Continental Bronze Co. v. Salvo & Armstrong Steel Co.

397 N.E.2d 1143, 8 Mass. App. Ct. 799, 1979 Mass. App. LEXIS 1074
CourtMassachusetts Appeals Court
DecidedDecember 14, 1979
StatusPublished
Cited by10 cases

This text of 397 N.E.2d 1143 (Continental Bronze Co. v. Salvo & Armstrong Steel Co.) is published on Counsel Stack Legal Research, covering Massachusetts Appeals Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Continental Bronze Co. v. Salvo & Armstrong Steel Co., 397 N.E.2d 1143, 8 Mass. App. Ct. 799, 1979 Mass. App. LEXIS 1074 (Mass. Ct. App. 1979).

Opinion

Greaney, J.

Continental Bronze Company, Inc. (Continental), supplied labor and materials to Salvo & Armstrong Steel Company, Inc. (Salvo), in connection with the latter’s subcontract to provide and install metalwork in a publicly funded project constructed for the New Bedford Housing Authority (Authority). Salvo failed to *800 pay Continental, thereby precipitating this suit for labor and materials by Continental against Salvo and its surety, the American Insurance Company (American). It appears that Continental, prior to commencing suit, lost its rights against the project’s general contractor, F. L. Collins & Sons, Inc. (Collins), and Collins’ surety, Travelers Insurance Company, on the bond posted in conformance with G. L. c. 149, § 29. Those rights had been lost as a result of Continental’s tardiness in complying with the notice provisions set forth in the third paragraph of § 29. 2 Pleadings and submissions (bids, contracts, the bond and affidavits) evolved into cross motions for summary judgment. Mass.R.Civ.P. 56(a)(b), 365 Mass. 824 (1975). The judge denied the defendants’ motions, allowed the plaintiff’s, and permitted Continental a recovery of $7,390 against Salvo and American. In so doing the judge found that American’s bond was written for Salvo to benefit Collins, but that Continental could reach the bond as a third-party beneficiary thereof. Despite the bond’s adherence to the provisions of G. L. c. 149, § 44H, he concluded that certain language in the bond was ambiguous and ruled that the ambiguity should be resolved in favor of permitting Continental a recovery on the bond. Although the appeal must be dismissed for lack of entry of a judgment (Mass.R.Civ.P. 58[a], as amended, 371 Mass. 908 [1977], Levy v. Bendetson, 6 Mass. App. Ct. 558, 561 [1978]), because the issues have been fully briefed we express our views that the recovery permitted Continental against Salvo was correct, 3 but that the recovery permitted against American was erroneous. This *801 will pave the way for the entry of a judgment consistent with this opinion.

1. The process of bidding and bonding on this public project followed the pattern established for such procedures in G. L. c. 149, § 29, 4 and in §§ 44A through 44L. Collins, the general contractor, obtained the bond required by § 29 of c. 149 in favor of the authority to secure the payment by Collins’ subcontractors for labor performed or furnished and materials used or employed in the projects. Because of the exposure of Collins and its surety under § 29 of c. 149 to parties who contracted with the various subcontractors, Collins requested (as expressly authorized by § 44H) that its principal subcontractors, including Salvo, be bonded. Salvo’s bond, written by American, contained the promises set forth in the margin 5 in language which tracked virtually word for word the requirements for this type of bond spelled out in the third paragraph of G. L. c. 149, § 44H.

American asserts correctly that it has written a statutory performance and payment bond pursuant to G. L. c. 149, § 44H, designed solely to benefit Collins. The bond’s promises are twofold: (1) to secure to Collins the performance of Salvo’s metalwork subcontract; and (2) to indemnify Collins in the event Collins became obligated under G. L. c. 149, § 29, to pay any of Salvo’s subcon *802 tractors. These promises must be construed in view of the third paragraph of G. L. c. 149, § 44H, inserted by St. 1960, c. 771, § 6, which defines the scope and contents of a subcontractor’s bond and which expressly states that “[a] performance and payment bond furnished by the subcontractor at the request of a general contractor . . . shall be for the benefit of the general contractor . . . [emphasis supplied]. ” This language and the insertion of the present third paragraph into § 44H four years after the insertion of § 44H itself (by St. 1956, c. 679, § 1) and three years after the rewriting of c. 149, § 29 (by St. 1957, c. 682, § 1), which broadened the range of remedies available to parties dealing with subcontractors against the general contractor and its surety, 6 lead to the conclusion that a bond written in strict conformity with the terms of § 44H is for the benefit of the general contractor alone. See generally Claycraft Co. v. John Bowen Co., 287 Mass. 255, 257 (1934); Waite Hardware Co. v.Ardini &Pfau, Inc., 339 Mass. 634, 637-638 (1959); James D. Shea Co. v. Perini Corp., 2 Mass. App. Ct. 912 (1975), which limit the range of obligees and beneficiaries of payment and performance bonds to those parties enumerated either in the bond or in the statute. See also Scaduto v. Orlando, 340 F.2d 293, 300 (2d Cir.), cert, denied, 380 U.S. 978 (1965) (applying Massachusetts, law). This conclusion is also buttressed by a comparison of the language in § 44H tying the benefits of a bond written thereunder to the general contractor with the language in § 29A of c. 149, 7 as amended by St. 1972, c. 399, *803 which permits a third party such as Continental in a private construction contract to claim the benefits of a subcontractor’s bond where the terms of the bond so permit. The absence of anything comparable to § 29A with reference to the interrelationship of § 29 and § 44H bonds further suggests that the Legislature did not intend direct suits by sub-subcontractors on subcontractor’s bonds. See and compare Powers Regulator Co. v. United States Fid. and Guar. Co., 7 Mass. App. Ct. 913 (1979) (where on a private project, a subcontractor’s bond, containing language unnecessary to the general contractor’s protection was held under G. L. c. 149, § 29A, to have promised payment to a person supplying labor and materials in the prosecution of the work provided for in the contract), with Mosaic Tile Co. v. Rusco Prod, of Massachusetts, Inc., 350 Mass. 433, 437 (1966) (where a supplier of materials to a subcontractor was denied recovery against the subcontractor’s bond because the benefit to claimants under § 29 “covers only bonds given by the general contractor and does not affect a payment security bond from a subcontractor to the general contractor”). The Mosaic Tile case is particularly instructive because the claim made and rejected in that case under § 29 is similar to the claim made by Continental under § 44H in this action. In view of the foregoing discussion and the predominant legislative facts, we cannot accept Continental’s argument that the bond which secured to Collins the performance of Salvo’s subcontract was meant to give Continental the right to sue American if it was not paid.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
397 N.E.2d 1143, 8 Mass. App. Ct. 799, 1979 Mass. App. LEXIS 1074, Counsel Stack Legal Research, https://law.counselstack.com/opinion/continental-bronze-co-v-salvo-armstrong-steel-co-massappct-1979.