Furniture Enterprises of Alaska, Inc. v. Jo-Ann Stores, LLC

CourtDistrict Court, D. Alaska
DecidedAugust 30, 2022
Docket3:20-cv-00272
StatusUnknown

This text of Furniture Enterprises of Alaska, Inc. v. Jo-Ann Stores, LLC (Furniture Enterprises of Alaska, Inc. v. Jo-Ann Stores, LLC) is published on Counsel Stack Legal Research, covering District Court, D. Alaska primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Furniture Enterprises of Alaska, Inc. v. Jo-Ann Stores, LLC, (D. Alaska 2022).

Opinion

IN THE UNITED STATES DISTRICT COURT

FOR THE DISTRICT OF ALASKA

FURNITURE ENTERPRISES OF ALASKA, INC., Case No. 3:20-cv-00272-JMK Plaintiff,

vs. ORDER GRANTING PARTIAL SUMMARY JUDGMENT JO-ANN STORES, LLC,

Defendant.

Before the Court is Defendant and Counterclaimant Jo-Ann Stores, LLC’s (“Jo-Ann”) Motion for Partial Summary Judgment1 and Plaintiff and Counter Defendant Furniture Enterprises of Alaska, Inc.’s (“FEA”) Cross Motion for Partial Summary Judgment.2 Both motions are fully briefed.3 Oral argument was not requested and is unnecessary to the Court’s decision. For the reasons below, Jo-Ann’s Motion for Partial Summary Judgment is GRANTED and FEA’s Cross Motion for Partial Summary Judgment is DENIED. Under

1 Docket 22. 2 Docket 26. 3 See Docket 25; Docket 27; Docket 30; Docket 31; Docket 32. FEA filed its “Memorandum in Opposition to Jo-Ann’s Motion for Partial Summary Judgment and in Support of Cross-Motion for Partial Summary Judgment” at both Docket 25 and Docket 27. Federal Rule of Civil Procedure 56(f)(1), the Court also GRANTS summary judgment in favor of nonmovant Jo-Ann with respect to FEA’s second claim for breach of lease.

I. FACTUAL BACKGROUND This litigation stems from a dispute under the parties’ commercial lease (the “Lease”); specifically, the parties disagree on which party was required to upgrade the property’s sprinkler system for retail use. Landlord FEA owns a portion of the University Center Mall in Anchorage, Alaska.4 In January 2019, FEA and prospective tenant Jo-Ann

executed a non-binding letter of intent (the “Offer Letter”) outlining an agreement that Jo- Ann would lease Suite A-1 of the mall (the “Premises”) to operate its signature crafts and fabric store.5 The parties continued to negotiate over several months, ultimately signing the Lease on August 8, 2019.6 The Premises needed significant renovation to function as a Jo-Ann’s Fabrics store.7 An attachment to the Lease entitled the “Shell Project Matrix” (the “Matrix”)

outlined each party’s construction obligations in anticipation of the store’s opening.8 Ultimately, FEA was to deliver a “code-compliant shell building” to Jo-Ann by November 4, 2019.9 Jo-Ann would then complete the store’s internal improvements before

4 Docket 1-1 at 4. 5 Docket 22-14. 6 Docket 22-43; Docket 22 at 7. 7 The Premises was used as a Natural Pantry grocery store until approximately 2010, after which it was a storage space for FEA’s owner, David Cavitt. See Docket 22-4 at 19:2–22; Docket 22-5 at 39:22–40:1, 43:14–24. 8 The Matrix originally was included in the January 2019 Offer Letter and later was incorporated into the signed Lease as Exhibit C. See Docket 22-14 at 8; Docket 22-43 at 62–63. 9 See Docket 27-17 ¶ 1.1; Docket 27-16 ¶ 2. its opening.10 The disputed provision assigns FEA “fire sprinkler system/monitoring – new and/or modifications for building shell compliance with code” before delivering the Premises to Jo-Ann.11

The Anchorage Municipal Fire Code requires a building’s sprinkler system to deliver a certain amount of water per minute based on that building’s fire risk.12 Any retail store or space with a “mercantile use” is classified, at minimum, as an “ordinary hazard II” fire risk.13 Accordingly, for Jo-Ann to operate its store, the Premise’s sprinkler system must comply with code requirements for an “ordinary hazard II” fire risk.14 By

contrast, a vacant building shell is classified as a “light hazard,” meaning that it has a lower fire risk and therefore its sprinkler system has lower requirements for the amount of water expelled per minute.15 In the spring of 2019, after the parties executed the Offer Letter and drafted the Matrix, FEA began construction to prepare the Premises for occupancy.16 It retained

McKinley Fire Protection, LLC (“McKinley Fire”) to upgrade the sprinkler system for an “open concept vanilla shell.”17 McKinley Fire changed the sprinkler heads from pendant to upright and did any other work required to bring the Premises into compliance with the

