B & H Const. & Supply Co., Inc. v. Dist. Bd. of Trustess, Tallahassee Com. College of Fla.

542 So. 2d 382, 1989 WL 32657
CourtDistrict Court of Appeal of Florida
DecidedApril 6, 1989
Docket88-446
StatusPublished
Cited by34 cases

This text of 542 So. 2d 382 (B & H Const. & Supply Co., Inc. v. Dist. Bd. of Trustess, Tallahassee Com. College of Fla.) is published on Counsel Stack Legal Research, covering District Court of Appeal of Florida primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
B & H Const. & Supply Co., Inc. v. Dist. Bd. of Trustess, Tallahassee Com. College of Fla., 542 So. 2d 382, 1989 WL 32657 (Fla. Ct. App. 1989).

Opinion

542 So.2d 382 (1989)

B & H CONSTRUCTION & SUPPLY CO., INC., a Florida Corporation; St. Paul Fire & Marine Insurance Co., a Foreign Corporation, Appellants/Cross Appellees,
v.
The DISTRICT BOARD OF TRUSTEES OF TALLAHASSEE COMMUNITY COLLEGE, FLORIDA, a Public Body Corporate, Appellee/Cross Appellant.

No. 88-446.

District Court of Appeal of Florida, First District.

April 6, 1989.

*384 Julie K. Hilton of Hilton, Hilton, Kolk & Laing, P.A., Panama City, for appellants/cross appellees.

J. Robert McClure, Jr. and Donald E. Hemke of Carlton, Fields, Ward, Emmanuel, Smith & Cutler, P.A., Tallahassee, for appellee/cross appellant.

BARFIELD, Judge.

In this case, B & H Construction and Supply Co., Inc., ("B & H"), appeals from a final judgment which awarded The District Board of Trustees of Tallahassee Community College, ("TCC"), attorney's fees under a construction contract. B & H challenges the propriety of the award and reasonableness of the amount of the award. TCC cross appeals, challenging the trial court's denial of attorney's fees incurred prior to the arbitration demand and subsequent to the arbitration award. TCC also challenges the trial court's refusal to modify the arbitration award, and the trial court's refusal to tax certain costs against B & H. We affirm the final judgment awarding contractual attorney's fees to TCC. We reverse and remand the order denying TCC's attorney's fees incurred subsequent to the arbitration for services rendered in litigating entitlement to the award of attorney's fees. We also remand for clarification of the trial court's order denying costs incurred by TCC for services rendered by its expert who testified as to the amount of reasonable attorney's fees.

I.

In May 1982, B & H contracted with TCC to build the "Lifetime Sports Complex" on the TCC campus. After two years of construction, disputes arose concerning the performance and completion of the project. In March 1986, TCC accepted the project as substantially complete and began preparation for final close-out. By written memorandum, TCC president Dr. James Hinson recommended to the Board of Trustees that it approve final item changes, including contract adjustments, time extensions and liquidated damages. Hinson reported that the balance on the contract was $405,655, and that the contract adjustments totalled $394,296.45.[1] In May 1986, former B & H attorney, J. Michael Huey, responded to Hinson's recommendation with a written offer of settlement for $306,086. TCC counter-offered to settle for $100,000, which B & H rejected.

On July 14, 1986, B & H filed a demand for arbitration under the contract with the American Arbitration Association ("AAA"). B & H had pending other arbitrations with subcontractors on the project and filed a motion to consolidate the TCC arbitrations with the other proceedings.[2] On July 30, 1986, TCC filed an action against B & H and its surety, St. Paul Fire and Marine Insurance Co., seeking a declaratory judgment, an order compelling arbitration, and an order enjoining consolidation with the other arbitration proceedings. B & H filed a counterclaim against TCC and a third party claim against subcontractors Birdair and Francis, to compel arbitration and consolidate all the arbitration proceedings. B & H also filed a motion for a temporary injunction seeking to enjoin the Birdair arbitration proceeding pending resolution of its counterclaim and third party complaint against TCC. In August 1986, the circuit court entered a temporary injunction order prohibiting the consolidation of the arbitration proceedings on the basis of the AAA's refusal to consolidate.

*385 In October, 1986, the circuit court entered a consent order wherein TCC and B & H agreed to arbitrate their dispute independently of the AAA and without joinder of the subcontractors. The circuit court retained jurisdiction over the parties, the subject matter and the arbitration proceeding. A tri-partite panel was picked; TCC selected Mr. William M. Bishop, and B & H selected Mr. A.O. White, as arbitrators; both parties selected retired circuit court Judge Ben C. Willis to serve as umpire. In December 1986, the parties filed specific claims with the panel, TCC requesting $1.7 million in damages, and B & H requesting $1.4 million in damages.

