritz stated: “Should RG&E elect to have ANDRITZ HYDRO immediately cancel the hedging contracts, the current real cost to ANDRITZ HYDRO is approximately $30,000.” Id. ¶ 30. The project did not proceed in 2014 and remained in suspension. Id. ¶ 31. In February 2018, RG&E informed Andritz that the project would be moving ahead, and at Andritz’s request, RG&E provided a project schedule for the installation of the equipment for April 2023 through December 2025. Id. ¶¶ 32–33. In September 2019, however, RG&E notified Andritz that the suspension order would not likely be lifted. Id. ¶ 39. On November 4, 2019, Andritz sent a letter to RG&E requesting its “official position” on either terminating the Agreement or lifting the

suspension order. Id. ¶ 40. Andritz stated that “[i]n the event of silence or refusal on the part of [RG&E] to provide such official position within such prescribed time, Andritz w[ould] deem the Contract terminated pursuant to Section 18.” Id. ¶ 40; ECF No. 1-6 at 2. Having received no response despite efforts to contact RG&E, Andritz advised RG&E by letter dated March 20, 2020 that it considered the Agreement terminated by RG&E for convenience in accordance with Section 18. ECF No. 1 ¶ 41. Andritz requested $1,126,970.48 Canadian Dollars as final termination costs, which included “the costs incurred as a result of the Foreign Exchange fluctuations allocated to the” Agreement. Id. ¶ 42. In response, RG&E wrote a letter to Andritz dated April 16, 2020. Id. ¶ 43; ECF No. 1-8. In that letter, RG&E stated that it “never issued a termination notice under the . . . Agreement” and

that it understood that Andrtiz had “terminated the Agreement.” ECF No. 1-8 at 4. RG&E further denied that it owed Andritz payment for costs associated with the currency hedges under the Agreement or any other additional payments. ECF No. 1-8.3 Because of the project’s suspension, Andritz kept the project active and rolled-over its contractual obligations, including its foreign currency hedging contracts. ECF No. 1 ¶ 35. RG&E was aware Andritz was incurring costs associated with the hedging contracts and Andritz expected

3 Andritz alleges that, in its letter, RG&E “acknowledged to Andritz that it terminated the Agreement for convenience pursuant to Section 18.” ECF No. 1 ¶ 43.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Bell Atlantic Corp. v. Twombly
550 U.S. 544 (Supreme Court, 2007)
Ashcroft v. Iqbal
556 U.S. 662 (Supreme Court, 2009)
DiFolco v. MSNBC Cable L.L.C.
622 F.3d 104 (Second Circuit, 2010)
Lockheed Martin Corp. v. Retail Holdings, N.V.
639 F.3d 63 (Second Circuit, 2011)
Faber v. Metropolitan Life Insurance
648 F.3d 98 (Second Circuit, 2011)
Hellenic Lines Limited v. Gulf Oil Corporation
340 F.2d 398 (Second Circuit, 1965)
Amidax Trading Group v. S.W.I.F.T. Scrl
671 F.3d 140 (Second Circuit, 2011)
Westchester Resco Co. v. New England Reinsurance Corp.
648 F. Supp. 842 (S.D. New York, 1986)
Knudsen v. Quebecor Printing (U.S.A.) Inc.
792 F. Supp. 234 (S.D. New York, 1992)
Top of Iowa Cooperative v. Schewe
6 F. Supp. 2d 843 (N.D. Iowa, 1998)
American List Corp. v. U.S. News & World Report, Inc.
549 N.E.2d 1161 (New York Court of Appeals, 1989)
My Play City, Inc. v. Conduit Limited
589 F. App'x 559 (Second Circuit, 2014)

Cite This Page — Counsel Stack

Bluebook (online)
Andritz Hydro Canada, Inc. v. Rochester Gas & Electric Corporation, Counsel Stack Legal Research, https://law.counselstack.com/opinion/andritz-hydro-canada-inc-v-rochester-gas-electric-corporation-nywd-2021.