This text of 339 So. 2d 689 (Beach Resorts Intern. v. Clarmac Marine Const.) is published on Counsel Stack Legal Research, covering District Court of Appeal of Florida primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Beach Resorts Intern. v. Clarmac Marine Const., 339 So. 2d 689, 1976 Fla. App. LEXIS 15647 (Fla. Ct. App. 1976).

Opinion

339 So.2d 689 (1976)

BEACH RESORTS INTERNATIONAL, INC., Appellant,
v.
CLARMAC MARINE CONSTRUCTION COMPANY, Appellee.

No. 75-1381.

District Court of Appeal of Florida, Second District.

November 19, 1976.

Adrian S. Bacon, Bacon & Hanley, St. Petersburg, for appellant.

William C. Ballard, Baynard, Lang & Ballard, St. Petersburg, for appellee.

HOBSON, Acting Chief Judge.

This is an appeal from a final judgment entered in favor of the plaintiff/appellee in a proceeding initiated as an action to foreclose a statutory mechanic's lien. Beach Resorts, defendant and appellant herein, specifically assails that portion of the final judgment awarding the plaintiff, Clarmac, attorney fees pursuant to the mechanic's lien statute, Section 713.29, Florida Statutes (1975). We agree and reverse.

In January 1974, Clarmac, the contractor, had completed a ramp and overpass built under a direct contract with the property owner, Beach Resorts. The contract included *690 the American Institute of Architects' general conditions which incorporated an arbitration clause. A dispute arose when Beach Resorts refused to pay the contract balance of $16,046.10, claiming defective performance. Clarmac filed a claim of lien against Beach Resorts and Beach Resorts transferred the lien to security deposit with the clerk of the court. Clarmac filed its action against Beach Resorts to foreclose its lien transferred to security. Beach Resorts answered, and raised as an affirmative defense the mandatory requirement in the contract for arbitration. Beach Resorts also counterclaimed for $50,000 for various damages arising out of Clarmac's performance of the contract.

Beach Resorts also filed an application for order directing parties to proceed with arbitration. The trial court did not enter an order on the application, but Clarmac voluntarily proceeded to arbitration and in its demand claimed $16,046.10 plus interest. The arbitration was held and the arbitrator awarded Clarmac the sum of $10,682.60, with the parties bearing the administrative fees and expenses equally. Later the arbitrator ordered Clarmac to pay Beach Resorts $242.50 for that portion of the fees previously advanced by Beach Resorts to the Arbitration Association.

On February 5, 1975, Clarmac filed a motion for award of attorney fees and for entry of judgment upon arbitration award and at the same time noticed the motion for hearing before the court on March 3, 1975. In support of its motion, Clarmac submitted the affidavit of an attorney, John C. Dew, who stated that in his opinion a reasonable fee for all work done by Clarmac's attorney, including the arbitration proceedings, would be $3,500. At the hearing on March 3 Beach Resorts delivered a cashier's check to Clarmac in the amount of the award, and filed a notice of payment of arbitrator's award and motion whereby the court was notified that Beach Resorts had paid the award in full and the court was requested to declare the claim of lien void and deny Clarmac's motion for attorney fees. Clarmac refused to accept the tendered check as payment in full of all Beach Resort's obligations and the court took the matter under advisement, requesting memorandums on the subject.

On March 18, Clarmac accepted the check. On August 26, 1975, the court entered its judgment, including therein the full amount of the arbitration award, and an award of attorney fees in the amount of $2,250 and costs to Clarmac. Thereafter Clarmac filed a partial satisfaction of judgment, recognizing payment of the full amount of the arbitrator's award.

The sole issue for our determination is whether the trial court erred in awarding Clarmac attorney fees in its final judgment confirming the award of the arbitrator. Resolution of this close question necessarily requires an analysis of the Florida Arbitration Code, Sections 682.01 et seq., Florida Statutes (1975) as it relates to the operation of Florida Mechanic's Lien Law, Sections 713.01-713.36, Florida Statutes (1975).

It is clear that the proceedings below were initiated pursuant to the mechanic's lien statute. It is equally apparent that subsequently the parties proceeded to arbitration as required by the contract between them. The fruit of those arbitration proceedings was an award substantially less than that claimed in the lien action initiated by Clarmac. Such arbitration agreements are generally favored by the courts and every reasonable presumption is indulged to uphold the proceedings resulting in an award. Blood v. Shine, 2 Fla. 127 (1848); Knight v. H.S. Equities, Inc., 280 So.2d 456 (Fla. 4th DCA 1973). Nevertheless, procedures do exist for confirming, vacating, or modifying arbitrator's awards. See Sections 682.12, 682.13, and 682.14, Florida Statutes (1975). Provision is also made for the costs of these subsequent court proceedings. Section 682.15, Florida Statutes (1975).

