H & S CORP. v. US Fidelity & Guar. Co.

667 So. 2d 393, 1995 WL 746381
CourtDistrict Court of Appeal of Florida
DecidedDecember 19, 1995
Docket92-2403, 92-2891
StatusPublished
Cited by10 cases

This text of 667 So. 2d 393 (H & S CORP. v. US Fidelity & Guar. Co.) is published on Counsel Stack Legal Research, covering District Court of Appeal of Florida primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
H & S CORP. v. US Fidelity & Guar. Co., 667 So. 2d 393, 1995 WL 746381 (Fla. Ct. App. 1995).

Opinion

667 So.2d 393 (1995)

H & S CORPORATION, a foreign corporation, and Fidelity & Deposit Company of Maryland, a foreign insurance corporation, Appellants/Cross-Appellees,
v.
UNITED STATES FIDELITY & GUARANTY COMPANY, Appellee/Cross-Appellant.
H & S CORPORATION, a foreign corporation, Appellant,
v.
JONES, EDMUNDS & ASSOCIATES, INC., Appellee.

Nos. 92-2403, 92-2891.

District Court of Appeal of Florida, First District.

December 19, 1995.

*395 Gregory A. Giordano of Shuttleworth, Ruloff, Giordano & Kahle, Virginia Beach, Virginia; William Avera, Gainesville, for Appellant/Cross-Appellee/H & S Corporation.

Steven George Schember of Schumaker, Loop & Kendrick, Tampa; Marguerite H. Davis, John C. Lovett, Alan Harrison Brents, *396 and Daniel C. Brown of Katz, Kutter, Haigler, Alderman, Davis & Marks, P.A., Tallahassee, for Appellant/Cross-Appellee/Fidelity.

Allan P. Clark and John A. Tucker of Foley & Lardner, Jacksonville, for Appellee/Cross-Appellant/USF & G.

Jack W. Shaw, Jr., of Osborne, McNatt, Shaw, O'Hara, Brown & Obringer, P.A., Jacksonville, for Appellee/Jones, Edmunds & Associates.

MINER, Judge.

These appeals present numerous issues arising from complex, multi-party litigation which was generated by the construction of a waste water collection system in Cross City, Florida. The record before us is massive — over 26,000 pages and 160 volumes. The bench trial alone produced nearly 6,000 pages of transcript. In resolving the issues on appeal, we have found no need to recite all the operative facts surrounding the several disputes in exacting detail but instead believe that a short synopsis will suffice.

Briefly, the original contractor on the project was terminated due to unsatisfactory performance, leaving its exposed surety, United States Fidelity & Guaranty Insurance Co. (USF & G) to engage another contractor as a "completing contractor". USF & G entered into a contract with H & S Corporation (H & S) to complete the work on the system. Subsequently, problems arose with H & S' performance leading to its default. Thereafter, USF & G asserted claims against H & S and H & S' surety, Fidelity & Deposit Company of Maryland (Fidelity) and H & S asserted counter claims against USF & G. H & S also sued the project engineer, Jones, Edmunds & Associates (JEA) for allegedly misrepresenting details concerning the project site and the nature of the work to be performed. The two cases were consolidated for a bench trial but the trial court issued separate final orders.

Procedurally, H & S is the appellant in both cases before this court but is joined by its surety, Fidelity, in case # 92-2403. That case contains most of the issues before us for resolution and arises from the USF & G v. H & S/Fidelity action below. Case # 92-2891 arises from the H & S v. JEA action below and while it presents only two issues to be resolved, it is part of the same complex fact situation found in case # 92-2403. In this court, the two cases were consolidated for record and oral argument purposes.

After considering the briefs filed in these two cases and hearing oral argument of counsel and after a painstaking review of the voluminous record on appeal, we conclude, as follows:

Case No. 92-2891

Appellant, H & S, as "completing contractor" argued below that the project engineer, JEA, misrepresented details concerning the project site and the nature of the work to be performed at the site. The trial court found that JEA was not liable to H & S for a changed site claim and further, concluded that JEA was not liable to H & S on a negligent misrepresentation theory. We find no basis in the record to overturn those findings and affirm as to these points.

