Cretex Companies, Inc. v. Construction Leaders, Inc.

342 N.W.2d 135, 1984 Minn. LEXIS 1198
CourtSupreme Court of Minnesota
DecidedJanuary 13, 1984
DocketCX-82-1676
StatusPublished
Cited by38 cases

This text of 342 N.W.2d 135 (Cretex Companies, Inc. v. Construction Leaders, Inc.) is published on Counsel Stack Legal Research, covering Supreme Court of Minnesota primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Cretex Companies, Inc. v. Construction Leaders, Inc., 342 N.W.2d 135, 1984 Minn. LEXIS 1198 (Mich. 1984).

Opinions

SIMONETT, Justice.

We conclude that unpaid materialmen, plaintiff-respondents on this appeal, are not intended third-party beneficiaries under the defaulting general contractor’s performance bond and, therefore, are not entitled to recover from the defendant-appellant surety. We reverse the trial court.

Northland Mortgage Company owns property in Maple Grove and Plymouth, Minnesota. It engaged defendant Construction Leaders, Inc., as its general contractor, to do the utilities construction for the development projects on the two properties. Defendant-appellant Travelers Indemnity Company wrote the performance bonds for the construction projects. There were two construction contracts and, since the work was to be done in five phases, five performance bonds. For each performance bond Travelers was the surety, Construction Leaders, Inc., as general contractor, was the principal, and Northland Mortgage Company, as owner of the projects, was the obligee.

Thereafter, during the course of its work, Construction Leaders defaulted and is now apparently insolvent. Travelers [137]*137stepped in and hired another contractor, who completed the work. Some of Construction Leader’s suppliers and subcontractors, however, were left unpaid, including plaintiff-respondents, The Cretex Companies, Inc., and Ess Brothers & Sons, Inc. Although Cretex and Ess Brothers could have filed mechanic’s liens against North-land’s property, they failed to do so; apparently they assumed their materials were to be used by the general contractor on public projects and they did not discover otherwise until it was too late to file liens. Having lost their lien rights, Cretex and Ess Brothers brought this action against Travelers in an attempt to collect on the performance bonds. In addition, plaintiffs sued the general contractor, Construction Leaders, for breach of their subcontracts.

On cross-motions for summary judgment, the trial court granted summary judgment in favor of the plaintiff suppliers against both the surety and the general contractor on the issue of liability. The parties then stipulated to the amount of damages. Travelers alone appeals, raising only the issue whether plaintiffs are entitled to recover their unpaid claims under the performance bonds.

The issue is whether unpaid materialmen are third-party intended beneficiaries under Travelers’ bonds. First of all, it should be noted that the two construction contracts between Northland (the owner) and Construction Leaders (the general contractor) plainly call for a performance rather than a payment bond. The contracts require:

A good and sufficient 'performance bond in the sum of not less than the full amount of the Contract, payable to the Owner, as provided by law, shall-be made and delivered * * *.
The Performance Bond shall guarantee the Contractors: [sic] performance as required by these Contract Documents, satisfaction of all lein [sic] rights of Subcontractors and materials suppliers, * *.

(Emphasis added.)

Pursuant to this contract requirement, Travelers, as surety, issued its “Contract Bond” with Construction Leaders as principal and Northland as obligee, providing:

NOW, THEREFORE, the condition of this obligation is such, that if the Principal shall faithfully perform the contract on his part, free and clear of all liens arising out of claims for labor and materials entering into the construction, and indemnify and save harmless the Obligee from all loss, cost or damage which he may suffer by reason of the failure so to do, then this obligation shall be void; otherwise to remain in full force and effect.

It seems clear enough, at least so far, that the contracting parties intended to have only a performance bond. The purpose of a performance bond is to ensure that the principal or his surety will perform the contract for an agreed price. Because performance of the work alone is not sufficient to protect the owner-obligee, the surety also agrees to indemnify the owner-obli-gee for any loss from liens filed against the property by reason of the contractor-principal’s default in payment of his material-men. Thus Travelers claims here that its bonds were intended for the exclusive use and benefit of its obligee, Northland, and afford no contractual rights to third-party subcontractors or suppliers.

