Millgard Corporation v. McKee a Joint Venture, Dallas County and the Commissioners Court of Dallas County, Texas, Defendants

831 F.2d 88
CourtCourt of Appeals for the Fifth Circuit
DecidedDecember 2, 1987
Docket87-1140
StatusPublished
Cited by4 cases

This text of 831 F.2d 88 (Millgard Corporation v. McKee a Joint Venture, Dallas County and the Commissioners Court of Dallas County, Texas, Defendants) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fifth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Millgard Corporation v. McKee a Joint Venture, Dallas County and the Commissioners Court of Dallas County, Texas, Defendants, 831 F.2d 88 (5th Cir. 1987).

Opinion

EDITH H. JONES, Circuit Judge:

. Millgard Corporation (“Millgard”) appeals from the dismissal of its complaints against McKee/Mays, a Joint Venture (“McKee/Mays”) and Dallas County. We reverse.

Dallas County contracted with McKee/Mays for the construction of the Lew Sterrett Justice Center in 1978, and McKee/Mays subsequently awarded Millgard the caisson foundations subcontract for the project. However, in June 1979, shortly after beginning work on the project, Millgard encountered subsurface conditions different from those previously reported by the project’s geotechnical engineers. According to Millgard, these unstable soil conditions necessitated approximately fifty percent more concrete in the foundation piers than originally anticipated, as well as the use of more expensive equipment and techniques. As per the subcontract, 1 Millgard continued work on the project and informed McKee/Mays of the situation on July 5, 1979, subsequently giving formal written notice that it was encountering an unexpected condition and was incurring increased costs.

On September 12, 1979, Millgard provided a detailed enumeration of the unexpected soil conditions on the project and an itemization of the estimated additional costs. McKee/Mays responded that Millgard’s information was inadequate and requested additional documentation. Millgard accordingly submitted a revised request for additional compensation in November 1979.

In January 1980, Millgard completed its work under the subcontract, and in May 1980 the company formally requested addi *90 tional compensation of $711,264, 25% above the original contract price. After consultation with the architects and geotechnical experts, McKee/Mays opined that there were no unexpected subsurface conditions, and on June 12, 1980, it rejected Millgard’s request for additional compensation.

Negotiations ensued. In March 1983, however, Millgard filed a demand for arbitration with the American Arbitration Association against Dallas County. The County countered with a state action to enjoin the arbitration, alleging lack of contractual privity between Millgard and Dallas County. Millgard, retaliating, petitioned to compel arbitration. In January 1984, the state district court sided with the County and entered a permanent injunction prohibiting Millgard from proceeding with arbitration.

Millgard instituted this diversity action on June 7, 1984 against McKee/Mays, which promptly impleaded Dallas County. In 1985, Millgard filed an amended complaint adding fraud and negligence claims against Dallas County, based on documents obtained in discovery that purportedly indicate that Dallas County knew of the unstable soil conditions in advance and did not disclose them to Millgard.

The district court granted the defendants’ motions for summary judgment, holding that Millgard’s cause of action against McKee/Mays accrued on the date Millgard made final demand under the subcontract (May 2, 1980), and was therefore barred by the four year state statute of limitations. It also is held that Millgard’s tort claims against Dallas County accrued in 1979 and thus proscribed under state law in 1981. Millgard now appeals.

I. MILLGARD’S CONTRACT CLAIMS AGAINST MCKEE/MAYS

Citing Godde v. Wood, 509 S.W.2d 435, 441-43 (Tex.Civ.App. — Corpus Christi 1974, writ ref’d n.r.e.), the district court held that Millgard’s cause of action accrued no later than May 2, 1980, when Millgard made written demand for the additional amount. Consequently, the court concluded that because the instant action was filed June 7, 1984, it was barred by Texas’ four year statute of limitations for contract claims, Tex.Rev.Civ.Stat. Art. 5527(1) (now codified as Tex.Civ.Prac. & Rem.Code § 16.004(a)(3) (Vernon's 1986)). Millgard asserts that its cause of action accrued no sooner than June 12, 1980, when McKee/Mays rejected its request for additional compensation, or June 16, 1980, when Millgard learned of the rejection.

It is not disputed that under Texas law, a contract cause of action accrues upon breach. Jackson v. J.R. Neatherlin Corp., 557 S.W.2d 327, 329 (Tex.Civ.App. — Houston 1977, writ ref’d n.r.e.); Hurbrough v. Cain, 571 S.W.2d 216, 221 (Tex.Civ.App.— Tyler 1978, no writ). The issue before us is at what point breach occurred. Millgard contends that breach occurred when McKee/Mays repudiated the contract by refusing its request for equitable adjustment in compensation due to unexpected subsurface conditions. Defendants argue that because the contract is silent as to the payment date for the equitable adjustment, payment was due when Millgard completed its performance under the contract (January 1980). Contending that Millgard could have filed suit for nonpayment at any time thereafter, defendants assert that breach must date from that time.

We find defendants’ arguments unpersuasive. The general rule that a right to recover under a contract accrues at the time performance is completed, unless otherwise specified in the contract, has been invoked in the context of setting the earliest time when suit could be brought for payment under a construction contract, see Jim Walter Homes, Inc. v. Valencia, 679 S.W.2d 29 (Tex.App. — Corpus Christi 1984, modified on other grounds 690 S.W.2d 239); Wade & Sons, Inc. v. Waco Construction, Inc., 612 S.W.2d 261 (Tex.Civ.App. — San Antonio 1981, no writ), or for defining the payment date for interest calculation purposes, Irrigation Construction Co. v. Motheral Contractors, Inc., 599 S.W.2d 336 (Tex.Civ.App. — Corpus Christi 1980, no writ); McDaniel v. Tucker, 520 S.W.2d 543, (Tex.Civ.App. — Corpus Christi 1975, no writ); Beck v. Lawler, 422 S.W.2d 816 *91 (Tex.Civ.App. — Fort Worth 1967, writ ref’d n.r.e.). It has not been unambiguously invoked in a limitations context. 2 Moreover, as will be seen, the existence of provisions “otherwise specified in the contract” renders this case different from the general accrual rule.

We agree with Millgard that in this case, the proper test is based upon the parties’ contract and derives from McKee’s repudiation of Millgard’s proposed Change Order. See Terry County Airport Board v. Clark, 378 S.W.2d 932, 934 (Tex.Civ.App.— Amarillo 1964, no writ); Permian Building, Inc. v. Greenblatt,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
831 F.2d 88, Counsel Stack Legal Research, https://law.counselstack.com/opinion/millgard-corporation-v-mckee-a-joint-venture-dallas-county-and-the-ca5-1987.