Floors, Inc. v. B. G. Danis of New England, Inc.

401 N.E.2d 839, 380 Mass. 91, 1980 Mass. LEXIS 1050
CourtMassachusetts Supreme Judicial Court
DecidedMarch 6, 1980
StatusPublished
Cited by45 cases

This text of 401 N.E.2d 839 (Floors, Inc. v. B. G. Danis of New England, Inc.) is published on Counsel Stack Legal Research, covering Massachusetts Supreme Judicial Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Floors, Inc. v. B. G. Danis of New England, Inc., 401 N.E.2d 839, 380 Mass. 91, 1980 Mass. LEXIS 1050 (Mass. 1980).

Opinion

Quirico, J.

This case presents two questions: (1) whether a suit on a contractor’s bond under G. L. c. 149, § 29 (as amended through St. 1972, c. 774, § 5), may be used as a vehicle to confirm an arbitration award handed down pursuant to G. L. c. 251; and (2) whether in such a suit a subcontractor may recover legal fees incurred in arbitration proceedings which resolved the underlying contract dispute in his favor. We hold that (1) an arbitration award may be *92 confirmed in the context of a preexisting action between the parties, and that (2) attorneys’ fees may not be recovered for arbitration proceedings absent such an agreement between the parties.

The appellee, Floors, Incorporated (Floors), is a subcontractor which entered into two subcontracts with a general contractor, appellant B. G. Danis of New England, Inc. (Danis), one on December 27, 1972, to provide resilient flooring, and another on August 7, 1973, to provide special flooring and carpeting. Both contracts were in connection with Danis’s general contract to build a public high school in Salem, and each included an “all disputes” arbitration clause, set forth below. 2 Floors furnished labor and materials under the contracts, plus certain “extras” agreed to by the parties. Floors finished work on the first contract in November, 1975, and on the second contract in March, 1976, and demanded payment. Danis paid part of the price requested as to each contract, but refused to pay the balance. On May 14, 1976, Floors demanded arbitration under the contracts and on May 28, 1976, it filed an action in Superior Court seeking relief under G. L. c. 149, § 29, on a public construction bond which Danis had provided pursuant to that statute and on which appellant Seaboard Surety Company (Seaboard) was surety. The complaint stated that it was “filed as a provisional remedy under c. 149, § 29 and is without prejudice to, nor waiver of, the arbitration proceeding now pending,” and further stated that “ [tjhis action is to be stayed pending the arbitration award.” Danis and Seaboard (defendants) answered, alleging that Floors had failed to complete certain aspects of the contracts, and stating that they and Floors were in agreement that the ac *93 tion should be stayed pending arbitration. No other motion for a stay was filed, but the parties proceeded to arbitration.

On February 25, 1977, the arbitrators awarded $21,000, including interest, to Floors, and denied Danis’s counterclaims relative to extra work due under the contract. Floors then filed in the pending c. 149, § 29, action a motion to confirm the arbitration award and a motion for attorneys’ fees, as well as a motion for summary judgment against the surety. The defendants Danis and Seaboard filed objections to these motions and filed a motion to dismiss the action because an award had been rendered. After a hearing a judge of the Superior Court confirmed the arbitration award of $21,000 and, after holding a further hearing, he awarded an additional $6,300 in attorneys’ fees to Floors. The defendants appealed to the Appeals Court, which upheld the hearing judge in his confirmation of the award, but reversed the award of attorneys’ fees to the extent that it included payment for services rendered in the arbitration proceedings. The Appeals Court held that “so much of the legal fees as were attributable to the arbitration should not have been allowed.” Floors, Inc. v. B. G. Danis of New England, Inc., 7 Mass. App. Ct. 356, 358 (1979). We granted Floors’ petition for further appellate review. For the reasons stated below, we agree with the result reached by the Appeals Court.

General Laws c. 149, § 29, requires contractors in public construction contracts to give performance and payment bonds to public authorities, and permits actions on such bonds by subcontractors and materialmen. As amended in 1972, the statute provides in part that “[a] decree in favor of any claimant under this section shall include reasonable legal fees,” and sets standards for the determination of their amount. St. 1972, c. 774, § 5. Chapter 774 of the Acts of 1972 is entitled, “An Act expediting payments to general contractors and to subcontractors and improving the flow of funds in the construction industry.” We had previously held that G. L. c. 149, § 29, “is a remedial statute which should be construed broadly to achieve the purpose of af *94 fording security to subcontractors and materialmen on public works.” Manganaro Drywall, Inc. v. White Constr. Co., 372 Mass. 661, 664 (1977), citing LaBonte v. White Constr. Co., 363 Mass. 41, 45 (1973). American Air Filter Co. v. Innamorati Bros., 358 Mass. 146, 148-151 (1970).

