Harris v. Dyer

637 P.2d 918, 292 Or. 233, 1981 Ore. LEXIS 1185
CourtOregon Supreme Court
DecidedDecember 22, 1981
DocketTC 78-1378-E-3 CA 17650 SC 27670
StatusPublished
Cited by13 cases

This text of 637 P.2d 918 (Harris v. Dyer) is published on Counsel Stack Legal Research, covering Oregon Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Harris v. Dyer, 637 P.2d 918, 292 Or. 233, 1981 Ore. LEXIS 1185 (Or. 1981).

Opinions

[235]*235LINDE, J.

A dispute between the parties to a construction contract led the owner to terminate the contract. The construction contractor demanded the amount he claimed to be owing under the contract, and upon the owner’s refusal to pay, the contractor filed a claim of lien, followed by a suit to foreclose the lien. As the contract provided for arbitration, the circuit court abated the proceeding pending arbitration.1 The arbitrators awarded the contractor $64,089.71 plus interest. The contractor then moved for a decree foreclosing the lien in a total amount comprising the arbitrators’ award, interest, lien preparation and recording fees, court costs, and reasonable attorney fees incurred in the arbitration as well as in the judicial proceeding. Defendant, the owner, tendered the amount of the award, with interest, and when plaintiff rejected this tender as insufficient, the circuit court dismissed the foreclosure suit on defendant’s motion.

The Court of Appeals reversed the dismissal, holding that an arbitration provision alone does not waive the contractor’s right to file a construction lien to secure eventual payment of his claim, and that plaintiff was entitled to have judgment in the foreclosure suit for all items included in the arbitration award that were properly covered by the lien. The court also held that plaintiff was entitled to costs and attorney fees related to the filing of the lien and the foreclosure proceeding, but excluding attorney fees incurred in the arbitration, and it remanded the case to the circuit court for determination of the proper amount of the judgment. 50 Or App 223, 623 P2d 662 (1981). The only issue before us on review is whether plaintiff is entitled to reasonable attorney fees incurred in arbitrating the amount of his claim.

[236]*236 Plaintiff relies on statutory grounds and on the arbitration provision of the construction contract for his right to recover attorney fees for the arbitration. The construction lien law directs that in suits to enforce a lien “the court shall allow as a part of the costs a reasonable amount as attorney fees to the prevailing party.” ORS 87.060(4).2 Plaintiff argues that the larger part of attorney fees in foreclosing a disputed construction lien arises not in filing the lien claims and the complaint but in litigating the amount of the claim, and that such fees should be recovered even if this phase of the dispute occurs before arbitrators rather than in court.3 Insofar as this part of an attorney’s time and effort would be expended in court and recoverable as part of costs if it were not transferred into the arbitration tribunal, plaintiffs argument is not unreasonable. On the other side, it may be said that arbitration is not imposed by law as a phase of litigation, but is chosen by the parties precisely as an alternative to litigation, on terms set by the parties themselves. Indeed, if the dispute had been arbitrated according to the contract without reaching any occasion to invoke the lien law, the costs of arbitration would be governed by the contract, and plaintiff could not invoke ORS 87.060(4), supra, to recover attorney fees. We doubt that when that section speaks of attorney fees to the “prevailing party” as a part of “costs” in a lien foreclosure proceeding, it means to include more than the statutory procedures themselves, or that it means to invite foreclosure suits as a step toward obtaining attorney [237]*237fees for an arbitration under a contract that does not provide for such fees. Cf. Beach Resorts Intern. v. Clarmac Marine Const., 339 So2d 689 (Fla App 1976), Oakdale Park Ltd. v. Byrd, 346 So2d 648 (Fla App 1977).

Plaintiffs second argument, however, is that this contract did preserve for the parties such rights to attorney fees as the parties would have had in the absence of the arbitration clause. The contract was a standard form construction contract published by the American Institute of Architects. Two provisions are relevant to the present issue.