Travelers points out that if the owner and general contractor had wished to protect third-party materialmen they could have purchased, for a separate premium, a “labor and material payment bond,” a bond which Travelers also sells and which is usually issued simultaneously with the performance bond. A “payment” bond expressly provides for the surety to pay the claims of third-party subcontractors and materialmen if the general contractor fails to do so.1 The distinction between per[138]*138formance bonds and payment bonds is well recognized in the construction industry; the two bonds cover different risks and premiums are set accordingly. See, e.g., Scales-Douwes Corp. v. Paulaura Realty Corp., 24 N.Y.2d 724, 301 N.Y.S.2d 980, 249 N.E.2d 760 (1969); J. Calamari & J. Perillo, Contracts § 17-7 (2d ed. 1977); A. Corbin, Contracts § 798 (Supp.1982).

Plaintiff-respondents argue, however, that though Travelers’ bond may be in form a “performance” bond, intended for the protection of the owner-obligee, it is also in fact a “payment” bond, intended for the benefit of third persons who are not parties to the surety’s contract. To reach this conclusion, respondents rely on the third-party contract beneficiary doctrine.

The trial court found, and Travelers does not dispute, that the provisions of the underlying construction contracts are incorporated by reference into the bonds, and apparently not just for identification purposes. Each bond identifies the construction contract between Northland and Construction Leaders and adds “a copy of which is by reference made a part hereof.” Among other things, section 9 of the construction contract reads that “the Contractor shall provide and pay for all materials, labor, water, tools, equipment, light, power, transportation and other facilities necessary for the execution and completion of the work.” Other sections provide that if the contractor fails to pay subcontractors or materialmen, the owner may terminate the contract or withhold payments. From this respondents argue as follows:, the bond is conditioned on full and faithful performance of the construction contract by the principal-general contractor; performance of the contract by the contractor includes payment by the contractor of the claims of his subcontractors and material-men; therefore, the surety has agreed that if the contractor does not pay his suppliers, the surety will do it for him, thus making the suppliers third-party intended beneficiaries of the bond. The trial court accepted this argument, relying also on Restatement of Securities, § 165 (1940), and two cases, Westinghouse Electric Corp. v. Mill & Elevator Co., 254 Iowa 874, 118 N.W.2d 528 (1962), and Iowa Sheet Metal Contractors, Inc. v. Knab Co., 17 Wis.2d 493, 117 N.W.2d 682 (1962).

The parties all cite Buchman Plumbing Co. v.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

BCBSM, Inc. v. GS Labs, LLC
D. Minnesota, 2023
Safety Signs, LLC v. Niles-Wiese Construction Co.
840 N.W.2d 34 (Supreme Court of Minnesota, 2013)
Minnesota Laborers Health & Welfare Fund v. Granite RE, Inc.
826 N.W.2d 210 (Court of Appeals of Minnesota, 2012)
Caldas v. Affordable Granite & Stone, Inc.
820 N.W.2d 826 (Supreme Court of Minnesota, 2012)
Hickman v. SAFECO Insurance Co. of America
695 N.W.2d 365 (Supreme Court of Minnesota, 2005)
Dayton Development Co. v. Gilman Financial Services, Inc.
299 F. Supp. 2d 933 (D. Minnesota, 2003)
Leamington Co. v. Nonprofits' Ins. Ass'n
615 N.W.2d 349 (Supreme Court of Minnesota, 2000)
Wallin v. Minnesota Department of Corrections
598 N.W.2d 393 (Court of Appeals of Minnesota, 1999)
Servais v. T.J. Management of Minneapolis, Inc.
973 F. Supp. 885 (D. Minnesota, 1997)
614 Co. v. Minneapolis Community Development Agency
547 N.W.2d 400 (Court of Appeals of Minnesota, 1996)
Rural American Bank of Greenwald v. Herickhoff
485 N.W.2d 702 (Supreme Court of Minnesota, 1992)

Cite This Page — Counsel Stack

Bluebook (online)
342 N.W.2d 135, 1984 Minn. LEXIS 1198, Counsel Stack Legal Research, https://law.counselstack.com/opinion/cretex-companies-inc-v-construction-leaders-inc-minn-1984.