Amelco Window Corp. v. Fed. Ins. Co.
This text of 317 A.2d 398 (Amelco Window Corp. v. Fed. Ins. Co.) is published on Counsel Stack Legal Research, covering New Jersey Superior Court Appellate Division primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.
Opinion
THE AMELCO WINDOW CORP., A CORPORATION, PLAINTIFF-APPELLANT,
v.
FEDERAL INSURANCE COMPANY, DEFENDANT-RESPONDENT.
Superior Court of New Jersey, Appellate Division.
*344 Before Judges CARTON, SEIDMAN and DEMOS.
Messrs. Heller and Laiks, attorneys for appellant (Mr. Richard K. Rosenberg, of counsel and on the brief).
Mr. Louis Auerbacher, Jr., attorney for respondent.
The opinion of the court was delivered by DEMOS, J.S.C., Temporarily Assigned.
Plaintiff The Amelco Window Corp. (Amelco) instituted an action against Federal Insurance Company (Federal) to recover, as a third-party beneficiary, on a surety bond provided by Federal for a construction project. In its answer Federal denied plaintiff was within the class of persons who were entitled to protection under the bond, asserting that it had only agreed to indemnify the owner for any loss resulting from a default by the general contractor and not to secure payment to subcontractors for labor and materials.
The parties filed cross-motions for summary judgment. The court below granted Federal's motion and entered judgment in its behalf. Amelco appeals from that decision.
The facts are not materially disputed. Amelco entered into a written subcontract with Frank W. Bogert, Inc (Bogert), the general contractor, for the installation of windows and doors on a project known as "No. 1 University Plaza." Bogert had furnished a performance bond, with Federal as surety, in accord with Bogert's contract with the owner, Fairleigh Dickinson University (University). The construction contract between the University and Bogert contained the following:
7.5 PERFORMANCE BOND AND LABOR AND MATERIAL PAYMENT BOND
The Owner shall have the right prior to signing the Contract, to require the Contractor to furnish bonds covering the faithful performance of the Contract and the payment of all ogligations [sic] arising thereunder in such form and amount as the Owner may prescribe and with such sureties as may be agreeable to the parties. If *345 such bonds are stipulated in the bidding requirements, the premiums shall be paid by the Contractor; if required subsequent to the submission of quotations or bids, the cost shall be reimbursed by the Owner. The Contractor shall deliver the required bonds to the Owner not later than the date of execution of the Contract, or if the work is commenced prior thereto in response to a notice to proceed, the Contractor shall, prior to commencement of the work, submit evidence satisfactory to the Owner that such bonds will be issued.
* * * * * * * *
Section 4:4.1. Unless otherwise specifically noted, the Contractor shall provide and pay for all labor, materials, equipment, tools, construction equipment and machinery, water, heat, utilities, transportation, and other facilities and services necessary for the proper execution and completion of the work.
The surety agreement stated that it was "in accordance with the terms and conditions of said contract [Bogert-University] which is hereby referred to and made a part hereof as if fully set forth herein". It also stated;
NOW, THEREFORE, THE CONDITION OF THIS OBLIGATION IS SUCH, that if the above bounden Principal [Bogert] shall well and truly keep, do and perform each and every, all and singular, the matters and things in said contract set forth and specified to be by said Principal kept, done and performed at the times and in the manner in said contract specified, or shall pay over, made good and reimburse to the above named Obligee [University], all loss and damage which said Obligee must sustain by reason of failure or default on the part of said Principal so to do, then this obligation shall be null and void; otherwise shall remain in full force and effect.
A subsequent rider substituted University Plaza Realty Corporation in place of University as obligee. The substitution has no effect upon this controversy.
Bogert went into bankruptcy before the building was completed, thereby creating a default under its contract with the University.
The essential issue involved here is whether a subcontractor may avail itself of a surety bond conditioned for the faithful performance by the principal of a prime construction contract containing no express provision for payment of unpaid claims of subcontractors, where the general contract requires the principal to pay all claims for labor and materials. Appellants' *346 position is grounded upon the fact that the surety bond and the construction contract are expressly integrated and therefore recovery is permitted under the bond for its unpaid claim.
There is no dispute that the execution of the bond in question established a suretyship, with Bogert as the principal, Federal as the surety and University (later replaced by University Plaza Realty Corporation) as the obligee.
Suretyship is a contractual relation resulting from an agreement whereby one person, the surety, engages to be answerable for the debt, default or miscarriage of another, the principal. While the contract of a surety is, in a sense, accessory or collateral to a valid principal obligation contracted by another person, either contemporaneously or previously, his obligation to the creditor or promisee of the principal is direct, primary and absolute. The surety contract is not that the obligee will see to it that the principal pays the debt or fulfills the contract, but rather that the surety will see that the principal pays or performs. 50 Am. Jur., Suretyship, § 2 at 903-904.
Surety bonds are commonly used in construction projects. Accordingly, our courts have been presented with situations involving the surety relationship and the rights, duties and liabilities flowing therefrom. While no previous reported decision in our courts meets the precise issue presented in the matter before us, several principles have been enunciated which control its disposition.
Before considering these decisions it is helpful to acknowledge some general points set forth in 4 Corbin on Contracts, § 798 at 162-164 (1951). Therein it is stated that a third party to a surety agreement need not stand in "privity" with the contracting parties. He need not be a "promisee" or give consideration in order to become a beneficiary under the surety agreement. The law recognizes that the third party has an enforceable right if the surety promises in the bond, either in express words or by reasonable implication, to pay money to him. If there is such a promissory expression, there *347 need be no discussion of "intention to benefit." These points are cited with approval in Schlanger v. Federal Ins. Co., 44 N.J. 17, 20 (1965).
Supported by these principles is the doctrine that where, as here the surety bond incorporates the prime construction contract by reference, the two, being integrated, must be considered together. Graybar Electric Co. v. Continental Cas. Co., 50 N.J. Super. 289, 295 (App. Div. 1958); Acoustics, Inc. v. Hanover Ins. Co., 118 N.J. Super 361, 364 (Law Div. 1971). Therefore a surety bond that is conditioned on full performance of his contract by the principal will operate in favor of such third parties as the principal, by his contract with the promisee, undertakes to pay. The bond need not be more specific. 4 Corbin on Contracts, supra. § 799 at 168.
Free access — add to your briefcase to read the full text and ask questions with AI
Related
Cite This Page — Counsel Stack
317 A.2d 398, 127 N.J. Super. 342, 1974 N.J. Super. LEXIS 738, Counsel Stack Legal Research, https://law.counselstack.com/opinion/amelco-window-corp-v-fed-ins-co-njsuperctappdiv-1974.