The arbitration article begins:

“7.9.1. All claims, disputes and other matters in question between the Contractor and the Owner arising out of, or relating to, the Contract Documents or the breach thereof * * * shall be decided by arbitration in accordance with the Construction Industry Arbitration Rules of the American Arbitration Association then obtaining unless the parties mutually agree otherwise. * * * The foregoing agreement to arbitrate shall be specifically enforceable under the prevailing arbitration law. The award rendered by the arbitrators shall be final, and judgment may be entered upon it in accordance with applicable law in any court having jurisdiction thereof.”

Nothing in the record elucidates the reference to the “Construction Industry Arbitration Rules of the American Arbitration Association,” and there is no evidence that either contracting party knew what they were. The arbitrators’ award ordered that the association’s fees and expenses and those of the arbitrators be borne equally by the parties, but there is no suggestion that either the arbitration rules or the award covered attorney fees.

Plaintiff contends that when the last sentence of art. 7.9.1., supra, refers to entry of judgment on the award “in accordance with applicable law,” the “applicable law” includes the attorney fee provision of the lien law and thereby also includes attorney fees for the arbitration. Assuming plaintiffs premise that “applicable law” in art. 7.9.1 includes more than the “prevailing arbitration law” mentioned in the preceding sentence, nevertheless this clause only provides for the entry of judgment upon the award itself. It says nothing about attorney fees which the “applicable law” allows for the enforcement of a lien.

[238]*238Plaintiff has a stronger argument under a general provision of the contract. Article 7.6.1. provides:

“The duties and obligations imposed by the Contract Documents and the rights and remedies available thereunder shall be in addition to and not a limitation of any duties, obligations, rights and remedies otherwise imposed or available by law.”

The question is what “duties, obligations, rights and remedies” are reserved by this clause.

The record does not offer any explanatory material bearing on the intended meaning and scope of art. 7.6.1. of the standard form contract. We disregard “duties and obligations” as referring most likely to the substantive performance required of the respective parties. Their “rights and remedies” clearly extend to the contingency of nonperformance. One of the standard remedies that must have been contemplated in this provision is the security of a construction lien and its eventual foreclosure, a procedure which in Oregon gives the prevailing party a right to attorney fees. The lower courts held that, despite art. 7.6.1., lien foreclosure had to await the result of arbitration under the contract. Had the dispute ended with the award, or with its enforcement under the arbitration statute, there would be no right to attorney fees for art. 7.6.1. to reserve. Cf. Oakdale Park Ltd. v. Byrd, supra.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

L. H. Morris Electric, Inc. v. Hyundai Semiconductor America, Inc.
125 P.3d 1 (Court of Appeals of Oregon, 2005)
CVN Group, Inc. v. Delgado
95 S.W.3d 234 (Texas Supreme Court, 2002)
Westwood Construction Co. v. Hallmark Inns & Resorts, Inc.
50 P.3d 238 (Court of Appeals of Oregon, 2002)
Stiglich Construction, Inc. v. Larson
621 N.W.2d 801 (Court of Appeals of Minnesota, 2001)
ASB CONSTRUCTION v. Bateman
863 P.2d 516 (Court of Appeals of Oregon, 1993)
P & C Construction Co. v. American Diversified/Wells Park II
789 P.2d 688 (Court of Appeals of Oregon, 1990)
Sentry Engineering & Construction, Inc. v. Mariner's Cay Development Corp.
338 S.E.2d 631 (Supreme Court of South Carolina, 1985)
Morrison-Knudsen Co. v. Makahuena Corp.
690 P.2d 1310 (Hawaii Intermediate Court of Appeals, 1984)
Cuevas v. Potamkin Dodge, Inc.
455 So. 2d 398 (District Court of Appeal of Florida, 1984)
Wills v. Boise Cascade Corp.
650 P.2d 109 (Court of Appeals of Oregon, 1982)
Harris v. Dyer
637 P.2d 918 (Oregon Supreme Court, 1981)

Cite This Page — Counsel Stack

Bluebook (online)
637 P.2d 918, 292 Or. 233, 1981 Ore. LEXIS 1185, Counsel Stack Legal Research, https://law.counselstack.com/opinion/harris-v-dyer-or-1981.