The panel entered its award on February 17, 1987. It determined that the unpaid balance on the contract was $405,655 and found that B & H was responsible for 278 days delay in completing the work, which under the contract amounted to $139,000 in liquidated damages, but denied TCC's claim for loss of revenue and for additional architect fees. The panel found that also TCC breached parts of the contract, including various delays and refusals to approve changes due to unforeseen conditions, which resulted in direct job costs to B & H. However, the panel rejected B & H's claim for attorney's fees as having no basis in contract or statute. The panel awarded B & H a net amount of $377,502.42. The panel ordered each party to bear its own costs, and found that TCC's claim for contractual attorney's fees was a matter for the court to decide.

Both parties filed requests for clarification and modification of the award.[3] Various responses and more motions were filed. In May 1987, the umpire entered an order on the post-award motions, finding that he had to resolve differences between the two arbitrators in that Mr. White had voted to deny all motions to modify the award while Mr. Bishop had concluded that there was some merit to TCC's claim that there was a $9,952.68 discrepancy evident in the award. Mr. White had concluded that the discrepancy was not "an evident miscalculation of figures" but rather that the panel had compromised to resolve early differences between B & H's claim for direct job costs and TCC's claim for architect fees. The umpire concurred with Mr. White and denied all post-award motions (except to correct a clerical mistake).

In June 1987, B & H filed a motion for confirmation of the arbitration award with the circuit court. TCC filed an answer and consolidated motions for post-arbitration award relief, seeking assessment of attorney's fees and costs against B & H, renewing its request for declaratory judgment, and requesting a reduction of the arbitration award based on the alleged $9,952.68 discrepancy. At the hearing on the motions, B & H president Gary Bailey testified that TCC rejected B & H's May 1986 settlement offer of $306,000 and instead counter-offered for $100,000 which Bailey declined.[4] Bailey testified that a day before the arbitration proceedings began, TCC's attorney, Robert McClure, visited the B & H office and offered to settle for $201,000 but Bailey declined that offer too. Bailey denied ever responding to McClure with an offer to settle for $600,000.[5] In regard to specific disputes at the construction site, Bailey testified that in early 1984, B & H officials had advised TCC's architect that there might be a problem with painting the pool at the Sports Complex because of unanticipated moisture build-up. B & H proposed to plaster the pool instead of painting it, and even offered to do it for free, but TCC delayed the decision for two years until January 1986, when the pool was plastered, solving the moisture problem.

*386 In August 1987, the circuit court entered an order confirming the arbitration award. The court found that the following provision of the construction contract authorized attorney's fees:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Dale Echeverria v. Suzanne Trombino, Individually, etc.
District Court of Appeal of Florida, 2024
In re Sagamore Partners, Ltd.
512 B.R. 296 (S.D. Florida, 2014)
Islander Beach Club Condominium v. Skylark
975 So. 2d 1208 (District Court of Appeal of Florida, 2008)
Jeanette Katherine Succar v. Safra National Bank
237 F. App'x 526 (Eleventh Circuit, 2007)
Young v. Midwest Family Mutual Insurance
722 N.W.2d 13 (Nebraska Supreme Court, 2006)
RJ & RK, Inc. v. Spence
855 So. 2d 642 (District Court of Appeal of Florida, 2003)
Rock v. Prairie Bldg. Solutions, Inc.
854 So. 2d 722 (District Court of Appeal of Florida, 2003)
Frankenmuth Mutual Insurance v. Escambia County
289 F.3d 723 (Eleventh Circuit, 2002)
Scottsdale Ins. Co. v. Haynes
793 So. 2d 1006 (District Court of Appeal of Florida, 2001)
CENTEX-ROONEY CONST. CO. v. Martin County
725 So. 2d 1255 (District Court of Appeal of Florida, 1999)
Hartleb v. STATE, DEPT. OF TRANSP.
711 So. 2d 228 (District Court of Appeal of Florida, 1998)
H & S CORP. v. US Fidelity & Guar. Co.
667 So. 2d 393 (District Court of Appeal of Florida, 1995)
Loney v. MHA v. Aetna
D. New Hampshire, 1995
Baker Protective Services v. FP INC.
659 So. 2d 1120 (District Court of Appeal of Florida, 1995)

Cite This Page — Counsel Stack

Bluebook (online)
542 So. 2d 382, 1989 WL 32657, Counsel Stack Legal Research, https://law.counselstack.com/opinion/b-h-const-supply-co-inc-v-dist-bd-of-trustess-tallahassee-com-fladistctapp-1989.