Evidence established that H & S representatives viewed the jobsite prior to bidding and were able to observe high ground water and subsurface rock that had been partially excavated. H & S' project manager informed USF & G at that time that he did not believe the original report regarding subsurface rock formations and water table levels, to which H & S had access, accurately depicted the prebidding inspection condition of the jobsite. Accordingly, the earlier report could not reasonably have been relied upon and, in fact, was not relied upon by H & S in making its bid.

Based upon the evidence at trial, the trial court properly rejected H & S' negligent misrepresentation claim against JEA. What H & S denominated as "misrepresentations" were, in our view, not misrepresentations at all. The record establishes that the earlier soil/rock/water table testing report was not false or misleading concerning the conditions present at the construction site in the area where the test borings were taken at the time they were taken. H & S was cautioned not to rely on this earlier test *397 data. As did the trial court below, we likewise find no misrepresentation concerning JEA's authority to test H & S work prior to authorizing payment. Such prospect was clearly set out in H & S' contract with USF & G. Finally, it was a matter of opinion rather than a misrepresentation concerning the extent of the latent defect work which needed to be done to remedy the shortcomings in the original contractor's work. By contract definition, latent defect work was "not discoverable in the exercise of reasonable diligence by persons possessing customary knowledge in the type of construction which is the subject of this Agreement."

Case No. 92-2403

Although all of the parties refer to the same basic facts, it is apparent to us from the briefs and oral argument that no single party is concerned with every issue raised on appeal in this case. For orderliness of presentation, we have regrouped the issues presented into three categories: (1) the issues raised by H & S and Fidelity; (2) separate "surety" issues raised by Fidelity, and (3) USF & G's cross appeal.

H & S/Fidelity Issues

H & S and Fidelity first maintain that the trial court erred in ruling that H & S materially breached its contract with USF & G. It was USF & G, they argue, that breached the contract prior to H & S' quitting the jobsite in May of 1987. Specifically, H & S claims that the requirement of testing H & S work before payment and the imposition by USF & G of a "pay when paid"[1] condition, constituted unauthorized changes in payment terms that justified H & S's walking off the job. On the record before us, we find that the trial court did not err in this ruling.

As we noted above in connection with Case No. 92-2891, testing is provided for in the contract between the parties. The specifics of such testing are explained in the contract's mechanical specifications. Although the "test before payment" condition was authorized by the contract and had been imposed upon the original defaulting contractor, this condition was not initially imposed upon H & S. It was only invoked in late October of 1986 when it became apparent to project engineers that H & S workmanship was substandard. The contract also required that partial payment requests be submitted to the engineer for approval, which approval could be withheld if the work was non-conforming.

Our review of the record does not indicate that H & S ever objected to the "testing before payment" specification.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cohen & Cohen, P.A. v. Gerson, Preston, Robinson & Co., P.A.
24 So. 3d 805 (District Court of Appeal of Florida, 2010)
Capitol Environmental Services, Inc. v. Earth Tech, Inc.
25 So. 3d 593 (District Court of Appeal of Florida, 2009)
Federal Insurance v. American Home Assurance Co.
664 F. Supp. 2d 397 (S.D. New York, 2009)
Bryan v. City of Cotter
2009 Ark. 457 (Supreme Court of Arkansas, 2009)
Coin-O-Matic, Inc. v. Cornerstone Residential Management, Inc.
879 So. 2d 649 (District Court of Appeal of Florida, 2004)
Glover Distributing Co., Inc. v. FTDK, INC.
816 So. 2d 1207 (District Court of Appeal of Florida, 2002)
FIRST FEDERAL SAV. AND LOAN v. Bezotte
740 So. 2d 589 (District Court of Appeal of Florida, 1999)
Davis v. Kaminsky
734 So. 2d 476 (District Court of Appeal of Florida, 1999)
Pat Martens Custom Homes Co. v. Landsteiner
711 So. 2d 1338 (District Court of Appeal of Florida, 1998)
Underhill Fancy Veal, Inc. v. Padot
677 So. 2d 1378 (District Court of Appeal of Florida, 1996)

Cite This Page — Counsel Stack

Bluebook (online)
667 So. 2d 393, 1995 WL 746381, Counsel Stack Legal Research, https://law.counselstack.com/opinion/h-s-corp-v-us-fidelity-guar-co-fladistctapp-1995.