Miller v. Handle Construction Co.

255 P.3d 984, 2011 Alas. LEXIS 65, 2011 WL 2937217
CourtAlaska Supreme Court
DecidedJuly 22, 2011
DocketS-13426
StatusPublished
Cited by6 cases

This text of 255 P.3d 984 (Miller v. Handle Construction Co.) is published on Counsel Stack Legal Research, covering Alaska Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Miller v. Handle Construction Co., 255 P.3d 984, 2011 Alas. LEXIS 65, 2011 WL 2937217 (Ala. 2011).

Opinions

OPINION

PER CURIAM.

I. INTRODUCTION

A landowner contracted with a manufacturer to purchase a pre-fabricated steel hangar. In a separate agreement, the landowner contracted with a construction company to erect the steel hangar on his land. After completing its work, the construction company sued the landowner for unanticipated costs it incurred as a result of manufacturing defects in the pre-fabricated hangar. The landowner made an $18,000 offer of judgment, which the construction company accepted. But when the construction company received a separate payment from the manufacturer, the landowner refused to pay the full $18,000, arguing that an offset was warranted. The superior court rejected the landowner's argument, ordering him to pay the full amount of the offer. Because the basis for the superior court's decision is unclear, we reverse and remand for additional factual findings.

II. FACTS AND PROCEEDINGS

Gary Miller is the lessee of a tract of land at Lake Hood. Planning to develop his land into a hangar facility, Miller purchased a prefabricated steel hangar building from VP Buildings (VP).1 Miller then entered into a contract with Handle Construction Company for Handle to erect the hangar and perform other services relating to the hangar's construction.

In assembling the building, two costly de-feets in the pre-fabricated hangar became apparent. - First, a paint-related defect caused rust damage. Second, an entirely separate defect relating to the steel caused Handle to incur more costs than it had anticipated in erecting the building. Handle claimed that the additional costs arising out of the steel defect amounted to $18,000. The hangar manufacturer, VP, acknowledged the steel defect, but claimed that the damages were only around $6,000. Miller also believed that the damages were less than Handle alleged.

Because both VP and Handle had contracted with Miller, but not with each other, Miller found himself in the position of a middleman with respect to the additional costs Handle had incurred as a result of the steel defect. Handle could not directly recover from the manufacturer VP; rather, Handle would have to assert a claim against Miller, who would in turn have to seek recovery from VP. Because Miller was reluctant to advocate for the higher amount of damages Handle alleged, and because he believed that Handle was in a better position to explain its claim, Miller authorized Handle to negotiate directly with the manufacturer as to the amount owed.

It appears that both Miller and Handle understood the seope of this granted authority to be quite narrow, consisting exclusively of the power to negotiate, and not the power to collect payment on Miller's behalf. Miller stated in an affidavit that he never assigned [986]*986Handle his contractual rights against VP. The superior court echoed this in its findings, stating that Handle had no contractual relationship with VP and, thus, could not independently assert a claim against VP. An email that Handle sent to Miller in May 2008 suggests that Handle shared this understanding of the authority it had been granted. Handle wrote:

Please understand that our contract is with you, not with [VP]. In an attempt to help you secure payment from [VP], I have forwarded all of the information.... Although, the bottom line is, we expect payment from you whether you receive payment from [VP] or not.

Thus, it appears that both parties understood that Handle's negotiating authority did not encompass the power to independently recover from VP.

In March 2008, Handle recorded a lien against Miller's leasehold in the amount of $39,600.11, plus interest, costs, and attorney's fees. This amount included the alleged $13,000 "backcharges" caused by the steel defect, which was in addition to other unrelated damages that Handle argued Miller owed. In June, Handle filed a complaint against Miller seeking recovery of the entire amount of the lien. The following month VP-which was not a party to the pending litigation-offered to pay Handle $5,900 as compensation for the additional costs it incurred related to the steel defect. On the same day, VP also offered to pay Miller $9,502. While Handle took no immediate action on its offer, Miller accepted his offer almost immediately. Although both Handle and VP later asserted that the $9,502 settled all of Miller's claims against VP, the superior court found that it was solely for the "paint/ rust claim" and Handle does not appeal this finding.

In September, Miller made a Civil Rule 68 offer of judgment to Handle in hopes of settling Handle's lawsuit. Miller's offer stated that it was

to allow judgment to be entered against him in complete satisfaction of Plaintiff's claims. This offer is in the principal amount of EIGHTEEN THOUSAND DOLLARS ($18,000.00), plus attorney's fees computed to the Civil Rule 82(b)(1) schedule (contested without trial), plus costs computed pursuant to Civil Rule 79, plus prejudgment interest.

Several days after Miller made this offer, Handle's attorney asked Miller's attorney if the offer included an amount for the claim that Handle had concerning the steel defect. Miller's attorney said that it did and that Miller intended to collect the $5,900 VP had offered,2 to which Handle's attorney replied that the offer was probably too low.

At no point did Miller revoke the authority he had granted Handle to negotiate directly with VP. On October 2, Handle informed VP that it would accept the offer of $5,900. The following day, Handle accepted Miller's $18,000 offer of judgment.

A week later, Miller's attorney wrote to Handle's attorney regarding Handle's acceptance of both offers. Miller's attorney stated that the $5,900 from VP was rightfully Miller's, and reiterated that Miller had intended the offer of judgment to settle the steel defect claim. Therefore, he explained, the amount that Handle had collected from VP would be credited against Miller's $18,000 offer of judgment. Handle's attorney responded by insisting that Miller had not conditioned the offer of judgment on an offset and that, as a result, Handle expected full payment from Miller. When Miller declined to pay the full amount, Handle filed a motion for entry of judgment upon confession, based upon Miller's Rule 68 offer and Handles acceptance of the offer.

Miller opposed the motion. The superior court held oral argument, but did not hold an evidentiary hearing. In its order on Handle's motion, the superior court rejected all of Miller's arguments, finding that the offer of judgment did not entail an offset under these circumstances and that Handle's accep[987]*987tance was not voided by unilateral mistake. The court made no findings as to whether the $5,900 Handle accepted from VP actually belonged to Miller. The court entered judgment against Miller, ordering him to pay the full $18,000, plus attorney's fees, costs, and pre-judgment interest.

Miller appeals.

IIH. STANDARD OF REVIEW

We interpret an accepted offer of judgment according to our independent judgment.3 We review questions of law de novo.4

IV. DISCUSSION

Miller argues that the superior court erred in finding that the cireumstances did not warrant an offset of the judgment.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Gunn v. Gunn
367 P.3d 1146 (Alaska Supreme Court, 2016)
McGinnis v. Cox
465 S.W.3d 157 (Court of Appeals of Tennessee, 2014)
Green v. Allstate Insurance
25 F. Supp. 3d 1215 (D. Alaska, 2014)
Zamarello v. Reges
321 P.3d 387 (Alaska Supreme Court, 2014)
Miller v. Handle Construction Co.
255 P.3d 984 (Alaska Supreme Court, 2011)

Cite This Page — Counsel Stack

Bluebook (online)
255 P.3d 984, 2011 Alas. LEXIS 65, 2011 WL 2937217, Counsel Stack Legal Research, https://law.counselstack.com/opinion/miller-v-handle-construction-co-alaska-2011.