NOT FOR PUBLICATION WITHOUT THE APPROVAL OF THE APPELLATE DIVISION
SUPERIOR COURT OF NEW JERSEY APPELLATE DIVISION DOCKET NO. A-1113-12T4
ALLIED BUILDING PRODUCTS APPROVED FOR PUBLICATION CORP., September 5, 2014 Plaintiff, APPELLATE DIVISION v.
J. STROBER & SONS, LLC, SUSAN F. STROBER, Individually, STEVE STROBER, Individually, and ARCH INSURANCE COMPANY,
Defendants,
and
DOBCO, INC.,
Defendant-Appellant,
COLONIAL SURETY COMPANY,
Defendant-Respondent.
_____________________________________
Argued September 11, 2013 – Decided September 5, 2014
Before Judges Grall, Nugent and Accurso.
On appeal from Superior Court of New Jersey, Law Division, Bergen County, Docket No. L-601-10. Christopher Nucifora argued the cause for appellant (Kaufman, Dolowich & Voluck, LLP, attorneys; Mr. Nucifora and Antonio J. Casas, on the briefs).
Greg Trif argued the cause for respondent (McElroy, Deutsch, Mulvaney & Carpenter, LLP, attorneys; Mr. Trif and Adam R. Schwartz, of counsel and on the brief).
The opinion of the court was delivered by
ACCURSO, J.A.D.
In this action on a surety bond, Dobco, Inc. (Dobco)
appeals from a September 19, 2012 final judgment denying its
motion for partial summary judgment against Colonial Surety
Company (Colonial), surety for J. Strober & Sons, LLC (Strober),
Dobco's subcontractor, and granting Colonial's motion for
summary judgment dismissing Dobco's cross-claims1 against
Colonial. The Law Division dismissed Dobco's claims against
Colonial under the bond on the ground that the bond did not name
Dobco as the obligee and because Dobco had rejected the bond as
not in the form required by its subcontract with Strober. We
deem neither of those facts material because we conclude that in
entering into its surety contract with Strober, Colonial
1 This action began as a book account complaint by Allied Building Products Corp. (Allied), a material supplier to Strober, against Strober, Dobco and Colonial. Dobco's affirmative claims against Colonial were thus properly denominated as cross-claims in that action. Because Allied's claims, which were resolved prior to these motions, are irrelevant to the issues before us, we do not discuss them.
2 A-1113-12T4 obligated itself to issue a performance bond to Dobco in the
form annexed to the Dobco/Strober subcontract. Accordingly, we
reverse.
The facts adduced on the motions establish that Dobco was
the general contractor to The William Patterson University (WPU)
for a project referred to as the "Science Hall Addition,
Renovation, and Greenhouse." Strober bid for and was awarded a
subcontract for the roofing work. Dobco and Strober entered
into a standard AIA ("American Institute of Architects") form of
agreement on November 11, 2008. The agreement required Strober
to furnish performance and payment bonds in the amount of
$890,000, in the forms annexed to the agreement, prior to
commencing work.2 Strober applied to Colonial, the surety that
had furnished Strober's bid bond for the project, for its
performance bond.
Colonial is a Pennsylvania company, licensed in New Jersey
as a property and casualty insurer. The company specializes in
contract surety and fidelity. By it's president's account,
Colonial does not "write business" in the way other insurers do.
Upon establishing a "partnership account" with Colonial, a
2 As only the performance bond is at issue here, we limit our discussion to it, although acknowledging that it was issued in tandem with the payment bond and the premium Strober paid Colonial was apparently for both bonds.
3 A-1113-12T4 contractor is provided a "line of surety" with single and
aggregate limits, a power of attorney and Colonial's seal. When
the contractor wants to obtain a bid bond for a project, it uses
its partnership account code to log into Colonial's website,
inputs the project information and prints out the bond and
consent of surety. The contractor signs the documents on behalf
of Colonial using its power of attorney, applies Colonial's seal
and submits the bond and consent of surety with its bid.
