Barboza v. Aetna Casualty & Surety Co.

465 N.E.2d 290, 18 Mass. App. Ct. 323
CourtMassachusetts Appeals Court
DecidedJune 29, 1984
StatusPublished
Cited by5 cases

This text of 465 N.E.2d 290 (Barboza v. Aetna Casualty & Surety Co.) is published on Counsel Stack Legal Research, covering Massachusetts Appeals Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Barboza v. Aetna Casualty & Surety Co., 465 N.E.2d 290, 18 Mass. App. Ct. 323 (Mass. Ct. App. 1984).

Opinion

Kass, J.

In order to prevail, the plaintiffs, doing business as Barboza Brothers (Barboza), suppliers of gravel, must establish that their agreement with the general contractor embraced deliveries made — but not paid for — under a contract earlier made with a subcontractor and that the earlier agreement with the subcontractor had ceased to have legal significance for purposes of securing benefits of a payment bond obtained in accordance with G. L. c. 149, § 29.

*324 The governing facts, developed by pleadings, affidavits, and a deposition filed in connection with a motion for summary judgment, follow. The Fairhaven Housing Authority engaged Liberty Contractors Co., Inc. (Liberty), as general contractor to build housing for elderly persons. Liberty let a subcontract to E. G. Mondor Construction Corp. (Mondor) for excavation and site work. Mondor agreed orally with Barboza for the delivery of gravel to the job site.

From February 19, 1974, through June 13, 1974, Barboza delivered gravel to the project site on an “as needed” basis and billed the deliveries by separate invoices to Mondor. As of June 13, 1974, Mondor had run up unpaid bills of $13,382.60 with Barboza, and Joseph Barboza, one of the plaintiffs, informed Mondor it would ship no more gravel to the job unless Barboza should receive payment in full for material already delivered. Joseph Barboza subsequently told Liberty that it was suspending gravel deliveries and why it was doing so. A responsible officer of Liberty told Joseph Barboza that if Bar-boza should resume shipments to the project site, Barboza would be paid by Liberty for the prior deliveries 2 to Mondor. As for future deliveries, they were to be billed directly to Liberty.

Barboza resumed deliveries on July 1, 1974, again on an “as needed” basis, and rendered bills to Liberty. The price changed. Barboza, which had charged Mondor $2.10 per cubic yard, billed Liberty, without notice of an increase, at $2.50 per cubic yard, a circumstance which later may have dampened Liberty’s zeal in helping Barboza to recover the Mondor arrear-age. Liberty paid in full for the gravel shipped for its account, the last shipment having been made on September 18, 1974. Neither it nor Mondor paid the pre-July 1st amount which Mondor owed, nor did Barboza send a bill to Liberty for that *325 amount. Barboza made an oral demand upon Liberty for payment of the Mondor arrearage on about October 1, 1974. On December 2, 1974, Barboza mailed a written notice of default, purportedly “in accordance with the requirements of [the payment] bond” furnished by Liberty and written by Aetna Casualty and Surety Company.

About six months later, on June 12, 1975, Barboza filed an action in the Superior Court against Liberty and Aetna. 3 Both made motions for summary judgment. Liberty’s was denied, but Aetna’s was allowed and, pursuant to a determination under Mass.R.Civ.P. 54(b), 365 Mass. 821 (1974), that there was no just reason for delay, a judgment entered dismissing the action as to Aetna. Among the defendants, therefore, only Aetna is involved in this appeal. 4

Under G. L. c. 149, § 29 (as amended through St. 1972, c. 774, § 5), a claimant against the payment bond required by that statute (see the first paragraph of § 29), if the claim is based on a relationship with a subcontractor, must give a written notice of claim to the general contractor “within sixty-five days after the day on which the claimant last performed the labor or furnished . . . materials ...” (see the third paragraph of § 29). As to its contract with the subcontractor, Mon-dor, therefore, Barboza must have given the statutory notice no later than August 17, 1974. See, e.g., Massachusetts Gas & Elec. Light Supply Co. v. Rugo Constr. Co., 321 Mass. 20, 23 (1947), applying an earlier version of the same statute. See also Continental Bronze Co. v. Salvo & Armstrong Steel Co., 8 Mass. App. Ct. 799, 800 & n.2 (1979). No written notice of any kind respecting gravel shipments was given until December 2, 1974.

Barboza recognizes it cannot have the benefit of the payment bond on the basis of the subcontract with Mondor and stakes *326 its claim instead against the general contractor, Liberty, and upon the second paragraph of § 29. Under that paragraph a claimant “having a contractual relationship with the contractor principal furnishing the bond [i.e., the general contractor] . . . shall have the right to enforce [its] claim” by filing a complaint “within one year after the day on which [the] claimant last . . . furnished the . . . materials . . . included in the claim.” G. L. c. 149, § 29. All of the material included in Barboza’s claim relates to gravel shipped for Mondor’s account. To press that claim against Liberty, Barboza theorizes that its agreement with Liberty changed the character of Barboza’s contract with Mondor, the subcontractor, into one continuous contract with Liberty, the general contractor. The Mondor subcontract, under the plaintiffs’ approach, is swallowed up in the contract with Liberty.

So to obliterate the Barboza-Mondor agreement requires us to overlook the following aspects of the record: (a) one set of invoices — for the deliveries through June 13, 1974 — was addressed to Mondor, another quite separate set, addressed to Liberty, covered the post-July 1st deliveries; (b) the Liberty set of invoices contained no charges for gravel previously delivered for Mondor’s account; (c) the price per cubic yard charged to Liberty was different (by twenty percent) from the price charged to Mondor. These are indicia of separateness as cogent as those at play in D & P Equip. Corp. v. Harvey Constr. Co., 5 Mass. App. Ct. 851 (1977). There, D & P, a supplier of equipment and labor to a subcontractor, Hawthorne, on an “as needed” basis, arranged to furnish the equipment and services, “as needed,” to the general contractor, Harvey Construction Co., when Hawthorne failed. D & P’s affidavits on summary judgment were to the effect that Harvey “took over” D & P’s contract with Hawthorne. In the D & P case the supplier gave timely notice to the general contractor of its claim under G. L. c. 149, § 29, third par., but did not, as required by the statute, file an action in court within one year after the day on which it last provided materials or services to the subcontractor. Instead it billed the general contractor directly — at a different price — for work and materials furnished after *327 termination with the subcontractor, Hawthorne, and then brought an action on the bond in the Superior Court within one year of finishing with the general contractor on the premise that the contractual relationship with the subcontractor and the general contractor was to be regarded as a continuous one. The action on the subcontract in the D & P case should have been brought by September 19, 1975, but was not filed until November, 1975.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

N-Tek Construction Services, Inc. v. Hartford Fire Insurance Co.
47 N.E.3d 435 (Massachusetts Appeals Court, 2016)
C&I Steel, LLC v. Peabody Construction Co.
22 Mass. L. Rptr. 402 (Massachusetts Superior Court, 2007)
Venus Drywall, Inc. v. Kullman Industries, Inc.
5 Mass. L. Rptr. 70 (Massachusetts Superior Court, 1996)
Bastianelli v. National Union Fire Insurance
631 N.E.2d 566 (Massachusetts Appeals Court, 1994)
Cinder Products Corp. v. Schena Construction Co.
492 N.E.2d 744 (Massachusetts Appeals Court, 1986)

Cite This Page — Counsel Stack

Bluebook (online)
465 N.E.2d 290, 18 Mass. App. Ct. 323, Counsel Stack Legal Research, https://law.counselstack.com/opinion/barboza-v-aetna-casualty-surety-co-massappct-1984.