10 See Docket 27-17 ¶ 1.2; Docket 27-16 ¶ 2. 11 Docket 27-17 ¶ 7.7. 12 Docket 27-2 at 15:5–15. 13 Stores with highly flammable goods or with “high-pile storage” may trigger a higher hazard classification. Docket 27-2 at 16:19–18:21. 14 The Court refers to the code requirements for “mercantile use” and “retail use” interchangeably. 15 Docket 27-2 at 16:4–16. 16 Docket 27-16 ¶ 7. 17 Docket 22-23; Docket 27-16 ¶ 7. FEA hired Neeser Construction to complete all other repairs under the Matrix, excluding work on the sprinkler system. Docket 27 at 8. fire code for an empty shell.18 As such, McKinley Fire’s permit for the sprinkler work was based on a “light hazard” use and was conditioned as being “for Core and Shell only.”19

Indeed, in a letter submitted to the Municipal Fire Inspector, FEA stated that, [a]s this space is unoccupied at this time, and we do not have a prospective tenant for this space at this time, [we] are working to turn the space into an open concept vanilla shell in preparation for any potential future tenants. As such, we would like to turn the sprinkler heads in this space upwards to maintain fire protection and keep with the open concept.20

The scope of this permit was entirely independent from the construction permit that Jo- Ann would later receive for its tenant build-out.21 Neither this permit nor FEA’s communications with the Municipal Fire Inspector were shared with Jo-Ann.22 FEA delivered the Premises to Jo-Ann on November 4, 2019.23 Representatives from Jo-Ann walked through the space and visually confirmed that the Premises met FEA’s requirements under the Matrix.24 Jo-Ann conditionally accepted delivery of the Premises pending the completion of smaller, unrelated projects.25 That winter, Jo-Ann began its tenant build-out. On January 20, 2020, Jo-Ann’s sprinkler subcontractor informed Jo-Ann that the sprinkler system was not up to code for ordinary hazard II risk, as is required for a retail store, but was instead outfitted for light hazard risk as an open shell.26 Jo-Ann informed

18 Docket 27-16 ¶ 7. 19 Docket 27-15; Docket 22-21 at 1. 20 Docket 22-23. 21 Docket 22-21 at 1. 22 Docket 22 at 9–10; see also Docket 22-8 at 118:10–21. 23 See Docket 27-16 ¶ 10. 24 Docket 22-8 at 118:10–21; Docket 27-16 ¶ 10. 25 Docket 22-22 at 1. 26 See Docket 22-27. FEA of the issue that same day, but the parties did not agree on who was responsible for the renovation.27 On February 21, 2020, Jo-Ann sent FEA a notice of default for its failure

to deliver a code-compliant building, informing FEA that it would perform the upgrades on FEA’s behalf.28 In anticipation of the store’s opening, Jo-Ann completed repairs of the sprinkler system on May 15, 2020.29 Jo-Ann has paid rent since it opened for business on August 13, 2020.30 However, because the parties dispute whose responsibility it was to bring the sprinkler

system up to code for mercantile use, the parties also dispute when rent began to accrue. Under the Lease, Jo-Ann is required to start paying rent on “(i) the 151st day after the Delivery Date, or (ii) the day that Tenant opens for business in the Premises, whichever day first occurs.”31 The Delivery Date is defined as “the date Landlord delivers the Premises to Tenant with all of the Delivery Requirements satisfied . . . . ”32 Jo-Ann argues that FEA failed to satisfy its delivery requirements; therefore, rent began to accrue when

Jo-Ann opened for business on August 13, 2020.33 FEA argues that rent began to accrue on April 3, 2020, which is 151 days after it purportedly satisfactorily delivered the Premises on November 4, 2020.34 Under FEA’s interpretation of the Lease, Jo-Ann is in arrears for $165,385, or approximately three months of rent.35

27 See id.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Erie Railroad v. Tompkins
304 U.S. 64 (Supreme Court, 1938)
First Nat. Bank of Ariz. v. Cities Service Co.
391 U.S. 253 (Supreme Court, 1968)
Anderson v. Liberty Lobby, Inc.
477 U.S. 242 (Supreme Court, 1986)
In Re Oracle Corp. Securities Litigation
627 F.3d 376 (Ninth Circuit, 2010)
Little Susitna Construction Co. v. Soil Processing, Inc.
944 P.2d 20 (Alaska Supreme Court, 1997)
Stepanov v. Homer Elec. Ass'n, Inc.
814 P.2d 731 (Alaska Supreme Court, 1991)
Monzingo v. Alaska Air Group, Inc.
112 P.3d 655 (Alaska Supreme Court, 2005)
Estate of Polushkin Ex Rel. Polushkin v. Maw
170 P.3d 162 (Alaska Supreme Court, 2007)
Rockstad v. Global Finance & Investment Co.
41 P.3d 583 (Alaska Supreme Court, 2002)
Mahan v. Mahan
347 P.3d 91 (Alaska Supreme Court, 2015)
JL Beverage Co. v. Jim Beam Brands Co.
828 F.3d 1098 (Ninth Circuit, 2016)
Graham v. Municipality of Anchorage
446 P.3d 349 (Alaska Supreme Court, 2019)
Danyelle D. Kimp v. Fire Lake Plaza II, LLC
484 P.3d 80 (Alaska Supreme Court, 2021)

Cite This Page — Counsel Stack

Bluebook (online)
Furniture Enterprises of Alaska, Inc. v. Jo-Ann Stores, LLC, Counsel Stack Legal Research, https://law.counselstack.com/opinion/furniture-enterprises-of-alaska-inc-v-jo-ann-stores-llc-akd-2022.