If the contractor wins the contract, it updates the online
information provided previously and requests issuance of the
performance bond. Colonial then has one of its bond
administrators make inquiries regarding the bid spreads between
the top few bidders, the identity of the architect and the
engineer's estimate.3 The package is then submitted to
3 Colonial's witnesses testified at deposition about the inquiries made in this matter with reference to notes on a bid bond request form printed the day before Colonial issued its performance bond. Colonial's underwriter testified that the notes would have been created by the bond administrator in the normal course of approving Strober's request for the performance bond and that the information reflected in the notes was in hand before the underwriter approved the issuance of the bond on February 25, 2009. Among other things, Colonial's notes on this document, which is not in the appendix, indicate that Dobco was the general contractor on the project and also state "Science Hall subcontractor to general contractor." Although the notes might appear to suggest that Colonial had actual knowledge of the true state of Strober's role in the WPU project before Colonial issued its performance bond, we cannot draw that (continued)
4 A-1113-12T4 Colonial's underwriter for his approval. Significantly,
however, Colonial does not request or review the actual contract
prior to issuing a performance bond. Colonial's president
testified at deposition that Colonial's "general policy is not
to request a copy of the contract." When asked why, the
president responded "General – just don't. Never do." When
asked how Colonial "would . . . verify that it is bonding the
correct contract, if it never reviews the contract" prior to
issuing the performance bond, the president responded
"[v]erification, in my opinion, is not necessary. That's why we
don't review the contract." Colonial did not review the Strober
subcontract before issuing the performance bond at issue here.
The parties agree that Strober submitted a bid bond for the
project through Colonial's online system and that Colonial
followed its usual procedures in issuing the performance bond on
February 26, 2009. The bond provides in pertinent part:
That J Strober & Sons, LLC, Ringoes, NJ as Principal, hereinafter called Contractor, and COLONIAL SURETY COMPANY a corporation organized and existing under the laws of the Commonwealth of Pennsylvania, as Surety, hereinafter called Surety, are held and firmly bound unto
(continued) conclusion on this record and do not rely on any such knowledge by Colonial here.
5 A-1113-12T4 William Patterson University, Wayne, NJ 07470
as Obligee, hereinafter called the Owner, in the amount of
Eight Hundred Ninety Thousand Dollars and No Cents Dollars ($890,000), for the payment whereof Contractor and Surety bind themselves, their heirs, executors, administrators, successors and assigns, jointly and severally, firmly by these presents.
WHEREAS, Principal has by written agreement dated November 11, 2008, entered into a contract with the Owner for Science Hall Addition to William Patterson University[.]
In accordance with drawings and specifications prepared by (here insert full name, title and address) Hellmuth, Obata & Kassabaum, 620 Avenue of the Americas, 6th Floor, New York, NY 10011 which contract is by reference made a part hereof, and is hereinafter referred to as the Contract.
NOW THEREFORE, THE CONDITION OF THIS OBLIGATION is such that if Contractor shall promptly and faithfully perform said Contract, then this obligation shall be null and void; otherwise it shall remain in full force and effect.
While the bond bears the correct date of the Dobco/Strober
subcontract, it misidentifies the obligee as WPU, the owner,
instead of Dobco, WPU's general contractor and the party to whom
Strober promised the bond in the November 11, 2008 written
agreement. Strober paid Colonial the full $16,350 premium for
the performance bond.
6 A-1113-12T4 Following Strober's delivery of the bond and accompanying
documents to Dobco, Dobco wrote the following memorandum to
Strober.
We are in receipt of the performance and payment bond # CSC-216974 dated February 26, 2009.
As identified in the AIA A401 Standard Form of Agreement Between Contractor and Subcontractor dated November 11, 2008, we required the performance and payment bond to be issued on a specific form. The performance and payment bonds we received do not comply with that requirement. Please re-issue the performance and payment bond on those forms. A copy of the forms are attached with this memorandum. Please provide the re-issued performance and payment bond no later than March 16, 2009. Thank you for your cooperation.
