Loney v. MHA v. Aetna

District Court, D. New Hampshire·Decided August 18, 1995·No. CV-92-461-B·Published

Opinion

Loney v. MHA v. Aetna CV-92-461-B 08/18/95 UNITED STATES DISTRICT COURT FOR THE DISTRICT OF NEW HAMPSHIRE

H. Loney Construction Co., Inc.

v.

Manchester Housing and Redevelopment Authority v. Civil No. 92-461-B Aetna Casualty and Surety Corporation

O R D E R

Manchester Housing and Redevelopment Authority ("MHRA")

moves for summary judgment on its claim for attorney's fees pursuant to a performance bond. Specifically, MHRA argues that it is entitled to the costs associated with defending against H. Loney Construction's claims for extra compensation due to a differing site condition because those costs resulted from honey's breach of the conditions of the bond. Defendants, Loney and Aetna Casualty and Surety Company, object to MHRA's motion and also move to have the claim for attorney's fees dismissed because of unfair prejudice. For the following reasons, I deny MHRA's motion for summary judgment and also deny the defendants' motion to dismiss.

I. BACKGROUND

A. The Renovation Proiect MHRA awarded a construction contract to Loney, a general contractor, that included heating renovations and the construction of new boiler rooms in several of MHRA's properties.

The buildings were constructed by MHRA in the early 1950's. The design of the buildings included a central heating system with lines running underground to each building. None of the buildings were constructed with basements. Instead, each building had a small crawl space under the first floor surrounded by a poured concrete foundation. MHRA experienced water problems in the crawl spaces between 1968 and 1972. It installed several sump pumps in the buildings in order to correct the problem. In 1988, MHRA decided to renovate the heating systems in these buildings.

The design for the renovations called for the construction of a boiler room in each building by excavating in the crawl space and constructing the boiler room in that space. In 1989, MHRA invited bids for the project. The bid documents reguired the excavation in the crawl space and the placement of sump pumps in each excavated boiler room below the floor slab to pump out water. The bid documents also provided that each bidder "assumed responsibility for all dewatering [sic] and shoring during construction of the project." B. The Contract and Performance Bond MHRA awarded Loney the project and the parties executed a contract which included general conditions, specific conditions.

specifications, and drawings. The contract required the contractor to furnish all labor, materials, equipment, and services, and perform all the work required for the renovations as contained in the bid documents. The contract was based on a lump sum fee.1 Further, the contract required the contractor to provide "all necessary protection and pumping work required to keep the excavated area free of water."

In addition, the contract required Loney as principal, and Aetna as surety, to execute a performance bond for the benefit of MHRA, the sole obligee, binding them to perform all obligations under the contract. The performance bond provided that Loney and Aetna were obligated to MHRA in the amount of $1,545,666.00, the contract price. Further, it stated that this obligation would be void if the principal satisfied the conditions of the bond. Specifically, it stated: "if [the principal] ... shall well and

1Lump sum contracts stipulate a sum for the entire cost of meeting the requirements of the contract. Any overruns are born by the contractor unless they fall within the equitable adjustments provision of the contract or some other exception.

Article 2 of the contract states in pertinent part:

Article 2 . The Contract Price. [MHRA] shall pay the Contractor [Loney] for the performance on the Contract, in current funds, subject to additions and deductions as provided in the Specifications, the sum of One Million Five Hundred Forty-Five Thousand Six Hundred Sixty-Six and 00/100 Dollars ($1,545,666.00).

truly indemnify and save harmless said Manchester Housing Authority against all counsel fees paid or incurred by said Authority as a result of a breach of any condition of this bond, . .. , then this obligation shall be void ... ."2 In addition, the bond provided that if the principal performed all agreements, terms, and conditions of the underlying contract, then the obligation to pay MHRA the contract price would also be void.

2This portion of the performance bond states in its entirety:

NOW, THE CONDITION of this obligation is such that if the same principal and his subcontractors shall well and truly keep and perform all agreements, terms and conditions in said contract set forth and specified to be by said principal kept and performed, and shall well and truly indemnify and save harmless said Manchester Housing Authority against all counsel fees as a result of a breach of any condition of this bond, and against all claims and suits for damage to person or property arising from carelessness or want of due care or any act or omission on the part of said principal during the performance of said contract, then this obligation shall be void; otherwise it shall remain in full force and virtue.

The performance bond itself consists of a one page, standard form, obligating Aetna and Loney to MHRA for the full contract price. In addition, the bond reguires Aetna, upon MHRA's written reguest, to complete the contract if Loney abandons the contract or MHRA terminates the contract.

C. The Ground Water Problem and Lonev's Claim for Extra Compensation

In the course of excavating for the new foundations, Loney encountered seepage problems as a result of surface and groundwater in the area. Contrary to MHRA's suggestions, Loney did not employ a pump or berm around the excavation to alleviate the problem. Instead, it used different methods and incurred additional costs and delays due to the groundwater. Subseguently, Loney informed MHRA that, pursuant to the differing site conditions and eguitable adjustment clause of the contract, it was seeking to have each excavation done on a time and materials basis because of the differing conditions that would be encountered with respect to each excavation. MHRA refused to make any payments to Loney for the additional costs incurred.

Loney then sued MHRA to recover the costs claiming that the expenses incurred were not part of the original contract and therefore they were entitled to an eguitable adjustment. MHRA raised several defenses and counterclaimed for breach of warranty with respect to the installation of the boilers and failure to complete the work specified in the contract. Specifically, MHRA asserted that Loney was obligated under the contract to handle any groundwater problems and any extra cost incurred by Loney

resulted from their failure to address the problems in a workmanlike manner as required by the contract. In its counterclaim, MHRA sought to recover damages plus costs and attorney's fees.3 In addition, MHRA unsuccessfully sought to have Aetna impleaded as a necessary party.

The suit was bifurcated so that the issue of MHRA's liability for the extra costs due to differing site conditions was adjudicated first. After a three-day bench trial, Loney was unsuccessful in proving that it was entitled to an equitable adjustment.4 The sole issue at trial was whether the contract provided for the contractor to be responsible for any

Free access — add to your briefcase to read the full text and ask questions with AI

Loney v. MHA v. Aetna, (D.N.H. 1995).

Loney v. MHA v. Aetna (Loney v. MHA v. Aetna) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Mason v. City of Albertville
158 So. 2d 924 (Supreme Court of Alabama, 1963)
Turner Construction, Inc. v. American States Insurance
579 A.2d 915 (Supreme Court of Pennsylvania, 1990)
Tentindo v. Locke Lake Colony Ass'n
419 A.2d 1097 (Supreme Court of New Hampshire, 1980)
Logic Associates, Inc. v. Time Share Corp.
474 A.2d 1006 (Supreme Court of New Hampshire, 1984)
R. Zoppo Co. v. City of Dover
475 A.2d 12 (Supreme Court of New Hampshire, 1984)
Maguire v. Merrimack Mutual Insurance
573 A.2d 451 (Supreme Court of New Hampshire, 1990)
Parkhurst v. Gibson
573 A.2d 454 (Supreme Court of New Hampshire, 1990)
Gamble v. University System
610 A.2d 357 (Supreme Court of New Hampshire, 1992)
Smith v. Town of Wolfeboro
615 A.2d 1252 (Supreme Court of New Hampshire, 1992)