State of Alaska, Department of Transportation and Public Facilities v. Osborne Construction Company

462 P.3d 991
CourtAlaska Supreme Court
DecidedMay 1, 2020
DocketS17048
StatusPublished

This text of 462 P.3d 991 (State of Alaska, Department of Transportation and Public Facilities v. Osborne Construction Company) is published on Counsel Stack Legal Research, covering Alaska Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
State of Alaska, Department of Transportation and Public Facilities v. Osborne Construction Company, 462 P.3d 991 (Ala. 2020).

Opinion

Notice: This opinion is subject to correction before publication in the PACIFIC REPORTER. Readers are requested to bring errors to the attention of the Clerk of the Appellate Courts, 303 K Street, Anchorage, Alaska 99501, phone (907) 264-0608, fax (907) 264-0878, email corrections@akcourts.us.

THE SUPREME COURT OF THE STATE OF ALASKA

STATE OF ALASKA, DEPARTMENT ) OF TRANSPORTATION AND ) Supreme Court No. S-17048 PUBLIC FACILITIES, ) ) Superior Court No. 3AN-17-04261 CI Petitioner, ) ) OPINION v. ) ) No. 7447 – May 1, 2020 OSBORNE CONSTRUCTION ) COMPANY, ) ) Respondent. ) )

Petition for Review from the Superior Court of the State of Alaska, Third Judicial District, Anchorage, Erin B. Marston, Judge.

Appearances: Jeffrey P. Stark, Chief Assistant Attorney General, Anchorage, and Kevin G. Clarkson, Attorney General, Juneau, for Petitioner. Michael E. Kreger and Sarah C. Gillstrom, Perkins Coie, LLP, Anchorage, for Respondent.

Before: Winfree, Stowers, Maassen, and Carney, Justices. [Bolger, Chief Justice, not participating.]

CARNEY, Justice.

I. INTRODUCTION A state agency appeals a superior court decision reversing the agency’s decision in an administrative appeal. The agency denied a contractor’s claim for additional compensation because the claim was filed outside the filing period allowed by the contract. After applying our independent judgment to interpret the contract, we agree with the agency that the contractor failed to file its claim within the period allowed. We therefore reverse the superior court’s decision and reinstate the agency’s. II. FACTS AND PROCEEDINGS A. Facts In August 2013 the Alaska Department of Transportation and Public Facilities (DOT) entered into a contract with Osborne Construction Company to upgrade the Aircraft Rescue and Fire Fighting building at the Fairbanks International Airport to withstand damage in the event of an earthquake. The contract listed a series of upgrades to be completed. In addition to renovations to the building, the contract required “soil structure improvements” to the building site. The purpose of the soil structure improvements was to alleviate the risk of liquefaction.1 This was to be accomplished by compaction grouting, a process in which grout is injected into the ground at regularly spaced intervals to increase soil density.2 The contract provided specifications for the material to be used in the grouting process; Osborne was responsible for obtaining conforming materials.

1 Soil liquefaction is a phenomenon in which the strength of a soil is reduced by strong ground shaking. This reduces the ability of the soil to support foundations for buildings. U.S. G E O LO GICAL S URVEY , What is liquefaction?, https://www.usgs.gov/faqs/what-liquefaction? (last visited Mar. 11, 2020). 2 The grout was required to be a combination of cement, “fine aggregate,” and water. The aggregate had to be a particular type of sand: “naturally occurring, clean, round to subrounded, hard, water-worn siliceous material, free of flat or elongated pieces, . . . or . . .foreign matter, and graded within the limits” set by the contract.

-2- 7447 The contract also established procedures for changes to the contract (Article 9), resolution of disagreements (Article 15), and requests for additional compensation or time (Article 15). Article 15 set out a series of deadlines by which the contractor had to notify DOT of any claim for additional compensation. Osborne hired AVAR3 in October 2013 as a subcontractor to perform the compaction grouting work; DOT accepted AVAR as a subcontractor in November 2013. AVAR then prepared and submitted a compaction grouting proposal to Osborne in December; Osborne forwarded it to DOT in January 2014. In March Osborne submitted a revised plan to DOT, identifying 437 grout injection points, the material and equipment to be used, and the installer’s qualifications. DOT accepted the proposal in late March. AVAR began the grouting work on June 30, 2014, but encountered difficulties. The sand AVAR intended to use was no longer available from the local supplier identified in its bid, and AVAR proposed an alternative source of sand to Osborne. Osborne provided an analysis of the sand to DOT’s engineers, Shannon & Wilson, and requested they approve its use. Shannon & Wilson recommended rejecting the sand as non-compliant with the contract terms. AVAR then located another alternative from an Anchorage-based source; Shannon & Wilson again recommended its rejection. AVAR located and began to import sand from a new source in California in late July. But even after obtaining better quality sand, AVAR was delayed again by equipment issues. AVAR was finally able to begin compaction grouting with the imported sand in mid-August.