The parties dispute whether Dobco returned the performance bond
to Strober. Dobco maintains that it retains the bond in its
possession. Strober, which is not a party to this appeal,
maintains that Dobco returned the bond and that it, in turn,
returned the bond to Colonial. Colonial denies that the
original bond was ever returned to it.
Upon receipt of Dobco's memorandum, Strober, using
Colonial's power of attorney and seal, executed performance and
payment bonds on Dobco's forms and telefaxed a copy to Dobco.
Colonial contends this second set of bonds is a nullity as its
agreement with Strober limited Strober to issuing bid bonds on
7 A-1113-12T4 Colonial's behalf. Upon receiving the second set of bonds,
Dobco sent Strober the following memorandum.
We are in receipt of the revised performance and payment bond # CSC-216974 dated February 26, 2009. A copy of which is attached.
The revised performance and payment bond is not acceptable. The performance and payment bond must be revised and issued by Colonial Surety Company with accompanying Surety Disclosure Statement and Certification, General Power of Attorney, and Financial Statement.
Please provide the re-issued performance and payment bond no later than March 18, 2009. A failure to provide this requirement by that day may delay the process of any payments to your company. Thank you for your cooperation.
Strober did not provide revised bonds to Dobco but
delivered material to the project site in April and began work
in May. In early May, Dobco personnel complained to Strober
about its work and noted that Strober had yet to respond to its
request that Colonial reissue the bonds. Strober, in turn,
asked Colonial to reissue the bonds on Dobco's forms. Colonial,
however, had become aware that Strober was experiencing
financial difficulties and instead asked for updated financial
information from Strober.
Strober continued to prod Colonial for revised bonds and
was several times advised by Colonial that "it is in
underwriting," notwithstanding that Colonial had already issued
8 A-1113-12T4 the bond and Strober had already paid for it. The record
contains evidence of several exchanges between Strober and
Colonial regarding the subcontract's requirement that the bonds
be issued on Dobco's form, Colonial's underwriter's discomfort
with Dobco's form and his suggestion that Strober approach Dobco
with other bond forms, the strength of Strober's finances and
whether Colonial was willing to continue to bond the company
going forward.
On July 21, Strober advised Dobco that "[w]e will . . . be
forwarding the bond." On July 24, Strober wrote to the
underwriter at Colonial asking that he "confirm the status of
our William Patterson Bond." Strober wrote that "[w]e received
it, paid for it, but had to send the original back to have it on
another form as per our GC. Please confirm the status." Later
that same day, Strober sent the following email to Dobco,
copying the underwriter at Colonial.
Hossam. I've reached out to our Bond company on several occasions requesting the Wm. Patterson Bond being re-sent on the form you requested. The bond is active but I'm unable to get this on your form as quickly as you would like. As soon as they change the form I will forward to you. I've cc'd the bond co[.] as well. Thanks[.]
Dobco called Colonial and was also advised the bond was active.
On July 27, Strober sent an internal email, copying the
underwriter at Colonial, advising that the underwriter was "not
9 A-1113-12T4 real comfortable with [Dobco's] form," and would review the
contract provision requiring that the bond be issued in that
format.
Dobco subsequently terminated Strober, which thereafter
sought bankruptcy protection. Dobco filed a claim against
Colonial under the bond. Colonial denied the claim on the basis
that Dobco rejected both sets of bonds, both sets of bonds name
WPU as the obligee, and Dobco knew or should have known "that
the Alleged Second Bonds were unauthorized and that there was
never an agreement between Strober and WPU in connection with
the Project." Colonial claimed that "[n]either the Bonds nor
the Alleged Second Bonds are in effect nor subject to claim by
Dobco." Colonial has never revoked the bonds nor returned the
premium to Strober.
After hearing argument on the parties' cross-motions, the
Law Division judge issued a written opinion granting summary
judgment to Colonial dismissing Dobco's claims. Relying on
well-settled law "that a surety is chargeable only according to
the strict terms of its undertaking and its obligation cannot
and should not be extended either by implication or by
construction beyond the confines of its contract," Monmouth
Lumber Co. v. Indem. Ins. Co. of N. Am., 21 N.J. 439, 452
(1956), the judge found that WPU and not Dobco was the
10 A-1113-12T4 designated obligee under both sets of bonds. The judge further
found that Dobco rejected both the first and second set of bonds
and thus no valid contract was formed between Colonial and
Dobco.
