Moore Construction Co. v. Clarksville Department of Electricity

707 S.W.2d 1
CourtCourt of Appeals of Tennessee
DecidedMarch 24, 1986
StatusPublished
Cited by83 cases

This text of 707 S.W.2d 1 (Moore Construction Co. v. Clarksville Department of Electricity) is published on Counsel Stack Legal Research, covering Court of Appeals of Tennessee primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Moore Construction Co. v. Clarksville Department of Electricity, 707 S.W.2d 1 (Tenn. Ct. App. 1986).

Opinion

OPINION

KOCH, Judge.

This case involves a contractor’s claim for delay damages arising out of the construction of the Clarksville Department of Electricity’s new office building and warehouse. Moore Construction Company filed this action in the Law and Equity Court for Montgomery County based alternatively on contract and quasi-contract theories against the Clarksville Department of Electricity, the Kennon Construction Company (a co-prime contractor), and the Cincinnati Insurance Company (Kennon’s bonding company). Following a trial without a jury, the trial court entered a judgment on January 9, 1984, wherein it awarded Moore Construction Company $2,719.75 in damages against the Clarksville Department of Electricity and dismissed its actions against the Kennon Construction Company and the Cincinnati Insurance Company. Moore Construction Company has duly perfected this appeal. For the reasons stated herein, we modify the judgment of the trial court.

I.

The Facts

In 1980, the Clarksville Department of Electricity [hereinafter referred to as the “Department”] embarked upon a project to construct a new office building and general warehouse on Highway 79-N in the St. Bethlehem community of Clarksville. The Department proceeded to retain two separate design firms to develop plans for the project. On November 20, 1980, it hired Clarksville Engineering Services, Inc. [hereinafter referred to as “Clarksville Engineering”] to prepare the plans and specifications for the site preparation and other exterior work. It also retained Rufus Johnson and Associates to design the office building and warehouse.

Once both sets of plans were completed, the Department decided to proceed by hiring two different prime contractors, one to perform the site preparation and other exterior work and the other to construct the office building and warehouse. On March 17, 1981, it entered into a standard form contract 1 in the amount of $469,747.55 with the Moore Construction Company of Clarksville [hereinafter referred to as “Moore”] to perform the site preparation and other exterior work. The Department gave Moore its notice to proceed immediately because a portion of the site preparation work was required to be completed before the other prime contractor could begin constructing the office building and warehouse. Moore began to work as soon as it received the notice to proceed.

On May 29, 1981, the Department entered into a second standard form contract 2 in the amount of $1,132,477 with the Kennon Construction Company of Nashville [hereinafter referred to as “Kennon”] to construct the office building and general warehouse. Following the accepted practice of the construction industry and pursuant to Tenn.Code Ann. § 12-4-201 et seq., Kennon furnished the Department with a standard form performance bond and a standard form labor and material payment *4 bond 3 each issued by the Cincinnati Insurance Company [hereinafter referred to by name or as the “bonding company”] to assure Kennon’s complete and satisfactory performance of its contractual obligations to the Department.

Following the execution of Kennon’s contract, all parties, including the Department, both general contractors, and both design firms, held a preconstruction conference at the job site to discuss the sequence of the work. In general terms, they agreed upon the work Moore would complete before Kennon started its work and upon the manner in which the two contractors would coordinate their work. After this meeting, all parties understood that Moore would be able to complete only part of its work before Kennon started construction and that Moore would be able to complete the remainder of its work only after Kennon had constructed most of the office building and warehouse. The parties also agreed upon the areas at the job site where Kennon and its subcontractors would store their equipment and materials in order to avoid interfering with the work that Moore was doing. Based upon this meeting and the terms of its contract, 4 Moore expected that its work would be substantially complete on October 26, 1981.

The Department gave Kennon its notice to proceed on June 22, 1981. Kennon began to work soon thereafter; however, its work began to bog down several months later when it experienced problems on the job. These problems were not due to the manner in which Moore was performing its work but rather were caused by the defective work of Kennon’s masonry subcontractor and by the installation of a defective roof on the warehouse portion of the project. The delay caused by these problems as well as delays caused by the weather put Kennon substantially behind schedule, and, therefore, it was unable to complete enough of its work to permit Moore to finish the remainder of its work within the time allowed by Moore’s contract with the Department.

Beginning in September, 1981, Moore began to make a series of complaints that it could not complete its work because of Kennon’s delay in performing its work and because Kennon and its subcontractors were not using the areas designated for storage of materials and equipment but rather were storing their equipment and materials adjacent to the building. This, coupled with the construction trash being strewn in the construction area, prevented Moore from completing its work.

As a result of Moore’s concerns, the parties conducted a meeting on the job site on September 14, 1981, to discuss a revised schedule for completing the work. As a result of this meeting, the parties agreed to adjust the schedule to allow for the delays they had already experienced. While no written change order altering the time for performance 5 appears to have been prepared, the project manager prepared a memorandum of this meeting on September 15, 1981, stating that the parties had agreed to extend Moore’s time to complete the paving portion of its work until the end of November, 1981.

Kennon continued to experience delays caused by its own subcontractors following this meeting, and Moore continued to be prevented from completing its work even in accordance with the revised schedule. At Moore’s request, another meeting was held at the job site on December 15, 1981, to discuss this problem. At that meeting, like other meetings, Kennon assured Moore *5 that the project would be ready for them to return to work “within a few days.” It was not.

During the period of delay commencing approximately in September, 1981, when Moore was unable to work, it was required to maintain certain of its supervisory employees on the project on a part-time basis to make sure that the work it had already done was protected. On several occasions, Moore moved its workers back onto the project based upon Kennon’s assurances that it could begin work only to find that it could not proceed.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Los Pumas Concrete v. Harmony Hospitality, LLC
Court of Appeals of Tennessee, 2021
Liberty Construction Company, LLC v. Peter H. Curry
Court of Appeals of Tennessee, 2020
101 Construction Company v. Lawrence B. Hammet, II
Court of Appeals of Tennessee, 2019
Avis Lavar King v. State
Court of Appeals of Texas, 2019
Howry v. New Leaders, Inc.
W.D. Tennessee, 2019
John Doe v. Belmont Univ.
334 F. Supp. 3d 877 (M.D. Tennessee, 2018)
Panika McFadden v. State
Court of Appeals of Texas, 2018
Kathryn J. Reitz v. City of Mt. Juliet
Court of Appeals of Tennessee, 2017
Sandra L. Wallis v. Brainerd Baptist Church
509 S.W.3d 886 (Tennessee Supreme Court, 2016)
Tim Grace v. Jeanna Grace d/b/a Grace Trucking
Court of Appeals of Tennessee, 2016
RCR Building Corporation v. State of Tennessee
Court of Appeals of Tennessee, 2015
Lindenberg v. Jackson National Life Insurance
98 F. Supp. 3d 934 (W.D. Tennessee, 2014)
Act for Health v. Case Management Associates, Inc.
128 F. Supp. 3d 1020 (E.D. Tennessee, 2014)
Brooke Buttrey v. Holloway's, Inc.
Court of Appeals of Tennessee, 2012

Cite This Page — Counsel Stack

Bluebook (online)
707 S.W.2d 1, Counsel Stack Legal Research, https://law.counselstack.com/opinion/moore-construction-co-v-clarksville-department-of-electricity-tennctapp-1986.