The general rule in Florida is that attorney fees associated with arbitration proceedings are recoverable only by statute or by specific agreement. Codomo v. Emanuel, 91 So.2d 653 (Fla. 1956); Tassinari v. Loyer, 189 So.2d 651 (Fla. 2d DCA 1966); *691 Hartford Accident and Indemnity Co. v. Holton, 190 So.2d 801 (Fla. 1st DCA 1966). In Tassinari we recognized that no statutory authority exists allowing attorney fees in arbitration proceedings. The relevant portion of the Arbitration Code, Section 682.11, Florida Statutes (1975) specifically provides,

"Unless otherwise provided in the agreement or provision for arbitration, the arbitrators' and umpire's expenses and fees, together with other expenses, not including counsel fees, incurred in the conduct of the arbitration, shall be paid as provided for in the award." (emphasis supplied)

In the case sub judice there was no award of attorney fees by the arbitrator nor was there any special agreement between the parties for payment of the same. Therefore, the remaining question is whether some other statute can be invoked to warrant the awarding of attorney fees attributable to the arbitration herein.

Section 713.29 of the Mechanic's Lien Law provides,

"In any action brought to enforce a lien under part I of this chapter, the prevailing party shall be entitled to recover a reasonable fee for the services of his attorney, to be determined by the court, which shall be taxed as part of his costs."

Clarmac asserts that this section authorizes the recovery of attorney fees in this situation. We disagree. Resolution of any conflict between the Arbitration Code, which prohibits attorney fees, and the Mechanic's Lien law, which specifically allows such costs, is determined by the nature of the recovery. Emery v. International Glass & Mfg., Inc., 249 So.2d 496 (Fla. 2d DCA 1971). In Emery, involving the construction of Section 713.29, we stated,

"... [A] claimant is not entitled to attorneys' fees under the section before us, notwithstanding that he ultimately prevails in the case, unless the mode and substance of his recovery is as expressly provided for within the lien law itself." 249 So.2d at 500.

We think it was error for the trial judge to declare a lien in favor of Clarmac since the nature of the recovery was pursuant to the arbitration clause and not the mechanic's lien statute. This conclusion is necessary for several reasons. First, the parties were bound by a general arbitration clause,[1] the purpose and effect of which was to resolve, outside of the court, any disputes arising from the contract.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Village at Dolphin Commerce Center, LLC v. Construction Service Solutions, LLC
143 So. 3d 942 (District Court of Appeal of Florida, 2014)
Rhodes v. Newport Building & Construction, Inc.
86 So. 3d 1245 (District Court of Appeal of Florida, 2012)
ROYAL PALM COLLECTION, INC. v. Lewis
36 So. 3d 168 (District Court of Appeal of Florida, 2010)
Suitt Construction Co. v. 147 Associates
611 So. 2d 1374 (District Court of Appeal of Florida, 1993)
Par Four, Inc. v. Gottlieb
602 So. 2d 689 (District Court of Appeal of Florida, 1992)
Complete Interiors, Inc. v. Behan
558 So. 2d 48 (District Court of Appeal of Florida, 1990)
Fewox v. McMerit Const. Co.
556 So. 2d 419 (District Court of Appeal of Florida, 1989)
St. Paul Fire and Marine Ins. Co. v. Sample
533 So. 2d 1196 (District Court of Appeal of Florida, 1988)
Zac Smith & Co. v. Moonspinner Condo. Ass'n, Inc.
534 So. 2d 739 (District Court of Appeal of Florida, 1988)
Roe v. Amica Mut. Ins. Co.
533 So. 2d 279 (Supreme Court of Florida, 1988)
Hahn v. A. G. Becker Paribas, Inc.
518 N.E.2d 218 (Appellate Court of Illinois, 1987)
CONSOL. LABOR UNION TRUST v. Clark
498 So. 2d 547 (District Court of Appeal of Florida, 1986)
Buena Vista Const. Co. v. Carpenters Local U.
472 So. 2d 1356 (District Court of Appeal of Florida, 1985)
Morrison-Knudsen Co. v. Makahuena Corp.
690 P.2d 1310 (Hawaii Intermediate Court of Appeals, 1984)
Cuevas v. Potamkin Dodge, Inc.
455 So. 2d 398 (District Court of Appeal of Florida, 1984)
Heyman v. Vonelli
413 So. 2d 1254 (District Court of Appeal of Florida, 1982)
Harris v. Dyer
637 P.2d 918 (Oregon Supreme Court, 1981)
McDaniel v. Berhalter
405 So. 2d 1027 (District Court of Appeal of Florida, 1981)
In re Outrigger Club, Inc.
11 B.R. 127 (S.D. Florida, 1981)

Cite This Page — Counsel Stack

Bluebook (online)
339 So. 2d 689, 1976 Fla. App. LEXIS 15647, Counsel Stack Legal Research, https://law.counselstack.com/opinion/beach-resorts-intern-v-clarmac-marine-const-fladistctapp-1976.