The judge rejected Dobco's claim for reformation as the
language of the bond was "clear and not ambiguous" and there was
no evidence of mutual mistake because "[t]he undisputed evidence
establishes that at the time of issuance, Colonial was unaware
that the bonded subcontract agreement was between Strober and
Dobco." The judge acknowledged "Dobco's general argument that
Colonial had a duty to read and approve the underlying contract
mentioned in the bond agreements" but found that "Dobco has not
supported said argument or conclusion with facts or competent
expert opinion that Colonial, the surety in this particular
matter, or any surety as a matter of standard industry practice,
had a duty to do so."4 This appeal followed.
Dobco contends that the trial judge erred in concluding
that Dobco had no rights under the bond or Strober's contract
with Colonial and further erred in concluding on summary
judgment that Dobco rejected the bonds. We review summary
4 The judge also addressed and rejected Dobco's claims under an assignment from WPU and the application of equitable estoppel. As our resolution of the appeal makes it unnecessary to reach these claims, we do not discuss them.
11 A-1113-12T4 judgment using the same standard that governs the trial court.
Henry v. N.J. Dep't of Human Servs., 204 N.J. 320, 330 (2010).
Our first task here is thus to determine whether the motion
judge was correct in determining that Dobco had no rights under
the bond or Strober's surety contract with Colonial. See
Prudential Prop. & Cas. Ins. Co. v. Boylan, 307 N.J. Super. 162,
167 (App. Div.), certif. denied, 154 N.J. 608 (1998). Because a
trial court does not enjoy the advantage in discerning the law
that it does in discerning the facts, a reviewing court owes no
special deference to the "trial court's interpretation of the
law and the legal consequences that flow from established
facts." Manalapan Realty, L.P. v. Twp. Comm. of Manalapan, 140
N.J. 366, 378 (1995).
"'Suretyship is a contractual relation resulting from an
agreement whereby one person, the surety, engages to be
answerable for the debt, default or miscarriage of another, the
principal.'" Eagle Fire Prot. Corp. v. First Indem. of Am. Ins.
Co., 145 N.J. 345, 353 (1996) (quoting Amelco Window Corp. v.
Fed. Ins. Co., 127 N.J. Super. 342, 346 (App. Div. 1974)).
Traditionally, these relationships involve three parties: "an
obligee who is owed a debt or duty; a primary obligor, who is
responsible for the payment of the debt or performance of the
duty; and a secondary obligor, or surety, who agrees to answer
12 A-1113-12T4 for the primary obligor's debt or duty." Cruz-Mendez v.
Isu/Ins. Servs. of San Francisco, 156 N.J. 556, 568 (1999). The
obligee has an enforceable cause of action to recover on the
debt from the surety "if the surety promises in the bond, either
in express words or by reasonable implication, to pay money to
him." Eagle Fire Prot. Servs., supra, 145 N.J. at 353-54.
New Jersey does not have as extensive a body of suretyship
law as do some other states, as evidenced by the parties'
extensive reliance on out-of-state authority. We do, however,
have some well-established principles to guide a court's
interpretation of a surety bond, most notably that when a bond
incorporates a contract by reference, the bond and the contract
must be considered as one integrated document in ascertaining
the meaning of the bond's provisions. Id. at 356-57.
Here, despite the performance bond's explicit reference to
Strober's contract for the Science Hall Addition at WPU dated
November 11, 2008, the Law Division declined to consider the
contract in interpreting the language of the bond. Instead,
relying on the well-established principle "that a surety is
chargeable only according to the strict terms of its undertaking
and its obligation cannot and should not be extended either by
implication or by construction beyond the confines of its
contract," Monmouth Lumber Co., supra, 21 N.J. at 452, the court
13 A-1113-12T4 concluded that Dobco had no rights under the bond because
Colonial's promise was unambiguously to WPU, the stated obligee.