Commercial arbitration is governed by G. L. c. 251, which, as totally revised by St. 1960, c. 374, is substantially similar to the Uniform Arbitration Act. 3 In any event, the differences between G. L. c. 251 and the Uniform Arbitration Act do not affect the result in this decision. Section 10 of c. 251 provides in relevant part: “Unless otherwise [agreed], the arbitrators’ expenses and fees, together with other expenses, not including counsel fees, incurred in the conduct of the arbitration, shall be paid as provided in the award” (emphasis supplied). Section 11 provides for applications to confirm an award. Sections 12 and 13 provide for applications to vacate, modify, or correct an arbitration award, on certain specified grounds. 4 Section 15 states in relevant part that “an application to the court under this chapter shall be by motion and shall be heard in the manner and upon the notice provided by law or rule of court for the making and hearing of motions. . . . [N]otice of an initial *95 application for an order [confirming, modifying, correcting, or vacating an award] shall be served in the manner provided by law for the service of an original writ of summons.”

1. The defendants argue that §§11 and 15 require commencement of a new proceeding to confirm an arbitration award, and that to allow confirmation to occur in the context of a proceeding previously filed does violence to the statutory scheme. Floors contends that the service of process attendant to its original c. 149, § 29, complaint was sufficient “notice of an initial application for an order,” since it had previously served on Danis a demand for arbitration, and a request for a stay of the action pending arbitration was included in the complaint. It argues that therefore it was proper for it to file a motion to confirm within that action. The defendants maintain that because the action was filed before the award was made, the earlier service of process cannot satisfy the statute. They do not allege, however, that they were inadequately notified of Floors’ motion to confirm the arbitration award, or of its other motions.

The apparent purpose of G. L. c. 251, § 15, is to ensure that parties have adequate notice and opportunity to be heard in court proceedings following an arbitration award.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Central Ceilings, Inc. v. Suffolk Construction Co., Inc.
101 N.E.3d 937 (Massachusetts Appeals Court, 2018)
Katz, Nannis & Solomon, P.C. v. Levine
46 N.E.3d 541 (Massachusetts Supreme Judicial Court, 2016)
Beacon Towers Condominium Trust v. Alex
42 N.E.3d 1144 (Massachusetts Supreme Judicial Court, 2016)
Vale v. Valchuis
30 N.E.3d 832 (Massachusetts Supreme Judicial Court, 2015)
City Rentals, LLC v. BBC Co.
947 N.E.2d 1103 (Massachusetts Appeals Court, 2011)
Elwood Insurance v. OneBeacon America Insurance
28 Mass. L. Rptr. 81 (Massachusetts Superior Court, 2011)
North Shore Construction & Development, Inc. v. Lee
28 Mass. L. Rptr. 234 (Massachusetts Superior Court, 2010)
Maverick Construction Management Services, Inc. v. Hodgson
26 Mass. L. Rptr. 369 (Massachusetts Superior Court, 2009)
Dukas v. Yiu
2009 Mass. App. Div. 234 (Mass. Dist. Ct., App. Div., 2009)
Cybulski v. Vaiani
914 N.E.2d 354 (Massachusetts Appeals Court, 2009)
Janney Montgomery Scott LLC v. Tobin
571 F.3d 162 (First Circuit, 2009)
Sun Fire Protection & Engineering, Inc. v. D.F. Pray, Inc.
899 N.E.2d 114 (Massachusetts Appeals Court, 2009)
C & I Steel, LLC v. Travelers Casualty & Surety Co. of America
876 N.E.2d 442 (Massachusetts Appeals Court, 2007)
Travelers Casualty & Surety Co. of America, Inc. v. Long Bay Management Co.
18 Mass. L. Rptr. 284 (Massachusetts Superior Court, 2004)
Driver v. SI CORP.
80 P.3d 1024 (Idaho Supreme Court, 2003)
Mongeon v. Arbella Mutual Insurance
16 Mass. L. Rptr. 93 (Massachusetts Superior Court, 2003)
Murphy v. National Union Fire Insurance
438 Mass. 529 (Massachusetts Supreme Judicial Court, 2003)
LaRoche v. Flynn
771 N.E.2d 792 (Massachusetts Appeals Court, 2002)
Gargano & Associates, P.C. v. Swider
770 N.E.2d 506 (Massachusetts Appeals Court, 2002)

Cite This Page — Counsel Stack

Bluebook (online)
401 N.E.2d 839, 380 Mass. 91, 1980 Mass. LEXIS 1050, Counsel Stack Legal Research, https://law.counselstack.com/opinion/floors-inc-v-b-g-danis-of-new-england-inc-mass-1980.