3 In its proposal to Osborne, AVAR identified itself as “GMI, A Division of AVAR.” This entity is referred to as GMI throughout the record, but because the parties use “AVAR” in their briefs, we do as well. -3- 7447 By September 7, 2014, AVAR had successfully completed 154 injection points in the exterior area surrounding the building. Grouting within the building’s interior began the next day. AVAR immediately encountered issues with grouting inside the building, and hired a consulting firm, Langan Treadwell Rollo (Langan), to study the soil underneath the building and determine the source of the problem. Langan prepared a report for AVAR and made several recommendations to alleviate the difficulty while still achieving the desired level of soil improvement. The Langan report attributed the difficulty of injection to nearby grouting injection points outside the building, which made the soil beneath the building more dense. AVAR provided the Langan report to Osborne on September 24. The next day Osborne petitioned DOT for a modification of the grouting plans, attaching a copy of the Langan report. On October 9 DOT tentatively approved Osborne’s request to increase the spacing between injection points, but withheld final approval until after Shannon & Wilson was able to observe and confirm that the modification was acceptable. DOT ultimately approved Osborne’s request to increase the spacing between injection points but did not permit any other changes. AVAR completed the injection grouting work the next day, on October 10. On October 13 Osborne transmitted to DOT a letter from AVAR, dated October 3 and addressed to Osborne, which was entitled “NOTICE OF CHANGE IN GROUND CONDITIONS.” In the letter AVAR stated that it had incurred increased costs due to soil conditions inside the building that were “dramatically different” than conditions outside the building. The letter also promised to provide Osborne with an analysis of the additional costs and the results of bore studies analyzing the soil conditions. On February 2, 2015, AVAR sent a letter with a claim for additional compensation to Osborne. The letter was addressed to both Osborne and DOT’s Anchorage office. In the letter AVAR stated two bases for its claim for increased

-4- 7447 compensation: (1) differing site conditions and (2) a lack of locally available sand that met the contractual specifications. On May 11, 2016, Osborne submitted a claim to DOT seeking additional compensation for the compaction grouting work, incorporating AVAR’s February 2015 letter to Osborne. DOT notified Osborne on July 13 that its claim was not valid because it did not comply with certification requirements.4 DOT requested that Osborne remedy the certification issue and re-submit the claim, which Osborne did on September 20. B. Proceedings The DOT contracting officer issued a written decision on October 28, 2016, denying Osborne’s May 11, 2016 claim for additional compensation. The contracting officer first explained that the claim did not comply with Article 15 of the contract.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Tesoro Alaska Petroleum Co. v. Kenai Pipe Line Co.
746 P.2d 896 (Alaska Supreme Court, 1987)
Stepanov v. Homer Elec. Ass'n, Inc.
814 P.2d 731 (Alaska Supreme Court, 1991)
O'CONNELL v. Will
263 P.3d 41 (Alaska Supreme Court, 2011)
Marathon Oil Co. v. State, Department of Natural Resources
254 P.3d 1078 (Alaska Supreme Court, 2011)
Rockstad v. Global Finance & Investment Co.
41 P.3d 583 (Alaska Supreme Court, 2002)
Norville v. Carr-Gottstein Foods Co.
84 P.3d 996 (Alaska Supreme Court, 2004)
SMJ Gen. Constr., Inc. v. Jet Commercial Constr., LLC
440 P.3d 210 (Alaska Supreme Court, 2019)
Graham v. Municipality of Anchorage
446 P.3d 349 (Alaska Supreme Court, 2019)

Cite This Page — Counsel Stack

Bluebook (online)
462 P.3d 991, Counsel Stack Legal Research, https://law.counselstack.com/opinion/state-of-alaska-department-of-transportation-and-public-facilities-v-alaska-2020.