In employing that principle of strict construction in
interpreting the bond, we think the trial court erred. The
Restatement makes plain that the principle relied on by the
trial court, although well known and oft-quoted, applies only
after one has determined the extent of the surety's undertaking.
It is not to be used to interpret the language creating the
surety's obligations under the bond. Instead, the Restatement
holds that contracts creating secondary obligations are to be
interpreted by the same standards that apply to interpretation
of contracts generally. Restatement (Third) of Suretyship and
Guaranty § 14 (Interpretation of the Secondary Obligation —
Generally) (1996).
The Reporters Notes explain the problem. Observing that
"[t]here are few, if any, principles of suretyship law that
cause more confusion than the standards of interpretation of
contracts creating secondary obligations," the Notes continue:
The principle adopted by this section, distinguishing interpretation of the contract creating the secondary obligation from the application of substantive principles of suretyship law to that contract, has been stated as follows:
"However, the rule of strictissimi juris requires only that, after the meaning of
14 A-1113-12T4 the contract of guarantee has been determined according to ordinary principles of contract construction, the obligations undertaken by the guarantor are to be strictly applied. . . . Thus, while '[t]he liability of a surety cannot be extended beyond the plain and explicit language of the contract . . . a surety is not entitled to any particular tenderness in the interpretation of the language of the contract.'" Banco Portugues do Atlantico v. Asland, S.A., 745 F. Supp. 962, 967-68 (S.D.N.Y. 1990) (quoting 63 N.Y. Jur. 2d Guaranty and Suretyship[] § 89 (1987)) (citations omitted).
[Ibid. (alteration in original).]
A close reading of our own law reveals it in accord with
the Restatement. See e.g., Eagle Fire Prot. Servs., supra, 145
N.J. at 356 (noting the rule of strict construction "has been
modified, if the language in the construction bond is ambiguous"
(citing V. Petrillo & Son, Inc. v. Am. Constr. Co., 148 N.J.
Super. 1, 4-5 (App. Div.), certif. denied, 75 N.J. 4 (1977))).
The Restatement approach is further reflected in the Court's
admonition that when the bond incorporates the contract by
reference, "the bond and the contract must be considered as one
integrated document." Id. at 356. As such, the bond
"should be construed in connection with, and in the light of, [the] contract with which it was executed or the performance of which it secures, especially where the bond refers to the contract and makes it part of the bond. Thus, the bond, the contract, and the
15 A-1113-12T4 specifications constitute an integrated obligation, and are to be read together."
[Id. at 357 (quoting 17 Am. Jur. 2d Contractors' Bonds § 7 (1990).]
Under our ordinary rules of construction, contract
provisions are to be "read as a whole, without artificial
emphasis on one section, with a consequent disregard for
others." Borough of Princeton v. Bd. of Chosen Freeholders of
the Cnty. of Mercer, 333 N.J. Super. 310, 325 (App. Div. 2000),
aff'd, 169 N.J. 135 (2001). "Literalism must give way to
context." Ibid. Applying those standards here, it is
inescapable that the bond was intended to secure Strober's
obligations under its November 11, 2008 contract with Dobco,
notwithstanding the bond's identification of WPU as the obligee.
There is no other contract than the one Strober had with Dobco,
and Strober owed no obligation of any sort to WPU. We may not
ignore the general design of the agreement in ascertaining the
sense of particular terms, even one so central as the identity
of the obligee. See Krosnowski v. Krosnowski, 22 N.J. 376, 387
(1956).
Having determined that Colonial bound itself to answer for
Strober's performance under the subcontract, we are led
ineluctably to conclude that Colonial agreed to do so in the
manner specified therein, that is, on Dobco's own form. The
16 A-1113-12T4 Dobco/Strober subcontract makes absolutely clear that Strober
agreed to provide Dobco with a performance bond in the sum of
$890,000 in the form annexed to the agreement. The hallmark of
a contract of suretyship is the surety's direct and primary
undertaking to answer for the performance of the principal.
