Stepanov v. Homer Elec. Ass'n, Inc.

814 P.2d 731, 1991 Alas. LEXIS 59, 1991 WL 118210
CourtAlaska Supreme Court
DecidedJuly 5, 1991
DocketS-3410, S-3496 and S-3497
StatusPublished
Cited by32 cases

This text of 814 P.2d 731 (Stepanov v. Homer Elec. Ass'n, Inc.) is published on Counsel Stack Legal Research, covering Alaska Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Stepanov v. Homer Elec. Ass'n, Inc., 814 P.2d 731, 1991 Alas. LEXIS 59, 1991 WL 118210 (Ala. 1991).

Opinion

OPINION

MOORE, Justice.

This case involves several claims arising from contracts between Homer Electric Association, Inc., and developers, George A. Stepanov and Laura Stepanov, and Gene Effler (Developers). 1 All parties appeal the superior court’s determination that the contracts were partially enforceable. In addition, the Developers contend that the superior court’s resolution violated their rights under the United States and the Alaska Constitutions. We affirm the rulings of the trial court as to both of these issues. The parties also challenge the superior court’s determinations regarding attorney’s fees. We affirm the trial court’s denial of attorney’s fees for administrative proceedings in this matter and reverse its award of actual fees to the Developers for the appellate proceedings.

I. FACTS AND PROCEEDINGS

Both of the Developers (Effler, and the Stepanovs) own real property which is within the service area of the Homer Electric Association, Inc. (HEA). The Developers began subdividing in the mid-1970’s. At that time, HEA’s policy for extension of electrical lines to newly developed lands provided that the cost of overhead line extensions was paid primarily by HEA. 2 The only time a property owner would incur *733 substantial costs in obtaining electrical service was if he or she wanted the lines installed underground. If an underground extension was requested, HEA still assumed the cost of basic (overhead) installation, but charged the customer for the additional expense of installing the lines underground.

The Developers wanted to assure that when individual purchasers arranged for electrical lines to be extended to their lots, the lines would be installed underground. To achieve this goal, they entered into agreements with HEA whereby the Developers would prepay the difference between HEA’s costs for installing lines underground and overhead. 3 The Developers subsequently represented to purchasers that underground electrical lines would be extended to their property for nominal fees. Because the subdivisions were developed in phases, the agreements provided that payment of the differential for underground service would coincide with each phase of development. 4 Over the next several years, as each phase of development occurred, Effler and the Stepanovs paid in full the cost differential for underground service to that portion of their development, and HEA extended lines to the lots without any significant cost to the lot owners.

However, in 1981, HEA petitioned the Alaska Public Utilities Commission (PUC) for permission to change its line extension policy. The proposed policy change would allow HEA to bill landowners for the cost of extending overhead electrical lines to their property rather than bearing that expense itself. On January 11, 1982, the PUC granted HEA’s petition. HEA subsequently revised its policy to include a tariff on overhead line extensions. 5 HEA did not notify the Developers that it was petitioning to change its rates for line extensions. They remained unaware of the new tariff until purchasers of lots in their subdivisions complained that HEA had assessed large fees for the extension of electrical lines to their property.

Effler and the Stepanovs each petitioned the PUC for review of HEA’s new line extension tariff. Their petitions were consolidated and a hearing was held in early 1986. The Developers alleged that their contracts with HEA bound HEA to the policies in effect at the time the contracts were entered. Since the policy at that time was that HEA would bear the cost of overhead line extensions, the Developers argued that their contracts exempted their respective subdivisions from application of the new tariff. They also argued that the contract clause of the United States and Alaska Constitutions precluded modification of the contracts via retroactive rate revision. HEA responded that application of the revised tariff to the Developers’ property did not affect the contracts. It interpreted the contractual payments to apply exclusively to the cost differential between overhead and underground extensions, and concluded that the contracts did not affect the charge that could be imposed for overhead service.

On August 21, 1986, a PUC hearing officer found that under the contracts, the Developers’ prepayment of the cost differential covered the entire cost of extensions within the subdivisions. He then concluded that the contracts were “special contracts” pursuant to title 3, section 48.820(36) of the Alaska Administrative Code (AAC). 6 He *734 further found that, although 3 AAC 48.390 provides that special contracts do not take effect without prior approval of the PUC, HEA could reasonably be expected to be aware of PUC regulations, whereas the Developers were “justifiably ignorant” of such requirements. Therefore, the hearing officer recommended that the PUC grant limited retroactive approval of the contracts until the time the Developers received notice that the revised tariff was applicable to their property. Based on his conclusion that the agreements were special contracts, he rejected the Developers’ argument that application of the tariff after the period of PUC approval was an unconstitutional abrogation of a valid contract.

Both parties objected to the hearing officer’s characterization of the agreements as special contracts. However, the PUC concluded that the contracts contained an implicit provision that the line extension rates in effect at the time the contracts were entered would control, even if HEA’s policies were modified before installation of service. Accordingly, it adopted the hearing officer’s recommendation and characterized the agreements as special contracts which it approved for the period prior to the dates on which the Developers received actual notice that the new tariff applied to their property. 7

All parties appealed to the superior court. On May 3, 1989, the court affirmed the PUC’s result on alternative grounds. 8 It rejected the Developers’ request for attorney’s fees for the administrative portion of their case, but awarded actual attorney’s fees and costs for their appeal pursuant to Alaska Rules of Appellate Procedure 508(d) and (e).

All parties again appeal.

II. CONTRACT INTERPRETATION

The proper interpretation of the contracts is the central issue in this dispute. We begin by analyzing the terms and conditions of the agreements to assess whether the PUC correctly determined that they are “special contracts.” 9 When interpreting contracts, the goal is to “give effect to the reasonable expectations of the parties.” Mitford v. de Lasala, 666 P.2d 1000, 1005 (Alaska 1983).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Graham v. Municipality of Anchorage
446 P.3d 349 (Alaska Supreme Court, 2019)
Lingley v. Alaska Airlines, Inc.
373 P.3d 506 (Alaska Supreme Court, 2016)
Bernard v. Alaska Airlines, Inc.
367 P.3d 1156 (Alaska Supreme Court, 2016)
Miller v. Handle Construction Co.
255 P.3d 984 (Alaska Supreme Court, 2011)
Hageland Aviation Services, Inc. v. Harms
210 P.3d 444 (Alaska Supreme Court, 2009)
Sowinski v. Walker
198 P.3d 1134 (Alaska Supreme Court, 2008)
Monzingo v. Alaska Air Group, Inc.
112 P.3d 655 (Alaska Supreme Court, 2005)
Matanuska Electric Ass'n v. Chugach Electric Ass'n
99 P.3d 553 (Alaska Supreme Court, 2004)
Exxon Corp. v. State
40 P.3d 786 (Alaska Supreme Court, 2001)
Aloha Lumber Corp. v. University of Alaska
994 P.2d 991 (Alaska Supreme Court, 1999)
Larsen v. Municipality of Anchorage
993 P.2d 428 (Alaska Supreme Court, 1999)
Alaska Housing Finance Corp. v. Salvucci
950 P.2d 1106 (Alaska Supreme Court, 1997)
Kilmer v. Dillingham City School District
932 P.2d 757 (Alaska Supreme Court, 1997)

Cite This Page — Counsel Stack

Bluebook (online)
814 P.2d 731, 1991 Alas. LEXIS 59, 1991 WL 118210, Counsel Stack Legal Research, https://law.counselstack.com/opinion/stepanov-v-homer-elec-assn-inc-alaska-1991.