Cruz-Mendez, supra, 156 N.J. at 569 (noting "the unique
characteristics of suretyship remain intact in New Jersey,
Newark Fin. Corp. v. Acocella, 115 N.J.L. 388 (Sup. Ct. 1935)
(explaining that surety undertakes 'direct and primary'
obligation, as distinguished from guarantor, whose obligation is
'secondary' and 'collateral')").
Here, Strober undertook to produce a performance bond in a
required sum on a particular form. When Colonial agreed to bond
that performance, it undertook the obligation to do so in the
form required by the contract. That Colonial chose not to
review the contract it bonded cannot relieve it of obligations
voluntarily undertaken. It has long been the law of this State
that "[t]he surety is chargeable with knowledge of the contents
of the contract it undertook to guarantee." Jersey City Water
Co. v. Metropolitan Const. Co., 76 N.J.L. 419, 421 (Sup. Ct.
1908). The law of other jurisdictions is in accord. See e.g.,
Western N. Y. Life Ins. Co. v Clinton, 66 N.Y. 326, 331-32
(1876) ("It is the duty of the sureties to look out for
17 A-1113-12T4 themselves and ascertain the nature of the obligation embraced
in the undertaking, and any other rule would not only work
serious inconvenience, but render securities of this character
of but little, if of any, value."); see also Rachman Bag Co. v.
Liberty Mut. Ins. Co., 46 F.3d 230, 235 (2d Cir. 1995) (decided
under New York law). Accordingly, we disagree with the Law
Division that Dobco required expert testimony to establish the
existence of a duty on the part of the surety to inform itself
of its obligations under the agreement incorporated in its bond.
Because we conclude that by entering into its contract with
Strober and accepting Strober's premium payment, Colonial
voluntarily obligated itself to issue its bond in the form
required by the Dobco/Strober subcontract, we reject the Law
Division's finding that reformation was unavailable here.
Reformation based on mutual mistake requires clear and
convincing evidence that the parties' minds have met in a prior
existing agreement that their written agreement fails to
express. Bonnco Petrol, Inc. v. Epstein, 115 N.J. 599, 608
(1989). The Court has explained "that in the context of
situations where a writing inaccurately reflects the parties'
agreement or intentions, 'mutual mistake requires that both
parties are in agreement at the time they attempt to reduce
their understanding to writing, and the writing fails to express
18 A-1113-12T4 that understanding correctly.'" Id. at 609 (quoting St. Pius X
House of Retreats v. The Diocese of Camden, 88 N.J. 571, 579
(1982)).
Here, there can be no doubt that Strober and Colonial both
intended that Colonial would bond Strober's obligations under
its November 11, 2008 contract to perform the roofing work at
WPU because the bond Colonial issued references an agreement for
such work dated November 11, 2008, and there is no other
contract to which that reference could apply. Colonial's
failure to correctly identify the obligee and to issue its bond
on the form incorporated in the Dobco/Strober subcontract did
not result from any failure of a meeting of the minds between
Colonial and Strober but solely from Colonial's election not to
review the contract it had agreed to bond. As our law charges
the surety with knowledge of the Dobco/Strober subcontract,
reformation is the appropriate remedy in these circumstances.
Finally, we reject Colonial's argument that it was relieved
of its obligation to Strober by Dobco's supposed rejection of
the non-conforming bond5 Strober tendered to Dobco. While
5 We refer here to the Colonial bond. Our resolution of the appeal makes it unnecessary for us to consider the parties' arguments concerning the second Strober "bond," only a copy of which was ever sent to Dobco, and without the surety disclosure statement and certification, general power of attorney and financial disclosure.
19 A-1113-12T4 Colonial argues that the law requires acceptance of the bond by
the obligee before the surety is chargeable, no New Jersey case
says so, although that appears generally to be the law
elsewhere, at least with regard to the older cases.6 See, e.g.,
Rachman Bag Co., supra, 46 F.3d at 238 (2d Cir. 1995)
(discussing traditional requirements of delivery and acceptance
under New York law).
Although we have found no New Jersey authority on the
necessity of acceptance of a surety bond by the obligee, the few
New Jersey cases treating delivery in the context of a
suretyship make clear that in this area, as in others, our law
does not exalt form over substance. See, e.g., Real Estate-Land
Title & Trust Co. v. Stout, 117 N.J. Eq. 37, 41-43 (1934)
(finding no delivery where delivery made in absence of all
required signatures); State Bank at Trenton v. Evans, 15 N.J.L.
155, 161 (Sup. Ct. 1835) (finding bond inoperative in the hands
6 More modern authority suggests, at least in the area of construction contract suretyship where custom and industry practice is well established, that the surety's communication to the obligee of its intent to be bound is sufficient to bind the surety before execution and delivery of the bonds in final form. See Turner Construction Co. v. First Indemnity of America Insurance Co., 829 F. Supp. 752, 760-61 (E.D. Pa. 1993) ("Pennsylvania statutory law confirms the conclusion that [the surety's] letter of intent on September 29, 1990 as a matter of industry practice and [the surety's] express words constituted a binding and enforceable surety contract even before execution and delivery of the bonds in their final form").
20 A-1113-12T4 of the obligee, by whatever means he got possession, until
condition of its delivery is performed); Folly v. Vantuyl, 9
N.J.L. 153, 158-59 (Sup. Ct. 1827) (noting "[t]hat there is no
precise or set form in which a delivery must be made" and
finding constructive delivery to obligee with words "here is
your bond, what shall I do with it"). The common law
requirement of delivery to the obligee was based on solicitude
for guarantors and accommodation parties, many of whom formerly
were individuals not receiving any remuneration for their
promises. See, e.g., Peoples Nat'l Bank of N.J. v. Fowler, 73
N.J. 88, 98-100 (strictly construing surety's obligation where
surety uncompensated), cert. denied, 434 U.S. 858, 98 S. Ct.
182, 54 L. Ed. 2d 131 (1977); Bank of Tarboro v. Fidelity &
Deposit Co., 38 S.E. 908 (N.C. 1901) (distinguishing between
private and paid sureties). The older cases hold that notice of
acceptance to the surety was required in the case of non-
absolute obligations because the surety would not otherwise know
whether it was obligated on its offer, Acme Mfg. Co. v. Reed, 47
A. 205, 206-08 (Pa. 1900) ("a party giving a letter of guaranty
has a right to know whether the person to whom it is addressed
means to hold him ultimately responsible, inasmuch as his own
caution and vigilance may, in a great measure, be regulated by
his knowledge of the fact"), or whether its form was acceptable
21 A-1113-12T4 to the obligee, see Fidelity & Deposit Co. v. West Point
Construction Co., 344 S.E.2d 268, 269-70 (Ga. Ct. App. 1986)
(discussing contract requirement that performance bond be
provided in form acceptable to the contractor).
Because no New Jersey case requires acceptance by the
obligee before the surety can be charged, we are not called to
consider whether such precedent, founded in a different era in
consideration of a variety of instruments many of which are now
obsolete, should apply to this performance bond issued for
consideration by an insurance company specializing in contract
surety. Instead, our focus is on the substance of the
Dobco/Strober subcontract Colonial voluntarily undertook to
bond.
Dobco was entitled by the terms of that agreement to a
performance bond in the sum of $890,000 on the specific form
incorporated therein. By contracting with Strober to bond
Strober's obligations under its subcontract with Dobco, Colonial
obligated itself to issue the performance bond on Dobco's form.
Colonial is in the business of writing surety bonds, and it
accepted a premium from Strober for this bond, which it has
never returned. Under these circumstances, we have no
hesitation in rejecting Colonial's argument that Dobco's
unwillingness to accept less than what it contracted for, and
22 A-1113-12T4 Colonial promised, relieved Colonial of its contractual
obligation to Dobco.
Reversed and remanded for further proceedings in conformity
with this opinion. We do not retain jurisdiction.